This is a blog managed by Construction, Engineering and Infrastructure Management (CEIM) at Asian Institute of Technology, Thailand. In this blog, CEIM shares our activities in providing excellent professional project management education at Master and Doctoral levels in Thailand, Indonesia and Vietnam. http://www.set.ait.ac.th/ceim/
Wednesday, 4 April 2012
Monday, 2 April 2012
HUMAN
RESOURCE MANAGEMENT IN CONSTRUCTION PROJECT A CASE STUDY – FOUNDATION PHASE OF
A CONSTRUCTION PROJECT EXECUTED BY SAIGON-RDC WORKFORCE
By
Phan
Hong Ngoc
Abstract
The
existence and development of an organization depend heavily on the exploitation
and efficient usage of all resources such as financial, physical facilities,
technology, human… these factors are intimate relationship and influence to
each other together, in which Human Resources is the most potential
determinant.
Construction
industry is deemed to operate by diversify workforce, hence managing human
resource issue deems to be a challenging task. However, as the role of Human
factors in the process of business and productive activities, Human Resource
Management is the key factor which has the immediate impact to the
organizational structure, especially in the Construction Industry, so Human
Resources are the most valuable source of Capital.
Realizing
the importance of the enormous direct impact of Human Resources Management to
the organization, the theme of “Human Resource Management in Construction
project” has been chosen for this Graduation Report.
This
study is to examine the
implementation of Planning and
Development of Human Resource Management in Construction Projects. The core of the study is to
optimize the specific area
of Organizational planning and Team development in enhancing the implementing of Construction Projects.
The problems that we always face such
as shortage of skilled labor
and dynamic work
force, lack of effective training
and performance in the Construction
Projects will be studied and evaluated in this Report. Research
results also indicate the improvement through the clear practices
of Human Resource Management in Construction Project, Human Resource Management will contribute
a significant positive impact towards the improvement of Project Management activities in Construction.
Executive summary
Rationale of research
This research has been conducted to identify best practices of
human resource management in construction projects.
Objectives of study
To
study practices of human resources management (HRM) in construction projects
towards performance, Develop a framework of HRM for project based
organizations.
Methodology
The exploratory method is used to review the literature and to
study, analyze HRM in construction
industry.
Findings and conclusion
Response to the study of the best practice
factors consider in Project Human Resource Planning and Development are as follows:
Best
practice of Project HR Planning:
- Fast
growth in exchange of Technology and Machinery operations.
- Organizational
structure with right people at right-time.
- Proper
Organization Structure and clear responsible Org. Chart.
- Proper
rewarding-scheme and good incentive wages.
Best
practice of Project HR Development:
- Continuous
improvement by recognizing of outside environment.
Positive
Impact in performance of the Construction project on:
- Efficiency of the project execution.
- Managerial and Organizational
Competencies.
- Personal Capability growth.
- Technical performance and innovation
creativity.
- Team Performance and interfaces.
Recommendation
For
practices of HRM in construction projects recommendation are as follows, which
can give a better way of managing human
resource in construction projects.
Objectives should be defined.
·
HRM Structuring should be there.
·
Need of performance assessment; Evaluation
·
Specific Job Objectives; Criteria’s for Promotion; Criteria’s for Transferring
must be defined.
·
Recruitment Flow-chart; Recruitment Procedure & System; Job Descriptions,
Criteria’s for selection.
·
Discipline; Grievance; the set process, Legal law & Regulations,
Work Obligations & Responsibility.
·
Feedback and appropriate action
·
Clear Salary Range; Formal compensation system & Software
·
Travelling, Extra Life Insurance
·
Organization Chart; Working Hours; Employment; Termination;
Payment; Turn-Around-Time;
·
Labor-Union Relation; Collective-Labor Agreement
·
Health Insurance; Medical Insurance
·
Accident Insurance; OS&H System, Safety Equipment
·
Orientation Program; On-Job-Training; Managerial & Leadership
Training
·
Staff Training; Technical Training; Operational Training; Training
Plan
·
Management Development, Career Path
·
Performance Review; Staff supervision;
PRE-CONSTRUCTION DELAY IN
BUILDING PROJECT DEVELOPMENT
A CASE STUDY OF “INVESTCO BABYLON ” PROJECT
IN HO CHI MINH CITY
By
Nguyen Tran
Toung Ly
Abstract
During construction, a project is considered
successful when it meets three basic conditions: completed on time within the
approved budget with quality to meet customer requirements and current
standards quality. As well as in the investment Real Estate projects, the above
three important elements are in close contact with each other. The Real Estate
needs turnaround quickly, so that the new Real Estate market can be
developed. Furthermore, according to
HOUSING LAW, the owner can only sell the product after having completed the
foundation works. This means that to have budget to continue to have completed
projects, the owner have to accelerate the pre-construction work. However, most
current construction projects in Vietnam are delayed, especially in
pre-construction phase. This shows that the project manager has not done their
job well. Therefore, the investigation the causes to delayed in
pre-construction phase and find solutions to reduce this problem is necessary
to have better job in management of projects in Vietnam, and help to solve the
puzzle of the Real Estate industry.
To solve this problem, first, determine the
cause and extent of impact, and then the important factors that need to resolve
will be recognized. Therefore, this report will identify, evaluate and analyze
the factors that cause delayed in pre-construction phase in Vietnam. Based on
the method of assessing the impact of each factor and then suggest prevention
solutions, in order to eliminate similar mistakes in the future.
Case study is used for researches and discussions
are: INVESTCO BABYLON - The High-Rise Apartment Commercial Office Building
Project.
Executive summary
Rationale of research
This research has been conducted to identify factors involved in
pre-construction delay in building project development.
Objectives of study
To
identify the delay and causes of delay in pre-construction stage, investigate
the impact of delay on overall project, and propose recommendations for improvement.
Methodology
The exploratory method is used to review the literature and to
study, analyze the pre-construction
delay in high rise commercial project.
Findings and conclusion
Delay has always been an unsolved problem to the construction industry
worldwide since then. However in developing countries, delay is more serious
because in addition to those caused by human, the weather, the Government
Policies are still inadequate.
“In fact, the administrative procedures in
construction investment are still complex and time consuming, especially for
the new urban projects, housing projects, the technical infrastructure of
industrial parks. Ministry of Construction have already in cooperation with the
People's Committee of Hanoi, Ho Chi Minh City and some of enterprises started
to review the administrative procedures of a some of projects in the area of
Hanoi City Ho Chi Minh and Ha Tay Province and the results showed that the
number of project’s procedures are still many (about 33 procedures / 1 project),
preparation time was long (average 3 years / 1 project). There are still some
procedures issued by local authorities or request the investor to proceed
without the provisions of the Government’s permissions, and some procedures in
the legal documents are insufficient need to be reviewed to consider
improvements to match the fact.”
This led to delay in pre-construction stage is
the most significant and take longest time. Therefore, the identification of
factors that cause serious delay and then to propose to restrict, prevent or
remove are sorely needed.
Recommendation
For Project Manager
·
Each
individual responsibilities and rights must be clearly defined.
·
Set up
the clear project Development Process Flowchart.
·
The
working conditions should be improved gradually aiming at building proper
working atmosphere.
·
Project
Manager should give feedback to the company Quality Manager to add in
personality test forms together with Job Application Assessment Procedures
forms base on ISO.
·
Relation
divisions always have the plan to solve problems with the method soon.
·
The
weekly meeting is very important , all problems will be resolve on that meeting
and relation division have limited time to return the request for information
to Designer or for Agreement from Government.
·
The
payment during project implementation, for example: land using fee, are a big
problem. Project will be delay have some reason relate to this problems. So the
Project must be actively capital.
For Project Employee
·
Trying
to self-improvement skills.
·
Set the interests of work to the highest.
·
Recognize
delay problems which will lead to large losses as well as benefits of the
project completion on time.
·
Monitor
the Design Consultant’s works of every period, if any changes happen, Design
Consultant must be accelerate in next period for catch up schedule.
·
Exchange
information dissemination and unified design concept from the start to avoid
the disagreement.
For Human Resource Department
·
Organization
training the Project Construction Management Group in order for them to know
how to use the process to accomplish project and contract condition.
·
Build an
ideology for all employees so that they can recognize delay problems which will
lead to large losses as well as benefits of the project completion on time.
Simultaneously, top management should establish a fair reward and punishment
policy which has to be strictly applied.
·
Wage
policy should meet the minimum standard of living. This will reduce the
pressure of economic and help managers focus on their work fully and
integrally.
·
It is
necessary to build up the relationship between benefits from the project
completed on schedule and the benefits of project manager and participants.
·
The project management training should be
paid more attention in the future. It should be the main goal in Construction University. It is not
only reduces delay problem but also enhances the success probability of
construction project. Not only project manager must be educated professionally,
but also their capacity has to comply with the assigned duty.
·
Employees of Government could make
difficulties for process. This intricate question not only happens in Vietnam
but also in developing countries. To restrict this problem to a minimum, the
wage policy should satisfy actual living standard and establish a strictly
reward or punishment
·
The procedures of legal regulation in
imports and some other areas have remained very limited and inadequate. To be the
member of WTO is a challenge which forces Vietnam to improve this legal
procedure. This legal process not only in import-export but also in the other
fields must be clear and transparent. This will help project planners to have
the basis to plan for their projects accurately. If this procedure is not
improved soon, Viet Nam will be left behind, compared to other countries in the
region and we, will be faced with great damages.
Sunday, 25 March 2012
ANALYSIS OF DEVELOPER’S MISTAKES IN APPRAISAL, APPROVAL AND PERMIT
ISSUANCE OF THE CONSTRUCTION INVESTMENT PROJECT IN HO CHI MINH CITY
By
Nguyen
Thi Thu Nga
Abstract
For construction investment
projects, the investment project time of performance directly affects the
investment efficiency. However, in the recent years, in Vietnam, the management
and the control of “the time of performing construction investment project in
Vietnam” has not been interested in and strictly managed, thus leading to many
projects delayed in a long time, badly affecting the economic development and
social living, especially as for projects using State budgets. Accordingly, the
time of performing the procedures of submitting and approving investment
project documents and asking for the permit of constructing the project is
always troubling the heads of investors and spends so much time. Thus, it seems
challenge for project management consultant, the owner, especially to the
foreign investors!
On PMC aspect, how to ensure
reducing the time for doing project procedures is one of the critical points
that I focus to study. My research is based on surveys about the normal problems
on approvals and permit phase of the construction project. This assessment is
studied together with theory application for the process, procedure of the
construction investing project approval and construction permit, the regulation
compliance in the construction; What to be prepared, done shall be systemized
as a well being prepared for future projects and a contribution to improve
overall the quality of the construction project document through approval and
permit phase.
Executive summary
Rationale of research
This research has been conducted to identify mistakes in
investment project document for approval.
Objectives of study
To
study, and find the appropriate investment project document without errors to
get approval, identify difficulties, mistakes and causes in different stages to
suggest recommendation for getting approval of construction investment project.
Methodology
The exploratory method is used to review the literature and analyze the survey difficulties and mistakes
happened in project approval document.
Findings and conclusion
Through this research, we can identify faults
discovered during the appraising process of
the construction investment project document and document asking for
construction permits
The common mistakes in investment
project document are follows:
·
Procedure
for adjusting the total investment quotation in the designing process
·
The
manner and the form of capital contribution
·
Fees
of evaluating the working drawing design and the cost estimations
·
Procedure
for approving and re-adjusting the project
·
Estimation
about the whole investment quotation
·
Constructive
criteria and norms for the emergency
·
Constructive
criteria and norms for disable people
·
Conformity
of the connection with the technical infrastructure of the area
·
Design
for the basement
·
Concerning
the anti-shaking
· Design
for traffic inside the building
· Concerning the project of total
height > 45m
·
Designing
ventilating height of the rooms
·
Designing
the size of the public community hall
·
Not
conforming to Design /Construction Standards & Construction Rules
·
Demonstrating
wrongly or not clearly the road limits of the lanes adjacent to the site
proposed for construction, leading to a wrong indentation of the project.
·
Lacking or not conforming to detailed planning
legality
·
Lacking
ideas of one or several relevant authorities about the proposed project
·
Lacking land legality
Recommendation
For Project Planning Consultant
·
Paying
more attention for frequent mistakes and often review design before submitting
document for approving.
·
Collecting
and carefully considering all codes and standards usually used in
design/construction activity in order to appropriately applying with each
function of building.
·
Clear
descriptions of using size and sort of functions have been showed on design document
·
Doing well the
survey of the current technical infrastructure before designing the technical
infrastructural system of the project
Project-planning
stage:
·
The
project-planning work is clearly carried out for the whole project in all
stages.
·
Conduct
socio-economic survey in detail, using the survey information from independent
survey sources.
·
Research
and offer all technical arguments to justify the selection of the site of
developing the project.
·
Analyze
and calculate intangible elements affecting the project such as the inflation
element, spiraling price; new guidelines and new policies of the Government
directly affecting the project.
For Owner
·
Together
with consultants well preparing all procedure for
defining deliverable, evaluation, report, assessment. (Quality assurance
system)
·
Choosing
a potential, experienced and prestige design consultancy unit in the designing
work;
·
The
more detailed the economic contract contains, the easier the faults are handled
once faults caused during the stage of making and evaluating the project
appraisal
·
Should
use the model design of several social infrastructure works such as apartment
buildings, schools, head offices of commune-level people's committees and
health clinics to reduce the cost of design consultancy
·
Prepare reality design management program for obtaining target
expected (containing time for review, revising, approval)
·
Verify scope signed in contracts for anticipating gap in the
approving work and asking for permit.
·
Monitor designs and project works to be integrated with operators
closely.
For Government
· Encourage an architectural design
contest for the projects financed by the State budget in addition to compulsory
projects for pre-qualification in order to exclude the less capable units.
Therefore, the design quality will be assured.
· All of detailed plans in the
territory of Ho Chi Minh City completed as soon as possible.
· Build the mechanism of
transparency in the field of investment planning.
· It is to further speed up
administrative reforms, reducing troubles in fields as granting building
licenses and granting investment licenses. .
· The implementation of strict
sanctions against violation of rules
CONSTRUCTION
MANAGEMENT IN PROCESS
PIPING
INSTALLATION
CASE
STUDY OF DUNG QUAT POLYPROPYLENE PROJECT
By
Vu Van
Tinh
Abstract
Petroleum industry has had a lot
of contributing to the economics of Viet Nam country since the first flow of
crude oil was exploited in 1986. Specific that, every year, petroleum industry
contributes from 20 percentages to 30 percentages of gross domestic product and
becoming the key industry in Vietnam. Petroleum industry is one of high
technology and complex technology that require attending all the main
technology such as civil, mechanic, electric, instrument…in to one to
contribute the project. Especially, refinery plant and petrochemical plant
where normally to use high technology in process industry. Process piping
installation is one important item in building the refinery plant and
petrochemical plant.
In the side of contractor, this
project case study will concentrate to provide basic knowledge of construction
management that applies in process industry.
The project case study will
consider to real process piping installation in the project that is Dung Quat
Polypropylene project in Quang Ngai province of Viet Nam. Actual subject will
show, analyze, evaluate and with draw and recommendations.
Finally, the project case study
will compare the construction management in actual project with basic knowledge
to have some conclusions.
.
Executive summary
Rationale of research
This research has been conducted to identify the problems in
project management of piping installation projects.
Objectives of study
To
study, and understand project management process of piping installation project
and to discuss strengths and weakness for project management procedure to
suggest recommendation for improvement.
Methodology
The exploratory method is used to review the literature and study installation of gas pipe line process and
project management methods.
Findings and conclusion
Construction
management in process piping installation is difficult and complex work that
requires us must to have high effort to reach the target of project. Through
the case study we can understand the main factors.
Basic knowledge of construction
management in process that include some factor such as organization management,
resource management, quality management, health and safety management, risk
management, construction planning and control.
The case study also provides some
feature and main factor in the contract that normally apply in construction of
process industry. The case study also introduces one real project – Dung Quat
Polypropylene project. Almost the factors in construction management in process
piping installation were implemented by one mechanical division. So, we can
understand the important of knowledge of construction management.
Recommendation
·
Working
method statement must be made with care by considering all factor including
inside and outside of project.
·
Work
checking system must be maintained on regular basis, that include understand
exiting status of work and having predict the situation in the future.
·
Fast
response to any condition
·
Good communication in construction is
contributing the effective of work.
IN
BAU SEN BUILDING PROJECT
By
Vo
Thanh Phong
Abstract
Variances
in the financial model of a project are unexpected by all involved parties at all
times since they are the critical items turning the project into a loss from an
expected profit. There have been a lot of studies on this subject, but usually
it is done after the project completion to find out the causations and
solutions to those problems to be referenced in the coming projects.
In this
report variances in the financial model between the model being made in the
feasibility study and the model made after the detailed design will be analyzed
in order to find the critical variant items. Assumptions in the critical
variant items will be then investigated to deeply understand the causations.
Recommendations will be proposed to improve the process of financial modeling
for the coming projects.
.
Executive summary
Rationale of research
This research has been conducted to identify the variances
between financial model for feasibility and financial model after design.
Objectives of study
To
study, and understand financial model at feasibility stage and after stage to
identify critical variant items, how they affect cash flow and income of
project.ans propose recommendations for improvement.
Methodology
The exploratory method is used to review the literature and study Design for data to put into financial
model. And critical activities of two financial models will be compared to find
out the variances and causes to propose recommendation.
Findings and conclusion
The above analysis illustrates all the
problems of this project and shows clearly the responsibilities of all the
involved parties in the project.
Why
big variances in the financial model made between the feasibility study and
after the detailed design occurs is answered here. It is obvious that the
owner’s competency, the consultant’s capability and state policies are the main
causes of those variances.
Moreover,
mal-practices of financial modeling and project management also play an
important part in causing those variances.
Also,
lack of collaboration among the stakeholders and unsuitable organizational structure
of the corporation makes assumptions inaccurate and unreal.
As
a result, the owner is the one who will suffer from the loss since those
variances increase the total investment cost dramatically and turn the project
into a loss.
However,
the owner cannot escape due to their big cost input and commitment to the local
authority to proceed the project. Moreover, they cannot insult their trade
brand in the local area as well as on the market. What they can do is to adjust
the project to make it marketable and keep the loss to a minimum level.
·
The
owner should use an appropriate procurement process for consultancy to hire a
competent consultant from the beginning of a project to carry out the designing
of all
·
They
should make agreements with all stakeholders in the project to get them assist
in comments on assumptions as well as other technical issues in all project
stages to make sure the project is on the right track.
·
Matrix
structure in the organization should be used and responsible people should be
appointed to manage the project effectively.
·
Data
for assumptions should be from researches and surveys to be trustable.
·
Components
of the financial model and items in those components should be checked
carefully to be sure that they are sufficient for effective analysis.
·
There
should be an update and forecast for related regulations intended to be issued
to reduce political and commercial risks to a minimum level.
Monday, 19 March 2012
Opening Ceremony of MPM intake 2012 in Can Tho city
On March 02, 2012, MPM organized an Opening Ceremony & Welcome Party for the 2nd entry of the Professional Master Program in Project Management in Construction (MPM Program) in Can Tho at the Ninh Kieu 2 Hotel on Friday, 02 March, 2012.
This event was attended by Dr. Amrit Bart, AITVN Director; Dr. B.H.W. Hadikusumo, MPM Coordinator; Mr. Nguyen Thanh Son, Chairman of Can Tho city People Committee; Mr. Duong Thai Cong, Rector of Can Tho In-service University Center; Mr. Huynh Van Duc, Manager of Administration Department, Learning Resource Center, Can Tho University.
Presented at the ceremony, Mr. Nguyen Thanh Son, Chairman of Can Tho People Committee, has given his speech to congratulate MPM program with new batch in Can Tho and wish MPM a strong development for the contribution of developing highly qualified and committed professionals who will play a leading role in the sustainable development of Can Tho and Mekong delta.
The ceremony was followed by dinner party.
Speech of Mr. Nguyen Thanh Son, Chairman of Can Tho city People Committee.
Sharing from MPM Can Tho alumni, Mr. Ta Chi Nhan, Deputy Director of Can Tho Department in Construction.
Group photo with new MPM Can Tho students 2012 intake and MPM alumni.
On March 02, 2012, MPM organized an Opening Ceremony & Welcome Party for the 2nd entry of the Professional Master Program in Project Management in Construction (MPM Program) in Can Tho at the Ninh Kieu 2 Hotel on Friday, 02 March, 2012.
This event was attended by Dr. Amrit Bart, AITVN Director; Dr. B.H.W. Hadikusumo, MPM Coordinator; Mr. Nguyen Thanh Son, Chairman of Can Tho city People Committee; Mr. Duong Thai Cong, Rector of Can Tho In-service University Center; Mr. Huynh Van Duc, Manager of Administration Department, Learning Resource Center, Can Tho University.
Presented at the ceremony, Mr. Nguyen Thanh Son, Chairman of Can Tho People Committee, has given his speech to congratulate MPM program with new batch in Can Tho and wish MPM a strong development for the contribution of developing highly qualified and committed professionals who will play a leading role in the sustainable development of Can Tho and Mekong delta.
The ceremony was followed by dinner party.
Speech of Mr. Nguyen Thanh Son, Chairman of Can Tho city People Committee.
Sharing from MPM Can Tho alumni, Mr. Ta Chi Nhan, Deputy Director of Can Tho Department in Construction.
Group photo with new MPM Can Tho students 2012 intake and MPM alumni.