International construction business is the kind which embodies with serious economic, social, and political ramifications leading to the failure of the international project success in term of time, quality and cost (Walewski, 2003). The difficulties such as client communication, understanding new market, avoiding local politics and supervising the diverse group of professionals are confronted by the international construction business (Kangari and Lucas, 1997). Moreover, the inability to understand the clients’ requirement affects the project success in international business (Ling et al., 2006). The increasing of the misunderstanding, delay and costs resulting from unfamiliar environment and different institution such as regulations, norm, and cognitive-cultural belief with diverse participant are critical things (Will and Levitt, 2010). As Han et al.,(2005) stated that the risk factors associated with overseas construction projects can diminish project profitability .There are many researchers found that the delay and cost are increased due to the confusion among project participants (Flyvberg et al., 2003; Miller and Lessard, 2000; Orr, 2005), and due to dispute resulting from different cultures (Ghopshal, 1987).
Mr. Hout Venghong made a research on an international construction contractor (ICCs) doing business in Cambodia in order to: (1) investigate the current practices of the factors affecting the performance of the international construction contractors doing business in Cambodia; (2) develop the causal relationships affecting the performance of ICCs model of each investigated factors and figured out how each contractor copes with; and (3) propose the recommendation and a framework to the international construction contractors to take into account in order to do business in Cambodia.
Research Findings
Investigated factors affecting the performance of the International Construction
Contractors (ICCs) doing business in Cambodia
Based on the data gathered, there are five factors influencing the decision making of the international construction contractors doing business in Cambodia taking to the account to strategize accordingly in order to execute the project lucratively. The current practices of the factors affecting the performance of ICCs doing business in Cambodia are:
(1) condition of the host country and project owner,
(2) international construction contractors’ ability,
(3) characteristic of organization and participation,
(4) entry mode, and
(5) Uncontrollable variables with nineteen sub-factors.
Develop the causal relationships affecting the performance of ICCs model of each investigated factors and figured out how the firms response to each factor
1. Cambodian Government policy. The government does not have clear procedure for project approval and construction law and regulation for the construction projects. The tax and custom system, still, are not transparent which can affect to the project schedule and performance as well. The unethical practice, construction law and regulation should be completely addressed the firm from the beginning of the planning stage. The procured materials have to be taken with high attention in order to meet the projects’ objectives to avoid delay and cost overrun. Lack of construction law and regulation with weak legal system leads the firm hiring a legal advisor or international lawyer to prepare the legal documents related to avoid the conflict during the projects execution. The legal advisor or lawyer is asked to involve after the international construction contractors awarded the contract.
2. The unskilled labor issue in Cambodia construction sector. This is a big problem challenging the international construction contractors, especially when the project is complex and very specialized. Because construction market in Cambodia is not really attractive yet. There are quite few tall buildings and complex projects in Cambodia. Consequently, this provides less opportunity to the local laborers to experience with similar project. Even the local labor cost is cheap but the problem is unskilled laborers who are mostly farmers, so they will quite the project to go back home.
3. Lack of local skilled engineers who are able to use English as official language, especially for technical terms in construction project. The knowledge of local engineers was considerably limited since they did not have a chance to involve with similar complex projects. The local contractors are lack of knowledge in quality control and they are mostly not qualified for either big projects or specific projects. The employment of the staffs has to be mixed because the local staffs need to coordinate at construction site between the local labors and foreign staffs. The research is also found that the entering of the international construction contractors is to consider market attractiveness with the local government support.
4. Owner delayed payment. It plays a crucial role to the quality of the project, delay payment will results to time delay.
5. No local financial institution to help the contractors or subcontractors. The lack of the big local contractors to join the international construction contractor is one constraint that the international firms do not want to do business in Cambodia. The firm has to ask for the home country contractor or the third country to execute the project. This is still riskier than joint venture with the big local contractor in case they find the suitable local contractor to make a joint venture.
6. Most of the projects are under loan or grant projects from ADB, World Bank or the other financial institution, therefore the international construction contractors did not want to bid the projects, because they are so competitive. On the other hand, the contractors who want to launch their projects with high quality to maintain their good reputation will not bid the public projects, because the project volume reflects to the skilled labors and many subcontractors to execute the project as well.
Recommendation
Based on analysis of current practices of the international construction contractors doing business in Cambodia, below is the summarized recommendation for the International Construction Contractors.
His thesis abstract is copied and pasted.
Abstract
This study aimed to investigate the factors affecting the performance of the international construction contractors (ICCs) doing business in Cambodia. Five firms in Cambodia were investigated through case study approach explanation building strategy as specific analytic approach in case study. The current practice factors/sub-factors were verified with nine industry experts and practitioners experienced in Cambodia construction industry. The administered research questions developed by a researcher being conducted with seven top management level of ICCs. In addition, the secondary data and the direct observation of the construction projects are carried out to get the supportive evidence to the result from the interview session. However, the short interview with the persons who were responsible at construction site was carried out during project direct observation. The research showed that the unethical practice, unclear tax and custom system, material availability, unskilled labor issues, lack of construction law and regulation, lack of legal system, unwillingness of local government support, different practices between the contractor and designer. From the finding, the response of the international construction contractors was pointed out with the each investigated factors accordingly. Objectively, the causal relationships affecting the performance of ICCs doing business in Cambodia was developed with the recommendation for better practices in Cambodia construction industry.
Key words: Factors, Performance, International construction contractors, Business,
Cambodia