Wednesday, 26 September 2012


invitation

AIT SEMINAR

CURRENT PRACTICE
IN JAPANESE CONSTRUCTION MANAGEMENT

The Asian Institute of Technology (AIT), as the Asia-Pacific Region’s first postgraduate engineering school, has striven to promote technological change and sustainable development through education, research and outreach. Over the years, AIT has produced a number of engineering and technology alumni for key organizations/sectors in Vietnam. Advanced education and research in engineering and technology continue to be among the Institute’s greatest strengths.
School of Engineering and Technology (SET) is one of the three schools at AIT. SET’s mission is to develop future leaders, highly qualified engineers and technologists who play leading roles in promoting the region’s industry competitiveness for its integration into global economy. Besides offering state-of-the-art multidisciplinary programs, SET annually conducts expert seminars to promote its cutting-edge applicable researches to interested experts/professionals.
We would like to inform you that Project Management in Construction program (MPM), SET is organizing a seminar in “Current Practice in Japanese Construction Management” at 9:00am on Thursday 04 October 2012, with participation of Prof. Takayuki Minato from The university of Tokyo, Japan.  
Location:          45 Dinh Tien Hoang Str., Ben Nghe ward, District 1, HCMC (Opposite to HTV broadcast station)
Language:         English
We are pleased to invite you or representatives from your institution, company to this seminar. You are kindly requested to confirm your attendance not later than 02 October 2012 to Ms. Nguyen Le Tuong at (08) 39107423 (ext:117); email: ngletuong@aitcv.ac.vn. Fax: (08) 39107422.
We look forward to meeting you all at the seminar and thank you for your cooperation.

Best regards,


AGENDA

08:45 - 09:00

Registration

09:00 - 09:15

Welcome speech
AIT/MPM Introduction

09:15 - 11:15


09:15 - 10:15

10:15 - 11:15

Presentation: Current Practice in Japanese Construction Management

Dr. Takayuki Minato – Associate Professor, The University of Tokyo, Japan

Mr. Le Hoang Nguyen – Engineering Manager, Nakano Corporation

11:15 - 11:30

Discussion


OPENING CEREMONY
MPM06 Ho Chi Minh City, intake 2012

On 22 September 2012, MPM HCMC has organised an Opening Ceremony for MPM06, intake 2012 at Kim Do hotel with participation of MPM06 new students, current students, MPM alumni, professors and guests.

MPM6 will start this course on next day, Sunday 23 September 2012 with Prof. Brockman, from Bremen University, Germany. This intake duration is from Sep 12 to Dec 13. 

In first semester, students will take courses:
  1. Organizational Management in Construction
  2. Integrated Project Planning and Control
  3. Communication and Negotiation for Project Managers
  4. Project Cost and Financial Management
2nd semester:
  1. Occupational Safety and Health Management in Construction Projects
  2. Legal and Contractual Risk Management
  3. Project Financing
  4. International field trip to AIT, Thailand: study 2 applied Project Management courses 
3rd semester
  1. Quality Management in Construction
  2. Applied Project Management in Construction
  3. Final project report
  4. 2nd International field trip to 1 country in Asia
Graduation at AIT, Thailand  


Group photo of MPM06 students and guests

Welcome MPM06 to join MPM from Ms. Mai Do Thuy Dung, President of MPM Alumni Club




Sunday, 23 September 2012

UAE construction summary 

Source: statistical department UAE
www.dsc.gov.ae

Friday, 21 September 2012

1st International Fieldtrip to Korea, September 2012
MPM5 Ho Chi Minh city

During the week 03-07 September 2012, MPM has organised the 2nd international field trip to Korea for MPM5 students. Students visited Hyundai E&C R&D Institute, high-rise building project and public infrastructure sites.

Visit to Hyundai E&C

Dr. Hadikusumo expressed the sincere thanks to Dr. Lee, Suckhong, Director of Hyundai E&C Co., Ltd., R&D Division

@ Hyundai High-rise building site, Korea

@ Amsa Grand Bridge Project, Korea
Lab tour at Hyundai E&C Research Centre

...with Dr. Park, Kyung Ho, Senior Executive Vice President, Civil and Environment Division, Hyundai E&C Co, Ltd. 

Sunday, 9 September 2012

Infrastructure report Indonesia

Activity in Indonesia's construction industry has returned robustly in the second quarter of 2011, bringing real growth for the sector to 6.36% year-on-year in the first half of 2011, in line with our 2011 full-year forecast of 6.3%. However, the lack of improvement in Indonesia's business environment and the weakening global economy will continue to pose significant risks to Indonesia's infrastructure and construction sector in 2012 despite the vast opportunities on offer. Nevertheless, construction activity, driven by investment into transport and energy infrastructure, as well as industrial construction related to the country's growing mining sector, is expected to be relatively robust between 2012 and 2016, averaging 7.2% per annum. 

Key factors that will facilitate growth include: 

In July 2011, Three state-owned Chinese companies, China Building Civil Constructions, Changjiang Waterway Engineering Bureau, and China Foundation for Desertification Control, had send officials to indicate their serious intent to invest in East Java, signed a memorandum of understanding for several infrastructure projects amounting to around US$3bn. This move once again highlight the robust interest companies from stagnant domestic markets have for Indonesia. 

In August 2011, Malaysian company Markmore Labuan had signed an agreement with Prodexim, a company owned by the South Sumatran provincial government, for the construction of a toll road in South Sumatra, Indonesia. The 137km road, requiring an investment of IDR7.5trn (US$882mn), will connect Kayu Agung in Oki with Betung Banyuasin. This investment highlights foreign interest in the sector which is largely dominated by domestic companies. 

In September 2011, the Jakarta administration had finally announced that it is aborting its US$630mn monorail project, a project that had originally started in 2004. The project, which started in 2004, failed to move forward due largely to the lack of financiers. The capital city has since move towards the development of a separate urban railway system. 

Indonesia’s business environment continues to pose downside risks for investors. Although the Indonesian government is working hard to attract private investors, there is still an underlying threat of corruption and a lack of transparency in the tendering process. The biggest concern is that Indonesia appears to be regressing in its fight against corruption, with a raft of proposals - that if approved - would undermine current anti graft laws. This culminates in a score of just 56.7 out of 100 for infrastructure business environment.


Business Monitor International
Source :http://www.marketresearch.com/Business-Monitor-International-v304/Indonesia-Infrastructure-Q1-6680228/

Friday, 7 September 2012


Source: Department of Statistics Singapore

Wednesday, 5 September 2012





Building Construction Activities in recent Years


Source: Building and Construction Authority via Department of Statistics Singapore

Sunday, 2 September 2012

SOCIO-ECONOMIC STATISTICS FOR THE FIRST HALF OF 2012  VIETNAM

1. Gross Domestic Products (GDP) Growth
GDP in the first six months of 2012 at 1994 constant prices was estimated increasing by 4.38% from the same period in 2011, of which it rose 4.00% in 1st Quarter; and by 4.66% in 2nd Quarter. Of the economy’s general growth, the sector of agriculture, forestry and fishery rose 2.81%, contributed 0.48 point percent; the industry and construction by 3.81%, contributed 1.55 points percent; and the service by 5.57%, contributed 2.35 points percent.
The low growth of GDP was due to difficulties met in production, business and consumption of goods by many economic sectors. The industry held great proportion in GDP but its growth was low. However, the economy has changed positively since 2nd Quarter, particularly for the sector of industry and construction: the value added of this sector in 1st Quarter rose only 2.94% from the same period last year, but in 2nd Quarter it rose 4.52%, of which industry rose from 4.03% to 5.40%.
2. Construction
As estimated, 6 months’ constructional production value at current prices reached 283.3 trillion dongs, of which the state sector reached 42.5 trillion dongs, accounted for 15%; the non-state sector 232 trillion dongs, accounted for 81.9%; and the FDI sector 8.8 trillion dongs, accounted for 3.1%. As estimated, 6 months’ constructional production value at 1994 comparison prices reduced 0.4% from the same period last year, of which the state sector decreased by 6.8%; the non-state sector increased by 0.8% and the FDI sector by 1.5%.
3. Labor and employment
The country’s labor forces aged 15 and above in 2012 were at an estimation of 52.7 million, rose 1.3 million from 2011, of which men accounted for 51.6%; women accounted for 48.4%. Laborers within the labor working age group were 47.1 million, rose 0.6 million, of which men accounted for 53.7%; women accounted for 46.3%.Laborers aged 15 and above working in the economy in 2012 were at an estimation of 51.6 million, rose 1.3 million from 2011, of which laborers working in the sector of agriculture, forestry and fishery accounted for 48.0%; in the sector of industry and construction accounted for 20.9%; and in the service sector accounted for 31.1%.
Unemployment rate of laborers within the labor age group in 6 beginning months of 2012 was 2.29%, of which it was 3.62% for urban area and 1.65% for rural area. Under-employment rate of laborers within the labor age group was 3.06%, of which it was 1.92% for urban area and 3.60% for rural area.

SOURCE: GENERAL STATISTICS OFFICE

                                                                                                                                                                                    

Saturday, 1 September 2012


CEIM Welcome Party for Aug2012 Batch 
with 
Dr. BHW.Hadi Kusumo & Dr. Santoso

Friday, 31 August 2012




THAILAND CONSTRUCTION DATA   


DATA SUMMARY
THE 2012 CONSTRUCTION AREA : Q1/2012



The National Statistical Office has collected data on permitted area both new construction, and addition or alteration since 1966. The data use for calculating the National Account, Real estate Indicators and for policy maker on economics and social development plan.

Data presented are the permitted construction area by municipal areas and Sub–District administrative organization with in building control regulation under the Construction Control Act : B.E. 2522 in 1Q12 of the nation. The main findings are follows as;

1. Number of permitted and construction area 
In 1Q12, the total permitted number of new construction building and addition or alteration were 43,432 persons, composed of 38,611 persons of construction building and 4,821 persons of civil engineering construction.

1.1 Construction building
The permitted of construction building with the floor area of about 15.8 million square meters, most of them (98.0%) were new construction and those of addition or alteration were 2.0%.
Comparing to the 4Q11, the permitted number of new construction increased by 17.0% and floor area increased by 12.8%. If compare to the 1Q11, the permitted number decreased by 6.1% and floor area decreased by 7.0%.

1.2 Civil engineering construction
For the civil engineering construction, the permitted number of about 4,821 persons, most of them (99.4%) were new construction and 0.6% was addition or alteration. In term of floor area such as the Car Park, Sport Ground, Petrol Station, Advertising Board, Swimming Pool, etc., there were totally 367,490 square meters. In term of the length of civil engineering construction such as Water-Drain, Road, Fence/Wall, Bridge, Dam etc., there were totally 445,424 meters.
Compared with 4Q11, the permitted number increased 14.1%. The floor area and the length of the construction decreased by 16.4% and 13.4% respectively.
Compared to the 1Q11 it was found that the permitted number of construction increase about
6.2% and floor area increase 28.0%. But the length of construction decreased by 27.9%

2. Type of construction building

2.1 The construction building
The Residential Buildings floor area of permitted were 10.3 million square meters (65.0%). Followed by Commercial and Office Building were 2.5 million square meters (15.8%).
The Industrial and Factory Building were 1.8 million square meters (11.6%). For Hotel Buildings
about 0.3 million square meters (1.9%). Education and Health Building were 189,698 square meters.
The overall permitted construction floor area (15.8 million square meters) increased of 12.8% from 4Q11, especially the Industrial and Factory Building increased by 133.3 %. The Commercial and Office Building increased of 37.1%. The Construction area for Residential Buildings increased about 12.1%. But the Hotel
Building decreased 74.4%, Education and Health Building decrease about 3.1%. from 4Q11.
Compared to the 1Q11 it was found that the permitted of construction floor area about 17.0
million square meters or decreased by 7.0%.

2.2 The civil engineering construction
For the civil engineering construction, the Water Drain construction was permitted about 253,248 meters (56.9%), there were 106,599 meters (23.9%) of Fence/Wall and about 76,598 meters (17.2%) of Road.
The total length (meters) of civil engineering construction permitted were 445,424 meters, decreased 13.4% from 4Q11, and decreased 27.9 % from 1Q11.
The floor area of civil engineering construction in term of the floor area such as Car Park was permitted 218,766 square meters (59.5%), Petrol Station was 29,420 square meters (8.0%).
Advertising Board was 14,946 square meters (4.1%), And Sport Ground was 17,359 square meters
(4.7%). Compared to the 4Q11, the overall permitted construction floor area was 367,490 square meters, decreased by 16.4% but 28.0% increased from 1Q11. 


Source :. National Statistical Office Thailand 









Friday, 17 August 2012



 PROJECT MANAGEMENT IN SUPERMARKET DEVELOPMENT -
A CASE STUDY OF SUPERMARKET PROJECT IN VIETNAM





By



 Tran Minh Nghia


Abstract
           
This report studied the owner’s project management in supermarket development in design, tender and construction phase. The first objective was to analyze the problems of the project management in design, tender and construction phase. The second objective was to suggest the solutions to resolve these problems.
The study found that the owner had some problems in organizational structure, project delivery system, design management, tender management and construction management (including project time management, project cost management and project quality management). Some recommendations were suggested to solve these problems to help the owner manage the project successfully.

Executive summary

Rationale of research                                  
This research has been conducted to identify project management process in supermarket development projects in Vietnam.
Objectives of study
To study the project management in supermarket development in design, tender and construction phase, To analyze the problems of the project management in design, tender and construction phase and suggestion of framework for the project management in supermarket development in design, tender and construction phase.
Methodology  
The exploratory approach was used to understand project management process at different stages through literature review, professional journal articles, and books.

Findings and conclusion

Owner’s construction project management takes an important role in the project development process. It has a major contribution to the project’s success. The study observed the owner’s development of supermarket project in design, tender and construction phases and concluded as follows:
In design phase, the relationship between the owner and the design professional is crucial. The professional services agreement between two parties is the key document in defining this relationship as well as the owner’s goals and objectives for the project. The owner monitors design activities by reviewing and approving contract documents, progress reports and other submittals which provide the opportunity for prompt decision-making.
In tender phase, the owner formulates a selection procedure that emphasizes the evaluation of constructor qualifications. The owner evaluates these qualifications and makes a list of bidders who are most likely to be capable of completing the project successfully. Because the owner has developed a great numbers of supermarket projects, they have a list of qualified contractors to select for bid. Therefore, they can save time for make a list of pre-qualified bidders. The bid consultant assists the owner in the contractor selection process.
In construction phase, the objective is to build the project in accordance with the plans and specifications within budget and on schedule. The owner’s project management focused on time, cost and quality of the project. The project time and cost management of the owner was adequate and suitable to procedures and principles. However, the project quality management of the owner was inadequate. The owner didn’t establish the quality management system which is an important factor impacted the project quality.

Recommendations


  • Clearly defined and assigned roles and responsibilities
  • Has qualified and experience manpower in construction project management.
  • The selection of an appropriate form of project delivery
  • Contract documents that clearly define the responsibilities of team members
  • Provide adequate funding.

Tuesday, 14 August 2012


DESIGN MANAGEMENT IN INFRASTRUCTURE PROJECT -
A CASE STUDY OF THE PHU MY 3 PROJECT





By



 Nguyen Nong Truong Thanh


Abstract
           
Infrastructure is the key to creating a dynamic, attractive, and thriving economic climate in communities around the world. It is important to nations’ future development and plays a critical role in creating and enhancing sustainable living conditions. Therefore, the planning, design and construction of full infrastructure system is of vital importance in developed and developing countries and in rural and urban areas, as it supports and connects our communities.
In recent years, the construction market have been swiftly blooming, especially the real-estate market in Vietnam. Thousands of the residential areas have been sprouting in the metropolis. This is one of important reason, why the government and the local authorities are attempting to invest and improve infrastructure system. This reason not only creating the huge market for construction consultancies but also raising these challenges for owners for managing these ones in design. Additionally, the owners have been facing the complexity of these infrastructure projects increasingly.
However, the role, the responsibility and the involvement of owner and consultant in each phase is unclear. Additionally, the design manager is not enough skills to meet the requirement of infrastructure project. As a result, the delay of pre-construction phase and the poor quality of existing buidlings as witnessed by the process of bad design management. The main purpose of this study is to conduct an intensive exploration and into the most problematic design management areas and to seek the invovement of owner and consultant and their skills as design manager in pre-construction phase for complex infrastructure projects in Vietnam, and assist owner and consultant finding appropriate solution and precise recommendations to improve them. Analysis of a case study in Vietnam suggests that owners requires careful planning, innovative managerial approaches, attention to behavioral issues, appropriate communication and information technologies, and mutual understanding of parties' roles and responsibilities.

Executive summary

Rationale of research                                  
This research has been conducted to identify problems in design process in infrastructure projects in Vietnam.
Objectives of study
To study the design management process and problems in the process for recommendations
Methodology  
The exploratory approach was used to understand the overall role of all sides in managing design and background of important design management with which design management problems are identified. Data were employed through direct interviews with the design managers, documentary evidence including all involved companies information on the internet professional journal articles, books.

Findings and conclusion

Design management is the way of how to get things done through the organization of design process is structured appropriately for project’s objectives, requirements, and resources. With developing market in Vietnam, the changes in legal always bring huge risk and therefore research to find out the suitable process for adapting the potential risk necessarily.
This study has successfully demonstrated an intensive exploration into the importance of design management in construction firm in Vietnam. A Concentration has been on analyzing and exploring the most arising issues in design management that significantly impact project performance. The findings resulted from thorough analyses based on the role and responsibility of design manager and the lack of skills for managing design work.
A case study has also been used that reflected major real-life problems found particularly in design management under a large and complex project in Vietnam, and closely related to the findings identified throughout the study.

Recommendations

According to the above results of analysis and assessment, illustrate that the current design management process has many serious issues that need to solve immediately to repeatedly avoid critical problems in future.
A good management process will effectively support for managers. It helps managers having a whole view of project aspects; detect the arising problems in the process rapidly, so that they can make a best decision to prepare errors. There are some following solutions need to apply to reducing minimal for the above process.

·         Firstly, the project manager must monitor ability of key individuals to know they can deal with their works by themselves or not in order to replace them instantly.
·         Secondly, the project manager must organize weekly meeting to monitor the project progress, know the arising problems, and let key members of the project can understand what they have been facing and find out best solution for them.
·         Thirdly, the project manager must avoid interrupting the project’ information. The issues and solutions must timely inform and send to key individuals via their email. If necessary, he needs to arrange an official meeting and ensure that they must participate fully.
·         Finally, the company must appoint a person to keep soft and hard documents by the best method in order to any people who take part in the project can easily find when they need but do not depend on the keeper or set sharing file for them.

Monday, 13 August 2012

Faculty Positions in Military College of Engineering,
National University of Science & Technology,Pakistan


Qualification: Masters, PHD in construction management

For Pakistani  Candidates


Please contact:

Dr Manzoor Hussain
Associate professor
Head of Department Transportation & Geo-technical Engineering
mhussain@mce.nust.edu.pk


Saturday, 11 August 2012



 PROJECT OWNER’S CONSTRUCTABILITY MANAGEMENT SYSTEM – A CASE STUDY OF SOUTH RACH CHIEC RESETTLEMENT AND RESIDENTIAL PROJECT




By



 Nguyen Hong Thanh

Abstract
             
This report expresses the main key issues in Constructability Management System that known as an important part for any organization wants to study and develop the constructability practices.
This report, which refers to some theories and the standards system, has expressed the concept of constructability practices in construction. These constructability theories and practices are in organization, in the owner side, requires for the owner’s constructability concept and practices in construction and its benefits. The study and its concept have briefed the main factors that most effect to the specific project studied from public reports and the key points to control project constructability concept and practices from the conceptual planning stage to construction stage. This report has introduced a constructability concept to the developers for the purpose of amendment to the existing constructability management system in order to obtain a complete constructability management system for better managing project.
The case study of this report is the case study on the South Rach Chiec resettlement and residential project that established to run and deliver an international project of the Keppel Land Vietnam. Via this project case study, the findings on the existing constructability concept, constructability practices and the application from the previous part to this existing constructability management system for improvement will be the foundation of constructability management system for toward Keppel Land’ projects.

Executive summary

Rationale of research                                    
This research has been conducted to identify constructability issues in residential building projects in Vietnam.
Objectives of study
To study current approaches to constructability practices in a complex functional project with high-rise building and commercial office, determine the methodology to improve constructability practices during conceptual planning stage, design and procurement stage, construction stage.
To study the problems occurring in constructability practices and provide the solution to adapt constructability practices and recommendations.
Methodology    
Initially five key issues of constructability are considered. They are: developing the project objectives and definition, project conceptual planning stage, project design stage, project procurement stage, project construction stage. Each stage offers a very important pros & cons opportunities for constructability improvements during those phases.
Data collection and gathering information from research theories. To develop comparison and applying those theories to the existing constructability management system, in order to improve it.

Findings and conclusion

Case study mentioned the understanding of constructability concepts applied in reality with limited acknowledgement of personal capacity. However, there are some observations from findings that might need to review to improve the constructability concepts and practices.
The company should improve following matter to enhance constructability in specific project as per discussion:
1. Contract Review
2. Selection of Consultants/Contractors/Suppliers or Procurement
3. Design Review
4. Process Control
5. Coordination and Communication
6. Control of quality records

In order to conduct constructability practices in the project successfully, the company would develop proper training courses to operation level and management level to be able to acknowledge the appropriate concepts of constructability.

Recommendations

  • Improve constructability concept and practices in project planning stage
  • Improve constructability concept and practices in project design and procurement stage
  • Improve constructability concept and practices in project construction stage 

Wednesday, 8 August 2012


STRATEGIC BEHAVIOUR APPLICATION IN MEDIUM-SIZE CONSTRUCTION: A CASE STUDY OF CAMBODIAN CONTRACTOR





By



Vannaro Kao

Abstract
             
The research aimed to study the strategic behavior application in medium size contractor in term of corporate strategies, business strategies, functional strategies, project operational strategies and strategic performance. Using an applied case study methodology, one road infrastructure construction company interviewing the president, general manager, each functional manager and senior project manager readjusted the strategic behavior theory in Thai contractors applying in Cambodian contractor. Under the case, the research findings of Hastheetham and Hadikusumo could be validated in case of Cambodian contractor. Moreover, the case proposed that the leadership style should be included as another component of project operational strategy. The readjusted framework could serve as a systematical guideline to develop integrated each level of strategic behavior and suggest the way of choosing an appropriate strategy in a specific situation.

Key words:      Strategic behavior, corporate strategies, business strategies, functional strategies, project operational strategies, strategic result performance, contractor.


Executive summary

Rationale of research
This research has been conducted to identify behavioural strategies of medium size contractors from Cambodia.
Objectives of study
The main objective of this research is to analyse strategic behavior application in medium size contractor in term of corporation strategies, business strategies, functional strategies, project operational strategies and strategic performance.
Methodology
The methodology for qualitative study is formed by instrument design, data collection, data analysis, and compiling the finding. Qualitative study methodology (Case study) has its purpose to fulfill the study’s objective which essays to study in medium size contractor of strategic behavior.

Findings and conclusion

The objective is to study strategic behaviour application in medium size contractor in term of corporation strategies, business strategies, functional strategies, project operational strategies and strategic performance. The literature review had been completely conducted to synthesize the key terminology related to strategic management in all level of the firm. The data analysis is purpose to validate the case of Arthasith’s strategic behaviour framework which is applied in Cambodia. To validate the data, the president and general manager of the firm ‘A’ are the key respondents to choose, to recommend, to advise, to adjust the attributes and provide more information the real firm practice.

Research Findings


The research findings under the case of Cambodian contractor are significantly valid the finding of (Hadikusumo & Hastheetham, 2011) in the theoretical framework of strategic behavior in Thai construction.
·         Besides, it is keen that the case in Cambodia proposed a very logical sense that company should know itself about the internal strength and weakness. The case suggested that expanding the horizontal growth whenever it intends to maximize the strength while extending the vertical growth whenever it intends to overcome its weakness.
·         Company could not implement Knowledge management as to manager the project via electronic media because of the limitation of communication infrastructure of Cambodia.
·         Further to another key finding that the case proposed is leadership style should be integrated into the project operational strategy since it is one of the key important success factors in the project.

Strategic behavior application in Cambodian medium size contractor case

Key implication of environment while the attributes finding stated below are the Strategic behavior applied in each level of company’s case from the top level management to the operational level. And it ends up with strategic performance measurement. The information of each level strategy is analyzed in detail and the framework which is applied and already adjusted by the case of Cambodian contractor.  The main factors found are:
·         Implication of environment emphasizing on the internal and external environment
·         Corporation strategy attributes are horizontal and vertical integration growth
·         Business level attributes are mode and scope competition
·         Functional strategy attributes include functional strategy, technology strategy, IT strategy, procurement strategy, HR strategy, and marketing strategy.
·         Interestingly, the project operational level attributes includes the leadership style of the project management and followed by project focus, project structure, project manager authorization, project knowledge management, and project communication.
·         The strategic performance is subjectively and objectively measured.