Monday 9 July 2012



 VARIATION CLAIMS IN HIGH - RISE BUILDING PROJECT




By



 Krisana Juanwanpen


Abstract
             
This paper presents a study made on causes, effects and controls of variation orders in high-rise building project in Thailand. To achieve the study objective, the researcher carried a literature review of the subject previous research studies and books written on the subject of variation orders. In light of the literature study the researcher developed a survey case study.
The big challenge for Thai Construction industry is to advance the management styles to cope up with challenges faced in a project. Procedures in managing contract and variation orders are viewed to know the effectiveness and liability ensuing steps observed. Disruptions in cash flow and program when mitigated and handled correctly may create confidence in handling changes that transpire in any project.
However, knowledge and skill in managing this challenging changes and observing effective procedures may eventually create a norm in Project Management system in the industry where tradition of strong relationship among Owner and Contract still prevails.
Literature relative to the research area was extensively reviewed. The data gathering approaches included an exploratory study on costs of variation orders on high-rise building project, interviews with three managers and seven engineers in construction site, and the audit of site instructions with regard to waste and their value-addends and self-administered questionnaires. A purposive sampling method was followed to identify participants into the study.
The study also concluded that responses from contractors and consultants agree about the causes, effects and controls of variation orders and recommended to include the owner in future studies to verify the reasons behind changes made by the owners.

Executive summary

Rationale of research
This research has been conducted to study variation claim issues in high rise building  projects
Objectives of study
To identify types and causes of variation claims in high-rise building project in Thailand, how to prove claim in different types of work in terms Analysis for additional cost and to propose an effective negotiation on the accepted price and time for both contractor and owner.

 Methodology
The exploratory research method is used to study variation claims, and with extensive literature review about variation claims and analysis of additional costs.
Findings and conclusion

The research set up to analyze the leading cause of variation orders on high – rise building project, to identify project characteristics correlated with frequency of construction variation orders, to develop variation order reference that identify the structured methodology for pricing variation orders. After completing these objectives, it was determined the causes of variation orders on this project.
Project characteristics were also examined. The breakdown of the project into five categories such as:
·         New work – are the additional item in the some part of building for more suitable and aesthetic of the building. Frequently, this category is initiated by owner
·         Modified work – are the existing of buildings becomes unsuitable for their present use, and then improvement, repair and maintenance are often required to keep them in usable condition.
·         Change work – are covered amend in some parts or whole scope of work that is stipulate in the contract
·         Move work – are Moving things without creating any damage to those items including storage of those items, they assume a duty to be included in this section.
·         Demolishing work – are move the existing part out and would not be reused. And the occupancy of debris that comes from the demolishing process will be agreed before starting work.

From analyzing the different methods used in these examples, a standardized pricing flowchart was developed for use. The flowchart was designed to be a one page quick reference that could be used for most situations involved in preparing an estimated price for comparison to the contractor’s submission. The flowchart still allows for the consultant to use some professional judgment but gives enough pricing options to take away some of the uncertainty in producing a price. A standardized pricing procedure implanted across the state will improve variation order pricing consistency among districts. This tool can be used also in training new engineer to allow them to progress in their decision making process.
Finally, based on the findings, it can be concluded that each of the condition of contracts has stipulated clearly the rules for method of valuing the claims of variation works. However, the adequacy and appropriateness of the mechanism are different based on the different types of contracts. The selection of the type of contracts to be used for a particular project may influence the project implementation in terms of contractual administration related to claims for variation works. By selecting an appropriate type of contracts for a project to be implemented may reduce the tendency of disputes arising from valuation of variation claims. Disputes related to claims of variation works can be avoided by overcoming the problems of the disputes. This may only be achieved through the proper selection of type of contracts which contain the most effective methods of valuing the variation claims. Despite the fact that BQ rates/Contract rates is the most instant method and agreeable among the contracting parties, it is recommended that this method should be improved by rationalization of the rates accordingly depend on the nature of the work of similar character executed under similar conditions. In other words, the BQ rates/Contract rates despite being the most agreeable rates they should be adjusted accordingly so that the rates for varied works will be fair to both contracting parties.

Recommendation


·         Out-Source Information - for variations that need price comparison, outsource information must be obtained such as price indices from the government, quotations from suppliers and price information from consultants.
·         Data collection – is to collect the correct information to support the validity of the any variation order. It can be Site Records such as site diaries, weather charts, site instructions, inspection reports, shop drawings and materials approval, RFIs, NCRs and other forms of communication like emails, transmittals, minutes of meeting and project reports.
·         Investigation - For variation order due to differing site conditions, sit investigation is imperative. It is essential in determining the actual site situations and for observing if the proposed change were feasible to the site. It is also done to verify quantities, type of material applied by the contractor and to confirm the methods proposed for application for use.
·         Know your references - reference materials would be the basis for evaluation first, entitlement of the contractor to a variation order, validity of the change, and determination of quantities either additive or deductive. Reference may include Construction Contract, Drawings, Specifications and other forms of site communications.

Friday 6 July 2012


Asian Institute of Technology in Bangkok
Construction Engineering & Infrastructure Management
BIM – Will it transform the industry,or will it be business as usual?

by
Dr. Henrik Linderoth
Associate Professor
School of Technology and Society
University of Skövde

Thursday 5 July 2012



ORGANIZATIONAL FACTORS AFFECTING BEHAVIOR BASED SAFETY PROGRAM AND PERFORMANCE: A STUDY IN OIL AND GAS CONSTRUCTION PROJECTS IN THAILAND




By


Jittanun Phuangphay

Abstract
             
The construction industry is a dangerous job when compared with other sectors because the nature of construction projects is very complicated. Many of the activities within the construction industry are associated with accidents and diseases. Safety Management System is one of the key things that the project should be concerned with especially in Oil and Gas Projects in Thailand. In depth, the project looks at the safety behavior of individuals to solve the safety related issues in the workplace. Therefore, this study was carried out to identify the factors that affect the behavior based safety and to study effective behavior based safety concentrating upon methods and practices by performance of the worker behavior.
To achieve the objective of the study, 8 main factors for the study were identified affecting behavior based safety. In addition, there are 10 factors under implementation for behavior based safety methods and practices which help to measure the safety behavior of worker. The study was conducted through Quantitative Research. Statistical hypothesis was done using the correlation model with SPSS program to find out the factors affecting behavior based safety and to find out the effectiveness of behavior based safety methods and practices in Oil and Gas Project in Thailand. For this purpose, the questionnaire intends to seek answers from the Director, Safety manager, Safety engineer, Safety officer of the project.
Moreover, to achieve another objective of the study, the organizational factor is very effective on worker’s safety behavior because all of the factors inside the organizational factors come from the vision, mission and perspective of top management level. However, the behavior based safety is less effective on worker safety behavior when it is compared with the organizational factors because all of factors inside behavior based safety implementations methods and practices come from the management of operation level.
Furthermore, the findings also suggest important factors needed for the implementation of the project to understand the strengths as well as the weaknesses of the behavior based safety methods as well as to talk about the important factors impact on behavior based safety. Therefore, the Safety officer will carefully understand the impact of their worker’s safety behavior. In addition, recommendations for further studies are suggested.

Executive summary

Rationale of research
This research has been conducted to understand the behavior based safety in oil and gas construction industry of Thailand.
Objectives of study
To study effective methods and efficient practices in behavior base safety implementation and to identify the organizational factors affect to behavior based safety. To examine the influence of factors and implementation (methods and practices) on worker safety behavior
Methodology  
Using questionnaire to collect data and interview the expert in the project at least the medium construction company in Thailand. The respondent of this study are the safety managers and project manager on Construction Company.
This study consists of conceptual stage, conceptual framework, hypothesis development questionnaire, data collection, data analysis and conclusion.

Findings and conclusion

This study is considered about the safety issue in construction industry especially in Oil and Gas sector. Because the construction industry involves dangerous work because the construction job is very complicated and involved many different parties, each activity is always participating with accident and injuries. Therefore, in construction industry, they always the company have to concern about safety as everybody safely. Therefore, this study tries to find which organizational factors affect to implementation methods and lead to worker behavior base safety. The main objective of this research is “to study factor that affects behavior base safety. Second objective is to study effective behavior based safety implementation (method and practices). In addition, to finding the factors, this study was reviewing discussing from many research, and theories, those who emphasis on effective safety system. Also, this study has been interviewing with the expert person.
Although the data collection requires many projects for corporation, most of them are busy with their job. Therefore, some projects did not attend, interview, and support to answer the questionnaire. Only the projects that realize the importance of academic research have paid attention in this study and allow collecting the data. There are 15 companies with 36 projects and 36 respondents in data collection. Most of the project locations are in Rayong province. The research was collect in contractor of oil & gas Construction Company. The framework of this research is tries to find the factor affect to the implementation methods and practices. In addition, this factors leads to improve the behavior of safety worker. There are 8 factors to study in this research; safety policy, top management commitment, company strategy, leadership, accident cost reduction, total quality management and quality improvement, customer requirement, and corporate social responsibility. Moreover, The behavior based safety implementation method and practice are including 10 items in this research; setting safety goal, assessment, training, coaching, observation data collection, rewarding, warning, safety communication and feedback, safety talk and tool box meeting. As showed all factors in this research, these factors were found from determining previous research and many theories.

Tuesday 3 July 2012


A RISK MANAGEMENT FRAMEWORK FOR HIGHWAY
CONSTRUCTION COMPANIES IN VIETNAM



By




Pham Quang Cuong

Abstract
             
Highway construction industry is long known to contain more risks than many other industries because of the effect of a variety of uncontrollable factors and the severe competition degree. However currently in Vietnam the understanding of highway construction companies about risk management is very poor, lacking of a clear identification of risks and the methods to deal with these risks systematically. The purpose of this study is to identify and rank the risks facing the highway construction companies as well as to determine the risk responses that effectively help the contractors to handle them.
This research is based on quantitative method, using questionnaire for data collection and utilizing SPSS software to analyze the data.
The respondents in this research are directors and experienced project managers from sixty different contractors. The respondents are asked to assess the risks and the degree of the application of risk responses in their company as well as to provide the information related to the corporate performance. The risks afterwards are ranked in terms of probability of occurrence, severity and impact and then the risk responses with strong correlation with corporate performance are pointed out.
The outcome of data analysis is the ranking of risks that will help increase the attention of the Vietnamese contractors to the critical ones which might threaten their project success.
The effective risk responses with strong correlation with project performance are listed and are put into the relevant stages of project life cycle to form the risk response framework.
This framework can be considered as an action guide that the highway construction companies should apply as strong as they can to make their projects more secured against the risks.

Executive summary

Rationale of research
This research has been conducted to develop frame work for risk management in high way construction projects in Vietnam.
Objectives of study
To identify major risks & emerging risk to highways contractors, risk responses and its relation with company’s corporate performance and to develop a framework for highway contractors.
Methodology  
The exploratory research method is used to study risk management in highway construction companies, through literature review, case study from Vietnam.
Findings and conclusion

The first objective is to assess the risks in terms of probability of occurrence; severity and impact, afterwards the ranking of risks are made in order to increase the contractors’ awareness towards critical ones. The second objective is to examine the application of risk responses which are developed through a deep literature review and interviews with Vietnamese experts. The risk responses will be evaluated based on the belief that the contractors with good performance will have better responses to risks and in turn, the good risk responses will enhance the performance of the contractors at both project level and corporate level.
As a result the correlation between the application of risk responses and the corporate performance is analyzed and the ones with the correlation coefficient larger than 0.7 are pointed out. The final objective is to put the effective risk responses into the relevant stages of project cycle to form the risk response frame work that can be applied by highway contractors to their projects.

Critical risks
The analysis result reveals the fact that the unstable economic conditions and the macroeconomic factors such as high inflation (rank 1), high interest rate (rank 2) are putting a lot of difficulties upon the highway contractors. Other big concerns come from the owners including Delay in delivering the site (rank 3), delay in progress payment (rank 4) and financial difficulties (rank 5). In top 15 of critical risks, there are some risks resulted from the poor management of the contractors themselves including Shortage of cash flow (rank 6), Too low bidding price under competition (rank 7), Inappropriate construction methods (rank 9), Poor performance of sub-contractors and suppliers (rank 10) and Poor quality and rework (rank 11). Consultants are an important party in projects and they contribute some significant risks to the work of contractors namely Site condition discrepancy (rank8) and Delay in testing and acceptance procedure of supervisors (rank 13).

Effective risk responses and risk response framework
The risk responses that can be applied to deal with every single risk are discussed in depth and the effective one which have the strong correlation with the corporate performance are pointed out. These risk responses are grouped into action categories and are put into the relevant stages of project lifecycle with the hope to provide a more systematic approach to these risks. The data analysis and the interview with experienced experts during data collection reveal many weaknesses of the contractors that make them vulnerable to risks. The cost estimate is the first thing that requires the more careful consideration and preparation of the contractors because it directly relates to the chance of winning the contract and the profitability of their work.
The contract content is another problem to the contractors because if the contractual clauses are provided poor and unclear they will become the source of many risks in the next stages. In the opinions of many respondents the contract in highway projects are still in a very low level in comparison with the contractual form suggested by FIDIC. The quality of construction planning and the tight construction control play the important role to mitigate or even eliminate the impact of many risks especially the on-site risks. 

Monday 2 July 2012

INVITATION FOR SEMINAR           @

Asian Institute of Technology in Vietnam (AITVN)
Master Program in Project Management in Construction (MPM)
BIM – Will it transform the industry,or will it be business as usual?

by
Dr. Henrik Linderoth
Associate Professor
School of Technology and Society
University of Skövde

Date: Friday, 13 July 2012
Time: 09.00 - 12.00 hrs.
Venue: Room A1.1, 45 Đinh Tien Hoang, Ben Nghe Ward, Dist. 1, HCMC (Opposite to HTV broadcast station)
Vietnam 

Abstract
The emergence of new technologies has always triggered visionary ideas of changes of the state of art in organizations, industries and society. However, what we know from research is that changes do emerge, but often not as fast as expected and not in the directions predicted in the visionary ideas. In this sense BIM – Building information models – is no exception. The transformative capacity of BIM and its potential benefits has been discussed for two decades, but it is only during the last few years a more encompassing deployment of BIM can be witnessed. However, challenges still exist for management before any deeper impacts on the industry will be achieved. The challenges to solve can be viewed as layers of challenges in at least four categories: technical, legal, organizational and managerial. During the seminar these challenges will be discussed and I will draw parallels with a similar process in the health care sectors that I have studied for ten years. It appears that at the bottom line is the issue: Who are the beneficiaries and who has the power to shape the process?
All interested persons are cordially invited. For further details, please contact Ms. Nguyen Le Tuong at (+84) 01 265 285 168 or (+84) 08 39107423 (117) - email: ngletuong@aitcv.ac.vn. 

Friday 29 June 2012


LEAN CONSTRUCTION: DEVELOPMENT OF ASSESSMENT CRITERIA & IMPLEMENTATION STRATEGY FOR INDIAN CONTRACTOR COMPANIES




By



Ranjeet Sandeep Pundlik


Abstract
             
The construction industry in India is one of the highest contributors to the national economy for over the past five decades and is one if the biggest in terms of generating employment in the nation after agriculture industry. This industry is a victim of low productivity, poor performance, lack of mechanization & sophistication, lack of skilled labors, shortage of professionally qualifies employees, cost over runs and delays. Lean construction is a recent development in the field of construction which aims for waste reduction and value generation for the client by increasing the efficiency of the construction processes by improving the processes and flows in the construction activities. Lean construction is successfully implemented by various companies the western countries and is also an important topic for researchers across many universities in the west. So this study aims to develop a system for the construction contractors in India to be able to use and incorporate the techniques of this domain of construction. The research has broadly identified 12 lean principles applicable to construction, especially in India. Development of a Generic model for the lean functioning of the departments of a construction contractor companies was done and lead to the identification of 33 lean practices in the five departments of the contractor companies. This lead to the development of assessment criteria for the lean compliance of the departments of the contractor companies in India. This model and criteria, after being verified and validated by 3 academic and 2 professional experts in India, was used for collection of data of compliance from 4 Indian Contractor companies, functioning in Central India. Detailed analysis of the working of each department of each company has been done to determine the strength & weakness of each department and also determine the reasons of non-compliances of the practices.
After the detailed analysis process, a strategy for the implementation of these lean practices in the departments of the contractor firms in India has been developed. The three stage strategy, along with the weaknesses and non-compliance reasons can be used together to combat the problems for implementation and hence the lean practices can be successfully implemented by Indian Contractor Companies.

Executive summary

Rationale of research
This research has been conducted to develop assessment criteria and implementation strategy of lean construction for Indian contractor companies
Objectives of study
To develop a model for assessment of departmental functioning of contractor companies and perform detailed analysis to find strengths and weakness, to propose implementation of lean practices in contractor companies.
Methodology  
The exploratory research method is used to study lean practices in Indian construction industry, through literature review, expert verification and by studying four cases from Indian construction industry..
Findings and conclusion

Development of the generic model and assessment criteria for the lean functioning of the departments of a construction contractor company

The first objective of the study was to develop a model and assessment criteria with the use of the lean principles for the lean functioning of the departments of a contractor construction company. The research started with the investigation and identification of the lean principles and their selection and segregation as per the applicability to the field of construction, primarily to the construction contractor companies. 12 lean principles were identified along with their lean features & effects. After that, a model of general functioning was made for contractor companies. Now, for the purpose of incorporating the lean practices into the model, the features & effects of the lean principles were converted as the objectives for the general practices so as to make them lean and after this the lean practices were incorporated to generate the final lean functioning model for a construction contractor company. This completed the development of a generic lean functioning model for construction Contractor Company. The practices identified in the model were then incorporated into a tabular form to generate the checklist or the assessment criteria with few more additions for the purpose of assessment of the contractor companies as the second objective of the study.
Assessment and detailed analysis of the functioning of the departments of the contractor companies

This developed model and criteria was verified and validated by a panel of 5 experts in India to check the relevance and applicability of the practices as per the Indian construction industry and scenario. This process generated a final model and criteria to be used for the assessment of the companies in India. A case study protocol was developed in this process and 6 companies were contacted for data collection. Finally, 4 companies out of them were selected and proceeded for data collection based on the criteria of company selection, as explained in chapter 3. Primary and secondary data collection was done in India and then the data analysis was started after coming back to Thailand. A detailed analysis of all the practices was done as per the compliance status of the practices. All the practices for each of the case was described and synthesized to obtain the strengths and weaknesses of the practices of each department of each company. During summarizing the lean practices for the four cases, it was observed that there were 8 practices which were compiled in all the four companies, whereas 10 practices out of 33 which were not compiled in any of the four companies. Reasons of non-compliance were primarily determined for the practices which were not complied in any of the four companies and were analyzed in depth. This also lead to tabulate the department wise reasons of non-compliance as per the four cases considered and are as the last part of chapter
Recommendations

·         The initiation and support for the top management level for the improvement of the basic processes including the ones which do not require much of the expertise training etc. Some academic-industry knowledge exchange programs can be organized. The top management should establish a system of involving the operational staff in problem solving, decision making, planning etc. Some permanent and trusted staffs are to be chosen who can be trained to be the last planners etc. The procurement department also has to make a database of trusted suppliers for the long term relationships ad partnering in the next stages.
·         The second or the preparatory stage is for the preparation of the company’s staff and systems for the implementation of the lean practices. Development of formats, guidelines have to be done in this stage. The companies can use and modify the formats proposed by the researcher as per their needs. Skill development sessions, knowledge exchange sessions, professional training sessions, preparation of related contractual arrangements etc should be organized for the trusted employees selected in the above stage for the capacity building of the company.
·         Application of the systems developed in the above stages. Trained staff should be in touch with the professionals for continuous improvements. Incentive based system can be practiced for some site practices like hygiene & housekeeping, safety compliance, adherence to the guidelines laid, performance etc.

Tuesday 26 June 2012


APPLICATION OF THE LAST PLANNER SYSTEM IN THE INDIAN
BUILDING CONSTRUCTION INDUSTRY



By




Senjam Romero Singh

Abstract
             
India is fast moving forward with the recent pace of economic boom that it witnessed. Its economy has been rapidly developing with respect to the various sectors. With a rising GDP and a Government Policy directed towards the development of Infrastructure, the construction
Industry is also witnessing a boom. The construction industry contributes to about 7.80% of the GDP. However, due to the use of the age old traditional method of planning and project control most of the projects in India have been suffering from schedule and cost overrun of as much as 50% in certain sectors. In order to avoid a loss in GDP the construction Industry has to find ways and means to adopt project control systems that results in removal of unnecessary wastage. The Last Planner System (LPS) should be adopted in the Indian Construction
Industry for the removal of wastage and better achievements of the project goals considering its wide application all over the world.
As India has its own unique problems and characteristics the LPS has to be remodeled to better suit its need. In this research work attempts have been made to provide a LPS model that addresses the issue keeping the core ideas and concept in mind.
Case Study research with an experimental setting has been used to achieve the research
objectives. Experiment and data collection has been carried out on two projects being undertaken by a small and a large scale industry that represents the different scale of construction. An attempt has also been made to provide an implementation strategy that can be effectively used in application of the LPS concept in the country.

Executive summary

Rationale of research
This research has been conducted to develop a model for Indian construction industry to for productivity improvement through Last Planner System.
Objectives of study
To develop a simple working model of the Last Planner System to be adopted in Indian Construction Industry. To implement the LPS model and study its effect on the productivity and plan reliability and to improve the LPS model and suggest an implementation strategy
Methodology
The exploratory research method is used to study productivity management in Indian construction industry, through literature review ,expert verification and by studying two cases from Indian construction industry..
Findings and conclusion

The Last Planner System Model used in the two case studies was designed based on studies of the characteristics of the Indian Construction Industry and the feedbacks received from the Experts who were consulted to verify the model and the construct of the experiment. The refined Model was then used for the experiment. This satisfies our first objective.
The model which was put into experiment has produced some positive result. The model used was able to solve certain problems related to wastage of time spent waiting for resources on site during execution of the activities in the projects. The project participants were confident that if the Last Planner System was applied in the projects and considerable amount of time was spent in gathering experience in its use, it can solve most of the problems related to unreliable planning that does not consider the ground realities in the site and problems related to resource allocation thereby avoiding wastage of time in waiting. Removing these two problems will remove unnecessary overtime and extra commitment of resources. A smoother work flow will lead to increase in motivation and commitment in the project participants. The
Last Planner System is hence considered effective for application in the Indian Building Construction projects. This satisfies our Second objective.
All the feedback received from the experiment participants and the observation made during experiment has led to an improvement in the Last Planner Model and development of an implementation strategy.


Recommendations

·         Maintenance of written guidelines of the implementation of the Last Planner System by each company based on the company structure and policy and the lesson learnt gained from experience in using the LPS. Roles and responsibility of each individual should be clearly defined.
·         The Last planner should be a group headed by the site engineer who will closely coordinate work with the supervisors and the work crew leader.
·         Root cause analysis should be done at each PEP meeting to discuss the incompletion of assignments of the previous week.
·         Incentives schemes should be adopted to further motivate the Last Planner group to release reliable weekly plans.