Friday 28 January 2011

Risk Management in Low-Income Housing Project Development in Ho Chi Minh City

Ho Chi Minh City (HCMC) is the one of the cities having highest population in Vietnam. Currently, migrants account for 21 percent of total population, and the average migration rate increases from 0.02% (1979-1989) to 0.84 (1989-1999) and reaches 2.33% (1999-2004) (Thanh, 2006). Most of people migrate to HCMC in order to get better employment opportunity, education condition, medical care, and so on (Thanh, 2006).

In order to increase housing supply for the poor, government has implemented different policies in various periods. However, housing supply for the poor is still low compared to demand. This market segment is still risky for developer (MOC, 2009).

Mr. Le Quoc Tuan made a case study which main objective was to propose the possible solution to manage the risks in low-income housing (LIH) project development. In order to achieve his main objective, the following objectives were needed to accomplish: (1) investigate the risk factors in each project phase during the implementation low-income housing project development, and (2) propose the recommendation to manage the risk factors in low-income housing project development.

Conclusion

In order to satisfy the first objective, the researcher reviewed book, journal, previous thesis, guideline, newspaper and so on to identify risk factors and then arranged them in four phases of project which are planning, financing, construction, and selling. After that, these risk factors were verified by 5 experts including deputy directors, government officials, and academician. Finally, the verified risk factors were analyzed through case study. The second objective, which was recommendation to manage risks, was made based on analysis case study and study literature.

It was found out that there are eight key risks for developer when investing in low-income housing project which are (1) complicated legislation procedure to get approval (2) low-profit margin controlled by government (3) unrealistic government support policy (4) risk in land acquisition from landowner (5) lack of fund to developers (6) inappropriate building standard (7) revenue risk due to ineffective demand (8) delay in selling housing unit.

Recommendation

The recommendations were made based on the risk analyses, suggestions from interviewees, and from literature review. The recommendations are presented as in the table below.

His thesis abstract is copied and posted

Abstract

Demand on low-cost housing for the poor in urban area of Vietnam is very high due to its high population, and high urbanization rate. Even though Government implemented many policies since 2009 in order to attract developers, the supply in low-income housing is still low compared to its demand. So far only 31 out of 263 registered low-income housing projects have been implementing. According to Ministry of Construction (2009), this market segment is still risky for developers. However, there are few researches on risk management specific in low-income housing projects. The purpose of this study is to propose recommendation to manage risks in low-income housing project development in Ho Chi Minh City.

This study used case study to conduct its two objectives. The first objective is to investigate risk factors in each phase of low-cost housing development. Researcher reviewed book, journal, previous thesis, guideline, newspaper and so on to identify 48 risk factors and then arranged them in four phases of project which are planning, financing, construction, and selling. After that, these risk factors were verified by 5 experts including deputy directors, government officials, and academician. Finally, the twelve verified risk factors will be analyzed through case study in Ho Chi Minh City. The second objective is to make recommendation to manage risks. The recommendation was made based on analysis of case study and study of literature.

The study found that developers are facing 8 risk factors and 12 risk sub-factors which are (1) complicated legislation procedure to get approval (2) low-profit margin controlled by government (3) unrealistic government support policy (4) risk in acquisition of land from landowner (5) lack of fund to developers (6) inappropriate building standard (7) revenue risk due to ineffective demand (8) delay in selling housing unit. Some recommendations to manage the risk are: (1) establish one independent government agency responsible for legislation issues, land acquisition, select the target low-income people, and guarantee for the output (3) government channels the fund borrowed from international agency such as World Bank, Asian Development Bank to developers with favorable interest rate or government guarantee for developers to borrow fund from bank (4) lower building standard.

Thursday 27 January 2011

Risk Management in the Design of Large - Scale Construction Projects: Case Studies of an Urban Area and a High-rise Building Project

Problems in the design of large-scale construction projects may come from many stakeholders: Owner, Designer, Project Management Consultant and external environment.

There are many kinds of problem arising from the Owner such as (i) sometimes they can’t finalize what they really expect in their project. The requirements are very vague and just base on their feeling; (ii) the structure is not well-organized. Everybody can give out opinions but no one makes decision; (iii) when employing the consultants, owners don’t have the right model of project team structure. The consultants are not put in the right position with proper scope of works and obligation.

The problems of Project Management Consultant are that sometimes they can’t fulfill their duty in assisting Client to conclude their requirements reasonably and to arrange the project team structure in a right way or can’t define the procedure of working and making decisions. Also, they can’t well manage the project team to shorten the time, eliminate the error, and reduce the cost. The project working environment is not efficient and effective because people in the team are not aware of the other member’s duties or how to contact them. In other words, many Project Managers in Viet Nam nowadays are just the Post Men.

As to Designer, most of their problems come from the unclear design contract without necessary conditions binding relevant parties to their commitment. This weak point becomes more serious especially to the large projects owned by many organizations and involve in many parties with different cultures, different customs and constructive understanding.

Last but not least, problems may emerge from the external environment, such as laws, regulations or market. These factors form an uncertain circumstance which needs to be well identified, and planned the measures to deal with.

Mr. Do Tran My Thuy made a case study which objectives were to: (1) identify the key risks affecting time, cost or quality during design process; (2) find out how to mitigate these risks through contract conditions, communication or some other management tools. Also, to define the role, responsibility of three parties: Owner, Project Management Consultant and Designer in mitigating these risks; and (3) identify the activities and required documents in each step of Design process.

Conclusion

In the design of large-scale projects which involved many investors and many professors in different fields, there are usually 12 risks relating to 3 groups of stakeholders such as Owners, Project team and external environment. Two among these risks are from the external environments which are “unpredictable response from Authorities” and “changes by unforeseeable causes”. These are difficult to be prevented, so the mitigation is just the negotiation between Owner and Designer on how to share the consequences if the risks happen. Ten reminders can be prevented or mitigated through a proper working process and three kinds of document.
A proper working process is the one which creates the reliable bases for the Owner to make proper decisions.

Three kinds of document are Design service contract, Design Brief and Project Management Plan. The purpose of these documents is to set out a clear, impartial working environment for all parties in the project. Depending on the specific situation of the project, each document can be amended a little bit, but there are some critical issues in these documents which are necessary to be considered and discussed carefully by the Owner, Designer and Project Management Consultant. The role and responsibility of these three parties during the design process are also found. Details of the finding are summarized in figure 4-1. Apart from these preparations, another tool to mitigate the risk is Communication. Communication should also be planned through three aspects: communication method, communication form and critical points to communicate.


Recommendation

The Project Manager should consider the steps shown in the table to prepare for large-scale construction projects.


His thesis abstract is copied and posted.

Abstract

Managing risks in construction project has been recognized as one of the key factors in the process leading to the success in term of time, cost and quality of a project. However, until now most researches in risk management have focused on the construction phase, rather than design phase. This paper aims to identify the risks in the design of large-scale construction projects and find out how to mitigate these risks. Through the two case studies in two different types of projects (one Urban Area project and one Building project), twelve risks are identified and risk mitigation are proposed. It is concluded that to mitigate these risks, the Project Manager should pay attention in several issues. Firstly, the Pre-design phase at the beginning of each project can not be omitted. This important phase results in a Design Brief and Project Management Plan which together with the Design Service contract made stronger commitments of parties. Secondly, FIDIC- white book which is usually used as the standard form in Architectural Design practice in Viet Nam nowadays needs to be added or amended some conditions. Lastly, communication also needs to be planned and implemented in a right way.

Tuesday 25 January 2011

Claim Management And Analysis: A Case Study Of High Rise Building Project

Normally, the success of construction claim management is the satisfaction of all parties involved in the project. This success must be started from the preparation of each claim such as entitlement, cost and documentation.

Normally, there are two parts of each entitlement for each claim. The first one must set up the legal / law as well as other data base on which normally extracted from the construction contract document. In case there are conflicts, the entitlement must be separated into many branches so that they can be understood easily in a logical express. The second one must describe the variation of the work and express the action of the contractor to each change, especially in quantity and quality.

The cost section is normally based on the available cost in the signed contract. The costs of each work must be considered carefully because they can affect the relationship between each party. In the contract, cost is always limited such as “can not be changed in case the total variation is smaller than 0.2% of contract amount for example”, etc. It is necessary to breakdown and explain the party how the cost is developed in this section.

Documentation seems to be the most important for the success of a construction claim. Generally, all the documents which involve to the claim such as variation order, drawings, contract, specification, etc must be included in this section. Project manager, site manager, engineers, consultant, lawyers and others are always involve supporting for the full success of this documentation.

Base on the above analysis, expert can pick out the weak points and strong points of each company for claim management and they can improve them. The guidelines below would be helpful to companies to improve their claim management :
• The project design and handling must be integrated in claim management
• Make the tight communication inside your company about the claim situations
• Prepare and check carefully the documentation which will support for the claim
• Reviewing all signed contract to check if they are feasible contracts or not
• Have an expert in making decision for the strategic claim

The following normally are the most related potential problems which affect the project entitlement, cost and document in construction claim:
• Scope definition is incomplete and inadequate
• Lack of integrating and understanding of each scope of work
• Not tight contract document
• Not enough condition from the client to support the contractor to execute the work
• Catch up the schedule by accelerating
• Acceleration of contractor without submitting claim to the client
• Delays
• Changes in work because of imperfect contract drawings lead to the disruption

According to Keith Pickavance (2008), “Poor quality of project documentation leads to poor factual evidence and present serious difficulties in identifying the rights of the parties.”

Lack of communication normally leads to the delay of the project and also shows that the project management is bad.

Mr. Giang Thien Duy Nguyen made a case study which objectives were to: (1) study claims in high rise building construction progress; (2) study what analysis method is used for claim; and (3) study the prepare effective claim analysis frame work.

Conclusions

In this study, the framework on claim analysis is designed. This study helped the claimant understand clearly about the claim documentation, the way to prepare a claim, the method to calculate the quantity – cost - profit – overhead, etc. The design documents are the most important thing during construction progress. The fewer the errors, the fewer the missing information, therefore fewer claims. So, the Client just should sign consultant contract with a very experienced Project Management company.

Furthermore, the Contractor’s ability is also very important. Their experience will help the Project Management foresee what would be the errors, and what information should be adjusted instantly. Their experience will both PM and Client to reduce the cost of the project by properly proposing method statement as well as cheaper but good quality material.

Recommendations

• In general, a tight contract such as the signed contract of the above project seems to be unfair with the contractor because of the clause “Contractors have to arrange and execute themselves to complete the project, no claim of weather condition be admitted by the PM, by the Client”, because in fact, contractor can not complete their mission if the weather condition is of disadvantage.

• Claim framework as well as procedure of claim approval should be applied but not in all cases. It’s up to each project character, it’s up to the relationship between the Client, the PM and the Contractor. Personally, the applied solution of the above project (using “technical meeting book”) is highly appreciated. This solution helps all parties speed up the schedule and everything can be solved quickly and fairly.

• Any how, the documentation, the factual support for the claim, etc should be prepared carefully so that every parties can review those easily and also for easy contract liquidation later.

• Careful preparation of all related document will help parties to avoid disputes.

• The level of project manager of the Client, and of the Project management is also very important. Their experience will help all the claims if any, be solved and be approved without disputes.

• Once again, a successful project is a project which brings benefit to all parties involve in the project. Therefore, before the problem starts, all parties must try their best to solve them first.

His thesis abstract is copied and posted.

Abstract

High rise project budget increased, project delayed in construction can be caused by a number of changes in a project such as scope change, extra work, lost productivity, acceleration, contract termination, etc. Many factors by many parties cause those matters. However, in general, cost & schedule control are really complicate. Non-critical activity does not make the affect to the project schedule, does not make the delay, and does not impact to the project amount. On contrary, the delay of a critical activity will make the project delay and impact the project amount also. The delay caused by critical activity will cause the damage to other parties. The reason of delay does not origin from any party but origin from no party (e.g. bad weather conditions). Base on those factors, each party can claim each other to protect the right of them. So, for a high rise building project, what should we do with a claim, when will we claim, how claim can be calculated, etc, that is main content of this case study.

Friday 21 January 2011

A Critical Appraisal Of Client Briefing Process In Construction: A Case Study Of Residential Project

Briefing is a communication process combined with record system to publish a set of documents to the design team. It is a process of developing a deep understanding about the client's needs, and it is a continuous interaction and involvement of the client where in this process, the role of professional team is very important. Through good briefing and grasping what the real needs are, client and professional consultants can work more effectively and productively on project and make decisions confidently.

Since Vietnam’s construction industry is attracting investors impressively by the possibility of its profitability, therefore, the development of strategies for international construction demands is very essential to meet the client’s objectives in terms of function, quality, value, time, and cost certainly. In contrary, Vietnam’s big problem is the lacking of skilled person to meet the requirement of construction project which lead to late delivery and over budget. Oftentimes, requirements and demands from clients are not collected adequately to provide solutions and the result is inappropriate.

Ms. Nguyen Chau Dieu An made a case study which objectives were to: (1) review the concepts, definitions of client and client briefing in construction in order to understand the client’s expectation through the client’s briefing process; (2) review the methods for strategic client briefing and other relevant literature on client briefing; (3) present the problems of briefing in a specific project in Vietnam and its solutions; and (4) propose a framework of briefing for next project.

Conclusions

Briefing has long been recognized as an important and essential part in the international construction process. It has a substantial contribution to the success of a project. However, briefing has not been acknowledged in the formal way by client and consultant in Vietnam construction industry. Client and consultants are not aware of the importance of the briefing process and most of them have not been trained with the factors related to the client’s brief.

The literature study shows the essential activities and interactive relationships involving the client organization and the design team as they progress through each phase of the project. It provides valued information to achieve assessments and project objectives.

Some problems in this study revealed that architect is stuck by not admitting what a paramount briefing and clarifies elements which important roles play in a successful project.

To know the client’s objective through the briefing process, the literature has been reviewed on the concepts of the briefing process, the definitions of a client, client’s expectations and the client briefing process within the construction. The investigation tried to understand the expectation of clients through the client’s briefing process.

To apply techniques of briefing process for architect, exploring different methodologies and tools that can be used to establish client’s demand and expectation on construction project such as questionnaire development, need analysis, briefing content, and communication.

To understand the administrative and official process impacting on the briefing process, involvement of client, stockholders, end user, and consultant during the process is very essential. Managing changes of requirement, recording verbal communication, and making decision are factors in briefing administration which has impacts towards the success or failure of project.

Aside form these, this research also provides the methods to the briefing process to get requirements from client such as empowering client, managing project, parties’ involvement, team building and using computer system, communication skill, and record system.

Although there are still some problems in Vietnam construction industry, this study has been achieved by the conclusion that the industry will be focused on a briefing process especially in application methods of briefing, training and proper acknowledgment of a brief to get efficiency and profitability from the project.

Recommendation

Recommendation to improve briefing process in Vietnam construction industry

Perceive role of briefing:
Need to train all parties involved in a project, be aware of how important the briefing is, the role of briefing in a project and contribution of briefing to the success of a project. Through a better briefing, an architect can get what the real client’s wants and client’s expectation. Even the clients will be able to make decisions related to investment with great confidence.

Understand briefing process:
Briefing process is an interactive process between the client and professional teams and briefing happens continuously during a construction process. Briefing process needs many techniques, tools to get requirements and demands from client such as team building, getting information, analyzing, managing changes of requirement, recording, and communicating.

Apply different techniques in construction:
Find out various techniques to apply in a briefing process such as using computer system to improve communication between client and professional team (Science & Engineering Research Council) includes general approach, questionnaire development, data analysis, and system contents.

Her thesis abstract is copied and posted.

Abstract


Client briefing plays a crucial role in success of a construction project. A successful briefing can achieve the target time, cost and quality for a project and make decision on project confidently. Although there are many attempts to approach client’s requirement and needs for a project, it is still not collected adequately to make appropriate solutions in design. In Vietnam, client briefing is not considered an important process and architects usually focus on design without paying any attention what their client really wants.

The objective of this research are to provide a basic knowledge of briefing process which is not consider as a integral process in construction process in Vietnam, present research, analysis of problems of briefing in a project and recommend a briefing framework in order to avoid client’s frequent changes and control information collected systematically.

This Project Report has taken a general view of Briefing Process in theory and analyzing a case study that applied in VN to find out reasons of failure, lack of briefing techniques. The report points out that a framework of briefing need to be established for identification what a client really wand and clarification of client’s demands.

Thursday 20 January 2011

Risk Management in Price Adjustment Contract: A Case Study of a Construction Project in Vietnam

During the past years, Vietnam’s construction projects used lump-sum contract and fixed unit price contract as the universal contracts. The lump-sum contract has advantages of easy acceptance of work and contract payment. If the Contractor implements the drawing and specs correctly as agreed, they would be paid 100% without any dependence on increase or decrease of the original work in the contract, or any price fluctuation in the market. While fixed unit price contract has advantages of enabling all parties to quickly implement contract payment. That is because the unit price is already fixed no matter what the real price in the market. The remained problem is determining the volume of work under actual situation. This part is quite easy to carry out and unlikely to cause argument.

However, both of these two contract forms revealed their big disadvantages in "price-storm" from the end of 2007 through the end of 2008. At that time, prices of fuels and materials such as gas, petroleum, steel, cement, brick, sand, stone, electric cable, wood, glass increased suddenly. Some materials increased the price three times. This is not the first time that contractors encounter problem of price fluctuation. At present, the price is gradually approaching the global price. Therefore, construction projects during this period were affected significantly by the “price-storm” and many contractors face risk of bankruptcy.

To solve this problem, the Prime Minister launched document 164/TTg-CN on January 29, 2008 saying “...deal with construction cost in lump-sum contracts”. After that, some authorized institutions like Ministry of Construction and Department of Construction launched many documents to guide adjusting form’s contractual prices of lump-sum contracts and fixed unit price contracts to contract price based on adjustable price form. The purpose of these documents is to solve the difficulties for Contractors and hasten projects implement.

After this event, contract price based on adjustable price form (volume under actual situation and cost adjusted under conditions in the contract) was preferred to use for many projects. However, most of this type of contract only has a very general content as “adjustment under guidance of the Government in case of price fluctuation” without any specific scope and methods to adjust. The result is, during the process of implementing the contract, there were many arguments on determining the adjusted unit price to pay the Contractor. Until now, many projects cannot execute price adjustment.

Mrs. Hoang Thi Hai Anh made a research in which she wanted to point out the problems in signing and implementation of the contract that has contract price based on adjustable price form of a project in Ho Chi Minh City, Vietnam.

Conclusions

Form and lump-sum or unit price contract is no longer suitable for big construction projects especially those with long construction time due to fluctuation in price of materials in Vietnam as well as in other countries. Using contracts under adjusted cost now is encouraged by the Government. However, during contract signing, all parties need to bring out their own rules clearly and specifically, and have to commit to obey those rules. Through the case study, there are two reasons revealed which lead to troubles when implementing the contract such as:

1. The Contractor intentionally proposed low price to win the tender. However, they misunderstood the meaning of the contract under adjusted cost. They think that although the price bid was low, still, they will be paid according to real price on the market during the time of payment, where actually, price adjustment is just to supplement fluctuated price between the time of signing and paying the contract, not dependent on if the tender price is high or low.

2. The Client was passive and did not foresee difficulties when paying the contract. They also relied too much on Government guidelines. Before planning the contract, they did not put forth conditions in relation with adjustment price such as adjusted scope, formulas, and bases to determine adjusted cost.

Recommendations

In the long term, the contractors need to know how to protect themselves and have to consider carefully when receiving the tender to implement the contract accurately. They should also be fair to accept loss. All parties need to learn experiences from developed countries to apply international rules in construction contracts. At the same time, they should also be more active and fearless to bring out conditions for cost adjustment with appropriate characteristics, scale and schedule for each project.

Her thesis abstract is copied and posted.

Abstract

Risk management in construction contract is always important items helping reduce the arising damage or disputes and is a solid basis to force the parties to fulfill their responsibilities in the contract.

In the contract, payment issues are always the core issues and often controversial if it's not really clear. Contract price adjustment due to price fluctuation is quite outstanding issue in Vietnam from 2008 to now; it has made the authorized agencies issue up to ten guiding documents within only one year to settle the problems during contract performance. With my own experiences, in this report I would like to talk about the popular errors while preparing the terms of payment of contract, especially the contracts in which form of contract price is based on adjustable price of the State-funded projects in Vietnam.

I do hope that my ideas shared above will help the Contractors and the Clients of the similar projects minimize the risks in the construction contract.

Wednesday 19 January 2011

Environmental Impacts Assessment of Nam Ly Bridge – Ho Chi Minh City, Viet Nam

Given Vietnam’s newfound prominence in Asia as the “The New Land of Opportunity”, people search for every opportunity to develop the economy and to satisfy the increasing demands especially in construction of infrastructure. When people gets profit in exchange of other use of land, water and other natural resources, there will be an equal impact in the environmental condition both natural and social.

The question is how to reduce these changes, while still aiming for economic growth.

Ms. Trinh Thi Thu Ha made a case study which main objectives were to: (1) study environmental impacts assessment methods; (2) compare of the Viet Nam’s policies and ADB’s policies in EIA; and (3) study environmental impacts assessment of construction project in Viet Nam

Conclusion

EIA is one of the policy tools that are used to evaluate project proposals. It is also a relatively recent development when compared to use of economic appraisal methods in Viet Nam.

Most of the construction projects in Vietnam which will invest funds from many different capitals are required to comply with laws and regulations to implement the project, and EIA must be researched in Preparation stage and presented in the Appraisal stage.

The contents of the EIA is usually consists of 9 parts such as: Introduction; Description of the Project; Description of the Environment; Alternatives; Anticipated Environmental Impacts and Mitigation Measures; Economic Assessment; Environmental Management Plan; Public Involvement and Disclosure; and Conclusions.
The EMP explains how the measures will be managed, who will implement them, and when and where they will be implemented.

During project implementation, the clients must implement properly the approved content of the EIA to ensure that the negative impacts have been mitigated so that the environment and the community have been protected for the sustainable development objectives.

There are differences between Vietnamese policies and the sponsors’ policies for EIA in Vietnam. With ODA projects, World Bank and Asian Development Bank have also established regulations and guidelines to ensure that EIA applies to projects funded. Possible policies and activities required them in different way, but the process is relatively the same for the building and approving the EIA. In Vietnam, in addition to the applicable policies of the sponsors for the project, the EIA also have to establish compliance with current policies of the government of Vietnam.
However, if there are differences between the policies of Vietnam and the donor's policies, they must apply the policies of the donors, which is required in the loan terms.

Recommendations:

1. Adjustment or harmonization of policies and laws in the implementation of EIA, without gaps to the policies of the donors (ADB, World Bank, etc.).

2. The Government should establish training programs for students of the EIA and raise awareness and capacity about the protection and management for environmental leaders, department managers and community;

3. Establish public databases and share the parameters of environmental quality for other projects in Vietnam;

4. There should be public participation during the implementation of EIA. The project must be publicly reviewed and evaluated by the public.

5. Full finance for the EIA study.

Her thesis abstract is copied and posted.

Abstract

The demands of people increase rapidly while the resources are limited. To satisfy the increasing demands, people search for every opportunity to develop the economy. Because of that, investing for construction of infrastructure is a need to develop economic regions, is a progress in the development of the society.

When human bring in financial to change the patterns of use of land, water and other natural resources, they will receive back profit from economy development, but will also change the other elements of the environment like natural condition and social.
Reducing the burden of environmental impacts is necessary if development is to become sustainable. Environment Impact Assessment (EIA) has become of ever increasing importance as a tool for development decision-making.

Environmental impact assessment, as a national instrument, shall be undertaken for proposed activities that are likely to have a significant adverse impact on the environment and are subject to a decision of a competent national authority.
In practice, EIA is applied primarily to prevent or minimize the adverse effects of major development proposals.

Tuesday 18 January 2011

Planning for Improving Efficiency of Housing Project’s Development Process

The increase in housing demand and the high cost of land in big cities in Vietnam such as Hanoi and Ho Chi Minh create a huge market for high-rise housing projects. However, development of these housing projects face many obstacles such as low income, high inflation, high bank interest rate, high land price, increasing construction materials and labor cost. In addition, the long project development period due to lack of transparency in local regulations and authority submission procedure also makes the investment projects less efficient. It requires the project managers / project planners having a good understanding on Vietnam law and regulations, and good planning skills to improve the development process of housing projects.

According to the 2009 Governmental Investment Project Assessment Report by Ho Chi Minh City People’s Committee, there are 1,177 projects completed until the end of the year 2009, which are currently equal to 20% of 5,886 operational projects in Ho Chi Minh City. However, 65% of the projects were delayed and only 20 projects achieved the 30% target progress. The obvious reasons for these are:
1. Weak financial capacity of the project owners.
2. Lack of experienced project managers and project management human resources.
3. Long period for authority submission and lack of transparency of Vietnam law and regulations.
4. Land clearance and resettlement

Mr. Bui Quang Huy made a study to investigate the basic requirements by Vietnam law and regulations, the common practice of housing development projects in Vietnam complying with Vietnam law and regulations; and to find out a more efficient process for developing a housing project in Vietnam.

Conclusions:

- The housing development industry has its own characteristics. Every single activity in the project development process has to comply with local law and regulations. Hence, the good understanding about local law and regulations is very useful for developers in their business. The success of the case project in this study also greatly depends on the understanding about local law and regulations beside the project management knowledge.

- The old practice of housing project development process complying with Vietnam law and regulation is not efficient, it takes 60 – 78 months to finish the project from the feasibility study and planning phase to handing over and obtaining the ownerships for the house buyers. The longer the project development period is, the more costly the investment in housing projects. Besides, Vietnam population and housing demand are developing very fast, the supply could not satisfy the demand. Hence, the housing price could not be reduced and a major part of people with low and medium income cannot afford to buy houses. It causes a lot of social issues in Vietnam.

- With the improved housing development process proposed, it takes 45 – 57 months to finish the project. If we only consider the Project Launching Preparation phase, 15 – 21months would be saved, then it takes 12 -15 months in the improved process instead of 27 - 36 months of the old process. This is a valuable improvement. The investment in housing project becomes more efficient when the developers can recycle their investment faster and cut down financial cost in housing projects. It helps to increase the supply of housing products and reduce house price.

- Besides the understanding about Vietnam market, the knowledge from lean production and last planner theory also offers a basis for evaluating the whole development process of housing projects and identify waste times in the process. The project manager/ planner should examine and schedule the project with all constituent and continuous activities as a whole. By implementing that, it will make the timing of whole project period more efficient, rather than only taking care of shortening the period of its individual activities. The application of lean theory is absolutely suitable for the current situation of Vietnam housing market. It helps to shorten the project development period and make the process more efficient by ignoring waste time. There are no additional costs to apply these theories.

Recommendations:

- In general, when the understanding about local law and regulations is very important in housing project development, the developers should continuously update and study local law and regulations, especially, the new issuances.

- A good relationship with government also helps developers in their submission works. This relationship could be created by contributing to society and maintaining the good image in the local market. The developers should properly deliver what they committed to the government and buyers.

- The developers are recommended to maintain their efforts in evaluating the working and project development process to find any problems for improvement, not only waste of time, but also any other wastes such as cost, manpower, etc.

- Lastly, the good schedule should never achieve the good actual result if it is not well controlled. The control system also needs to be established to monitor the execution of the project to ensure it is carried out in accordance with the plan.

His thesis abstract is copied and posted.

Abstract

Vietnam is a developing country, it means that the country need a lot of knowledge for development, especially in the field of construction project management.
Some “old men” think that all the construction projects are similar, about the process, technology and method, especially housing development projects. They are actually not similar, there are many projects carried out in such a way of wasting time and cost; and achieving bad quality.

In this study, a more efficient process for housing development project is introduced. Hopefully, it could help the project managers / planners schedule and execute their projects strictly complying with the local law and regulations, in shorter cycle without any additional costs for advanced technology and materials.

This study also affirms that there is always inefficiency in project development process of every construction projects. The project managers should always spend enough efforts to identify wastes and improve them. This is helping the projects, the company and the country, in a wider angle of view.

Monday 17 January 2011

Project Management Practice in Small and Medium Vietnamese Contractor: A Case Study of Nhat Dang Company

In the last ten years, Viet Nam economy is one of the fastest growing economies in the world. Along with this economic development is the boosts in construction industry which mostly involve are small and medium construction enterprise. These SMEs are comprised of small number of employees and have limited total assets. According to Vietnam’s Decree 56/2009/NĐ-CP, SMEs are divided into three levels based on the total assets and number of employees such as:
- Micro enterprises: under 10 employees.
- Small enterprises: total assets are under 20 billion VND and number of employees is from 10 to 200 peoples.
- Medium enterprises: total assets are from 20 to 100 billion VND and number of employees is from 200 to 300 peoples.

With limited financial and human resources, SME contractors are unable to win big projects or operate many projects at the same time. SMEs also easily encounter cash shortage problem. According to Ling et al. (2009), one of the weaknesses of Vietnamese contractors is lack of project management ability. Almost all performed projects in Vietnam encountered delay, low quality or cost overrun due to low project management capability of the owners and contactors. Most SMEs are founded by an engineer or architect, who had worked for a bigger company and who is well-experienced in construction but not in management. With limited financial capacity, SMEs cannot hire good project manager resulting to poor project management capability.

The requirement of strong project management ability is becoming more essential for Vietnamese SME contractors since more projects have participation of foreign owners, consultants or main contractors, where requirement of schedule and quality performance are very strict. But how could SME contractors do it effectively with limited resources is still a question.

Mr. Vo Dinh Nguyen made a project study which objectives were to: (1) investigate project management functions of a small construction company; (2) identify strengths and weaknesses of project management of the company; and (3) propose recommendations for improvement of project management functions in small construction company.

Conclusion

By reviewing related theory of project management and analyzing the operation practice of Nhat Dang Company, the strengths and weaknesses of the company in certain areas of project management are summarized in table below.



Project management is not just limited in these aspects and to have a more general view of company management capability; other areas of project management knowledge should also be studied. These include:
- Project scope management;
- Project human resource management;
- Project communications management; and
- Project integration management.

Base on identified strengths and weaknesses, the case study proposed solutions to improve project management competency of the company in studied areas. Some solutions that require more resources should be planned to apply when the management capability reach a higher level. They may be useful for some Vietnamese SME contractors which are in the same situation but may be unsuitable for others. Some essential solutions that the company needs to achieve to ensure their operations are:
- Full utilization of earned value technique for better schedule and cost control.
- Develop an advance resource requirement plan for each project.
- Establish the project spending plan and funding requirement and follow the plan in operation.
- Carry out the project risk management process.

- Enhance the role of the project team.

Another weakness that the company management has is the lack of measuring, recording and analyzing the results of management processes for improvement. A useful model for continuous improvement is the Plan – Do - Check – Act cycle as show in figure below.



Plan : Define the goal and processes to achieve it

Do : Implement processes

Check : Measure the process and results against defined values to find out variations.

Act : Analyze variations and determine necessary actions to improve future operations.

This model is helpful and can be applied in any process of management, any organization for improving management competence.

His abstract is copied and posted.

Abstract

Project management plays a very important role in the management of construction enterprises. Although being the major element in Vietnam construction industry, most of Vietnamese SME contractors are still weak in project management capability. Improving project management capabilities are essential needs for survival and development of SME contractors.

This report reviews theory of project management in areas of time, cost, quality, procurement and risk management. Necessary processes and knowledge for those project management functions are identified and analyzed.

By analyzing past performance and practice of project management in Nhat Dang construction company, a typical SME contractor in Ho Chi Minh City, the report point out strengths and weaknesses in project management of the company. Necessary solutions for improvements of project management functions are proposed. These solutions can be applied to similar small construction companies either.

Friday 14 January 2011

Minimizing Impact of Change Order to Projects Cost

Contract Management is a vast scope particularly in construction industry wherein a single contract normally finishes from months to years. Managing a contract in any construction project is a tedious task. All pertinent documents must be monitored, diligently recorded and filed before, during and after construction. Changes in construction as we know are inevitable but can be properly managed and controlled. Deviation from the contract, often called change order or variation order are changes brought about by the owner or changes due to site conditions, damages or weather. These changes may not directly affect the contract in terms of time and cost, but both parties must be knowledgeable as to how to control and protect the owner and contractor from any changes necessary in the construction and implementation of the project. In order to manage such changes or variation orders, proper guidelines must be followed.

Knowing and carefully reviewing the contract, following the proper variation procedure and constantly taking in to consideration the risks that may bring about if poor records of everyday activities particularly on change orders would be taxing if the Contractor claims.

Ms. Chona S. Salvahan made a study which objectives were to: (1) identify changes occurring in a residential apartment project. Identify the type, causation and resolution; and (2) identify proper procedure, develop methodology and documentation to control and manage variation or change orders. Identifying the type of change order will help formulate a procedure adapt to the variation.

Conclusion

Based on the case study, the residential apartment project garnered change order that were classified into five (5) categories such as:

1. Addendums – included additional packages outside the scope of the original contract and are entirely different work but necessary for the project.

2. Price Fluctuation – included price adjustments to construction materials used on site specifically on concrete, reinforcement bars, sand and cement used for structural works on site.
3. Variation due to Design Change – these changes may have resulted from design revisions, defects in drawings or contract documents and differing site conditions grouped into main building works and external works package.

4. Damages – were from re-works items or damages due to negligence of other contractors and sub-contractors.

5. Deductions or Omission – included items that were not installed on site and items that were cancelled and were redundant to the design

Variations that were considered under Extra Work are the three (3) Addendums to the contract. While variations directly requested by the Owner to improve serviceability and aesthetic of the building are considered Additional works. One example is the supply and installation aluminum louver to cover the condensing unit of air-conditioning in every apartment. This additional work is considered Directed Change because the instruction to change or add is from the project owner. Other variations resulted from factor that influence the change were considered constructive change as well as Price Fluctuation, Damages and Omissions were all under different situations during implementation of the project.

Factors that contributed to the change were clearly specified in this study. These events in the construction that caused changes generated even before the main building works started. Continuing to the construction, another set of variations emerge during implementation. At this stage, causes may have been different from the causes during the pre-construction stage. Towards completion of the project, changes still occur, seeing the defects and the need to add or enhance serviceability of the development. Current procedure is useful but can be developed to improve processing period and administer each changes lessening the probable effect to the whole project particularly on the cost.

Below are the suggested stages of processing procedure for better time table of change order settlement:

Validation – where entitlement is agreed and analyzing the effect of the change to project cost and schedule.

1. Evaluation – verifying and gathering data to substantiate the claim. It is also the time of determining the true cost of the variation order thru investigation, review of quantities and considerations in estimates. It is also at this time that both parties should concur and agree on quantity, measurement and total cost in order to save time and will only proceed to the next whenever disagreement on cost arises.

2. Negotiation – only and only if both parties cannot arrive into agreement on price, quantities, measurement or methods should resort to this step where the top management is involve in order settling amicably.

3. Final Approval – time when both parties are satisfied with the evaluation, change order is prepared for final documentation and approval.

Special concerns have to be met particularly of this project. Many of the units have already been sold and were committed to deliver to the tenant on specific dates. The project has no luxury of extending the time thru which in trying to satisfy the commitment of the Owner, the construction restrained the project from achieving a more quality and a more organized method in implementing the project. Change order management helped control the changes incurred during construction but not totally eliminate the potential changes. It may prevent these changes to accumulate and later when accumulated can become a bigger claim for the contractor which is more tedious, complicated and time consuming task to process.

Furthermore, prior to implementation and part of Change Order Management is the adding change clause in the contract, formulating variation procedure and setting or allocating time for settlement process. The deliberate inclusion of change clause is similarly important to control probable change order in a construction project. As observed, the other 3 main sources of change on site were the following:

Differing site conditions resulted from defects in the construction of substructure. The previously installed piles were displaced and because of this the foundation design has to be checked and revised. The owner was compelled to review and revise if necessary the whole structural building.

Defects in contract documents where a number of items were not in the drawings or specification but necessary to install or construct on site.

Owner direction or instructions where the rest of the variations were directed by the owner either thru modification of design drawings or changes had to be added for aesthetic reasons. A lot of variations were requested by the owner or unit buyers.

Recommendation

In order to manage Change Order, both parties should identify their right to vary, the Owner right to include change clause to protect their benefit. These change clauses must be anticipated during planning and before composition of the contract. Therefore a meticulous study of the drawings, site conditions and other factors that may affect arise change in the contract and construction. Clear definition of scope of work would minimize the risk of misinterpretation and misjudgment of the work. In a way, changes would be avoided and if items were not included in the contract, it can be easily identified and agreed on. More so, clear distinction of the methods and procedure to use in claiming variations and the authority issuing the VO. This will clearly guide the contractor on how, what and who to talk to in case a change would occur.

Her thesis abstract is copied and posted.

Abstract

Construction industry is often described as a volatile industry which can be true in implementing a project. Construction itself is more often unpredictable due to the different situations a project may face. Changes may occur in the preparation, during construction and even upon completion of the project. The veracity of inconsistent nature of construction, change management procedures must be considered to minimize the effects particularly to project cost, time schedule and overall quality of the project.

Recently, the high turn in of foreign investors and Vietnamese nationals living abroad inspired a number of Developers to venture in High End Apartments. The big challenge for the Vietnam Construction industry is to advance the management styles to cope up with challenges faced in a project. Procedures in managing contract and change orders are viewed to know the effectiveness and liability ensuing steps observed. Disruptions in cash flow and programme when mitigated and handled correctly may create confidence in handling changes that transpire in any project.

However, knowledge and skill in managing this challenging changes and observing effective procedures may eventually create a norm in Project Management system in the industry where tradition of strong relationship among Owner and Contract still prevails.

Thursday 13 January 2011

Risk Management in PPP Expressway Project in Vietnam: Ha Noi – Hai Phong Expressway Project Case Study

The rapid growth of Vietnam’s economy over the past few years contributes a significant strain on the country’s physical infrastructure. With economic development expected to continue at a rapid pace, pressures on roads, ports and other infrastructure systems will increase. Vietnam’s underlying concern for the last 10 years is a failure to develop infrastructure, which is now become a bottleneck of economic growth.

In next ten years 2010 to 2020, demands for infrastructure investment will increase by 10%, But how the Vietnam government can mobilize such huge capital shortfall for infrastructure investment, while state budget deficit stands at high level for a very long time and the public debt is in high level and in fast increasing trend (the economist newspapers at http://www.economist.com). With these problems, Public-Private Partnerships (PPP) becomes the optimal solution to fill the shortfall of finance resource.

However, until now, there is still no legal concept of PPP or a separate law on PPP in Vietnam. The only current separated regulation for investment under BOT scheme (a kind of PPP model) is Circular No.108/ND-CP dated 27, November, 2009. The Vietnamese Government and relevant ministries recognize need to established PPP’s legal framework to raise capital from the private sector and from banks and credit institutions, regardless of whether they are under domestic or foreign. PPPs regulations, after one year of preparation by MPI and related ministries were issued on 15th November 2010 by Prime Minister.

Until now, there are only few researches have been conducted on risk management in PPP expressway project in Viet Nam. In order to help investors and policy makers to have a better perception on risk management in PPP expressway project in Vietnam, Mr. Vu Van Cao made a case study with the following objectives:

1. identify and assess the key risk in investment under PPP in Viet Nam;
2. how this key risk in investment under PPP in Vietnam are allocated in Ha Noi – Hai Phong expressway project through Project structure; and
3. recommendation for the Project Company to improve mitigation of critical Risk in Ha Noi – Hai Phong expresses way Project

Conclusion

Base on the results of analysis, it can be seen that risk allocation among related stakeholder is not so good and fair because Vietnamese government transfers all critical risks to Project Company and to road users which causes BOT project long period concession; and the Project Company have to take the financial burden leading to company bankruptcy.

Recommendations for Project Company (VIFIDI)

1. Establishing a specified team in charge to investigate the risks through BOT contract and to propose mitigation strategy;

2. Renegotiation with MOT on BOT contract provision on allocation of risks, which are assessed “cannot be accepted”;

3. Need to sharing risks, which are assessed “Accepted” with the third party;

4. Reevaluation of commercial viability of BOT project and recalculation of financial ratio of BOT project (ROE, NPV, and IRR) to reassess feasibility of the project; and

5. Propose to Government to give financial support to fund land acquisition and resettlement to reduce financial burden during construction period because (i) D/E ration level is too high 13.3) and can cause instability in financial situation when project comes into operation (recommended D/E ratio is 3 times following the PPP pilot regulations No. 71/2010/QD –TTg issued by Prime Minister on 9th November 2010); (ii) Concession period is too long (30.36 year) which causes long return for investors.

Recommendation for Ministry of Transportation (MOT) and GOV (Vietnam Government)

The Ha Noi – Hai Phong expressway is the first expressway project invested under BOT in Vietnam. The success of this project can be a good example to attract more private capital investment on expressway development under PPP model. Therefore, GOV and BOT must share the risks with project company and road user in order to help VIDIFI to implement the project successfully. Below are some recommendations for GOV and MOT to follow:

1. Most of the risks in Ha Noi – Hai Phong expressway project have been transferred to the road user and Project Company. It is proposed that the MOT and GOV fund to land acquisition and resettlement in order to reduce financial burden of Project Company and shorten the concession period;

2. GOV has to give Project company right to develop Land expressway to return their capital investment (profit from land development is expected 7.890 billion VND). Project Company needs more finance resources to fund land development project by itself. This causes unintentionally increasing financial burden on investors. Thus, instead of giving the Project Company the right to develop Land expressway to return capital investment, GOV should allow VIDIFI to increase toll rate of existing NHNo.5, and access to preferential loan with low interest rate and long payback period to reduce financial burden, shorten concession period and increasing feasibility of project.

Mr. Cao’s thesis abstract is copied and posted.

Abstract

Recent years in Vietnam, many Public Private Partnership (PPP) expressway projects have been being invested under PPP model. But the Risk management, which is critical factor of project success, is undervaluation by investors and policy maker. This project case study will contribute on increasing perception on risk management of the investors and policy makers in Vietnam. Project case study will indentify, classify and assess the risks in PPP expressway investment in Vietnam and specify the critical risks, for which the investors and policy makers must pay their attention. The investors and policy makers will understand how the above critical risks to be managed through case study of Ha Noi – Hai Phong expressway project. In the case study, the research will assess the risk allocation among three parties including investor (Project Company), public authorities and road users. The research will also propose recommendation for Project Company improving the risk management in case study.

Wednesday 12 January 2011

A Hybrid Stochastic/Mechanistic Model for Determining Bridge Condition Rating

Bridges like other infrastructures such as roads and dams require proper inspection and maintenance programs to reserve bridge structural integrity and to ensure public safety. The structural integrity decreases through time due to several factors such as material degradation, environmental attacks, and an increase in usage over time. The consequence of improper inspection and maintenance programs can cause catastrophic bridge failure.

Dr. Rajwanlop Kumpoopong made a research which focused on developing a hybrid deterioration model that combines the quantitative analysis of damage mechanisms and the stochastic process based on the concept of Markov chain. The proposed model enhances the existing Markov deterioration model in a more reliable condition prediction of bridge elements at the network-level since relevant variables which affect the deterioration of bridge elements are properly addressed. Only the hybrid deterioration model for bridge deck is developed in this research.
The main objective of this research was to develop the methodology for developing the hybrid deterioration model for bridge deck that combines the quantitative analysis of crack mechanism due to truck traffic loads and the stochastic process based on the concept of Markov chain for the network-level bridge management. The methodology is then applied to develop the hybrid deterioration model for bridge deck under truck traffic condition in Thailand as a case study. The secondary objectives of this research were to: (1) study the effect of each truck category on the deterioration of bridge deck; (2) study the effect of upgrading regulatory truck weights on the deterioration of bridge deck; and (3) study the effect of overloaded truck for the transportation of sugarcane on the deterioration of bridge deck.

Conclusions

Bridge deck is the major bridge component that requires significant maintenance effort. The factor that contributes most to the deterioration process of bridge decks is concrete cracking which is directly related to the traffic volume and can be accelerated by increasing truck traffic. Bridge deck deterioration models in most recent bridge management systems are expressed in the form of probabilistic deterioration models such as the Markovian process. The transition probability matrix is developed to capture the deterioration mechanism of bridge decks.

The strength of the Markov deterioration model is its practicality when it is applied to forecast at the network-level bridge management. The condition of the bridge deck over time can simply be predicted through the multiplications of the initial state vector and the transition probability matrix. However, the Markov deterioration model has some weaknesses since the model may not reflect the actual condition of bridge decks. In the Markov chain models, relevant variables which affect the deterioration process of bridge decks, such as changes in traffic volume and environmental conditions are assumed to be constant throughout the analysis period. This may not be realistic and can result in the overestimation or underestimation of the forecasted bridge condition.

This research work aims to develop the methodology for developing the hybrid deterioration model for reinforced concrete (RC) bridge deck that combines the quantitative analysis of crack mechanism due to truck traffic loads and the stochastic process based on the concept of Markov chain for the network-level bridge management.

In this research, the finite element program that can simulate cracks in RC bridge deck due to truck traffic is developed to capture the crack mechanism. The results are presented by S-N relations of RC bridge deck at different levels of damage. The damage is defined in this study as the extent of crack on the bottom surface of the deck slab or the crack level. Distribution curves of the number of trucks required for the crack to reach each crack level are then developed from the simulated S-N relations and the truck weight information. From these distribution curves and the specified truck traffic volume and composition, transition probabilities based on the concept of Markov chain can be calculated. Based on the proposed technique, transition probabilities can be calculated for truck traffic data that is non-homogeneous with respect to both composition and volume which provides the flexibility of the model to be applied to highway bridges of different truck traffic conditions. The effect of specific overloaded trucks on the deterioration of DOH bridge deck is discussed through the case study of the transportation of sugarcane. For practical assessment of the deterioration of DOH bridge deck, a series of distribution curves of the number of trucks required for the crack to reach different crack levels for different truck categories and gross weights is provided.

His dissertation abstract is copied and posted below.

ABSTRACT

The concept of Markov chain has been widely used to predict the condition of bridge deck. The transition probability matrices, which are mostly developed by inspection data and experts’ opinion, are used to capture the deterioration of bridge deck. The Markov deterioration model developed by this approach although states deterioration in probabilistic sense may not be reliable because relevant variables which affect the deterioration of bridge deck such as changes in traffic volume and environmental conditions are not explicitly emphasized in the model. Concrete cracking which can be accelerated by increased truck traffic is the factor that contributes most to the deterioration of bridge deck and should be addressed in the deterioration model. This research work aims to develop the methodology for developing the hybrid deterioration model for reinforced concrete (RC) bridge deck that combines the quantitative analysis of crack mechanism due to truck traffic loads and the stochastic process based on the concept of Markov chain for the network-level bridge management. In this research, the finite element program that can simulate cracks in RC bridge deck due to truck traffic is developed to capture the crack mechanism. The results are presented by S-N relations of RC bridge deck at different levels of damage. The damage is defined in this study as the extent of crack on the bottom surface of the deck slab or the crack level. Distribution curves of the number of trucks required for the crack to reach each crack level are then developed from the simulated S-N relations and the truck weight information. From these distribution curves and the specified truck traffic volume and composition, transition probabilities based on the concept of Markov chain can be calculated. Based on the proposed technique, transition probabilities can be calculated for truck traffic data that is non-homogeneous with respect to both composition and volume which provides the flexibility of the model to be applied to highway bridges of different truck traffic conditions. The methodology is presented through the development of hybrid deterioration model for Thailand Department of Highways (DOH) bridge deck. In the presentation, the effect of each truck category and the effect of upgrading regulatory truck weights on the deterioration of DOH bridge deck are discussed. The effect of specific overloaded trucks on the deterioration of DOH bridge deck is discussed through the case study of the transportation of sugarcane. For practical assessment of the deterioration of DOH bridge deck, a series of distribution curves of the number of trucks required for the crack to reach different crack levels for different truck categories and gross weights is provided.

Tuesday 11 January 2011

CEIM-SET Congratulates the Graduates of 114th Batch

We would like to congratulate the new graduates who received their diploma during the 114th AIT Graduation Ceremony on December 17, 2010. The names of graduands and their Thesis/Project title are listed below:

DOCTOR OF PHILOSOPHY DEGREE (CEIM)

1. Rajwanlop Kumpoopong
A Hybrid Stochastic/Mechanistic Model for Determining Bridge Condition Rating

MASTER OF ENGINEERING DEGREE (CEIM)

1. Kittichai Kanjanakantika
Risk Factors Affecting Business Diversification in a Real Estate Company

2. Vuong Hai Khoa
Supply Chain Management: A Case Study of Construction Companies in Vietnam

3. Tinn Withayawaragul
Relationship Between Project Phases and Stock Performance: A Study in Stock Exchange of Thailand (SET)

MASTER OF ENGINEERING DEGREE (PROFESSIONAL)
(Area of Specialization: Project Management in Construction)

1. Nguyen Chau Dieu An
Project: A Critical Appraisal of Briefing Clients in the Construction Process: A Case Study of Residential Project

2. Hoang Thi Hai Anh
Project: Risk Management in Price Adjustment Contract: A Case Study of a Construction Project in Vietnam

3. Dang Tuan Anh
Project: Risk Management of Basement Construction Affecting Adjacent Buildings: A Case Study of Construction Project in Ho Chi Minh City, Vietnam

4. Truong Thai Binh
Project: Owner's Involvement in the Preliminary Stage of Real Estate Development: A Project Case Study in Vietnam

5. Nguyen Phan Hoa Binh
Project: Integrated Project Management Assessment for a Development Property Project at the Capital Fund in Vietnam

6. Le Nam Binh
Project: Owner's Project Schedule Management for High-Rise Office Building Projects: A Case Study of the Construction Project of Petrovietnam Finance Centre in Danang City

7. Nguyen Hung Cuong
Project: Delay in Planning, Design and Construction: A Case Study of Residential Development Project in Ho Chi Minh City

8. Le Ngoc Diep
Project: Risks Affecting Construction Cost in Vietnam

9. Do Tran My Thuy
Project: Risk Management in the Design of Large-Scale Construction Projects: Case Studies of an Urban Area and a Highrise Building Project

10. Truong Ngoc Dung
Project: Effectiveness of Feasibility Study Analysis in an Apartment Building Project: A Case Study of a Two Towers-Twenty Six Storey Apartment Project in Ho Chi Minh City

11. Nguyen Duy Thien Giang
Project: Claim Management and Analysis: Case Study of a High Rise Building Project

12. Trinh Thi Thu Ha
Project: Environmental Impacts Assessment in Nam Ly Bridge - Ho Chi Minh City, Vietnam

13. Vo Si Hoai
Project: Schedule Planning and Control in an Engineering, Procurement and Construction Project: The Case of a City Hall Project

14. Le Quang Khanh
Project: Owner's Organization Project Management Maturity: The Case of Petrolimex Saigon

15. Nguyen Trung Kien
Project: Project Owner's Quality Management System - The Case of Sails Tower Project

16. Tran Thanh Liem
Project: Project Management Life Cycle and Risk Management in a New Residential Development Project in Vietnam: The Case Study of the Fifth Street New Residential Project (D2D's Company) and its Secondary Project (Berjaya-D@D Join Venture Company)

17. Nguyen Cao Bao Luat
Project: Design Management in a Design-Build Project Based on the Design Team of Contractor Perspective

18. Vo Dinh Nguyen
Project: Project Management Practice in a Small and Medium Vietnamese Contractor: The Case of Nhat Dang Company

19. Do Huu Phuoc
Project: Owner's Project Life Cycle Approach: The Case of Rubber Plantation Project in a Vietnam Rubber Company

20. Tran Duc Quang
Project: Project Organizational Structure Roles and Responsibility - The Case of Marriott Five-Star Hotel

21. Chona Salvatus Salvahan
Project: Minimizing the Impact of Change Order to Project Costs

22. Nguyen Duy Duc Thu
Project: A Feasibility Study of a Curtain Wall Testing Company in Hanoi

23. Nguyen Le Thuan
Project: Owner's Project Control Strategy

24. Le Mien Thuy
Project: Method and Effectiveness of a Feasibility Study for an Apartment Project: The Case of Carina Plaza Building

25. Nguyen Thu Trang
Project: Application of Fidic Contract in a Bridge Project: The Case of Can Tho Bridge

26. Tran Thi Thien Trang
Project: Assessment of Risks on the Design Management Aspects in Luxury Hotel Development Projects: The Case of Le Meridien Saigon Hotel

27. Nguyen Duc Trong
Project: Organizational Project Management Structure in a Real Estate Developer Company: The Case of Namlong Corporation

MASTER OF SCIENCE DEGREE (PROFESSIONAL)
(Area of Specialization: Project Management in Construction)

1. Mr. Nguyen Duc Thanh
Project: Risk Factors in Vietnam Power Plant Projects: A Case Study of Nhon Trach Power Plant and Camau Gas Power Fertilise Projects

2. Tran Van Trung
Project: The Delay Factors in EPC Contracts in Vietnam: The Case of Uong Bi Thermal Power Plant

3. Mr. Vo Quoc Vinh
Project: Contractual Risks of SME Contractors - A Case Study a of Mechanical and Electrical Contractor

Monday 10 January 2011

Greetings from CEIM/MPM

Dr. B. H. W. Hadikusumo, Dr. Chotchai Charoenngam and the CEIM/MPM staff wish you a blessed and bountiful year 2011!