PVN has invested & built the first power plant since 2005 with only one Management Board (MB). The objectives of the MBs change very fast but the organization structure for all MBs is still same from the beginning. Therefore, PVN’s management for power projects has still some outstanding issues which are the weakness in organizational structure for project management.
Mr. Le Anh Thong made a case study which objectives were to: (1) deeply understand the existing organizational structure of PVN power plant project, to analyse the strength and weakness, advantages & disadvantages of the existing system; and (2) propose recommendation for improvement.
Conclusion
The objectives of PetroVietnam Power Plant Projects (PVN’s PPP) are usually changed very fast, but PVN has still kept the type of organizational structure which is “Functional Structure” since 2004. Although this structure has some advantages, but this structure is not suitable with growth of PVN’s PPP which has caused some weakness and disadvantages in its management so far. With four individual Management Boards, they have not achieved perfect result in time. It is very difficult to control the scope, contingency funds, overall project value; and also it is very difficult to monitor or audit the project’s progress, stakeholder’s commitment, results achieved and the leading indicators of failure, and so on.
Recommendation
Therefore, with the study and analyses of this case study, the proposed improvement is given in which the essential issue of this proposed improvement is the recommendation to apply the Matrix Structure for One General Management Board instead of the Functional Structure for Four existing Individual PVN’s project management organizational board. Consequently, the advantages of the Proposed PVN’s project management organization will be almost same the advantages from the Matrix Structure.
The most important advantage of the Proposed Improvement is efficient use of resources of the whole Proposed General Management Board where specialized individuals can be shared and transferred from one Branch to another or in any PVN’s projects. Therefore, the project management cost is minimized; the total quantity management staff shall be decreased, but the professional grade is easily increased. These are the most useful & efficiency of this proposal.
With the detailed analyses and proposal, the strength & advantages of the proposed improvement are very clear and prevailed to compare with its disadvantages. Besides, there has the proposed solution to solve for these disadvantages. Therefore, it should be considered as preliminary study to apply in the PVN’s thermal power project management with the additional study needed.
However, the proposed improvements will not be enough to improve everything for PVN’s project management. It is necessary with best effort to apply some other solutions in order to gain actual significant improvement and overcome other outstanding weakness of PVN’s project management.
His thesis abstract is copied and pasted.
Abstract
Electric Power is an essential energy for people’s daily life and one of the major factors in labor productivity growth. It helps to develop the economy of the countries in the world, especially for the developing countries like Vietnam. Consequently, it’s very important to know how to manage power plant projects effectively and successfully.
PetroVietnam (PVN) who is the biggest Economic Group of Vietnamese State-Owned Groups has been assigned by Government to invest & build some power plants. So it is necessary for PVN to improve their power plant project management. With the scope of my report, I will mention about the improvement for organizational structure of PVN’s thermal power plant project management and my Management Board.
The Objecctive of my Report is the Proposal to improve ORGANIZATIONAL STRUCTURE of PVN’s PPP to manage PETROVIETNAM POWER PLANT PROJECTS (PVN’s PPP), and solve their weakness/disadvantages & gain better effectiveness and success.
The reason to find the above Ojective are the objectives of PVN’s PPP are usually changed very fast, but PVN still has kept the beginning type of organizational structure from 2004 up to now, and some weakness/disadvantages were found in PVN’s PPP management so far.
Therefore, the case chosen for my report which is the organizational structure of PVN’s PPP.
By the analyses based on theory of organizational structure for project management colland my experience during a long time work in PVN’s PPP, my recommendation of the Proposal in my Report is the application of the Matrix Structure for One General Management Board instead of the Functional Structure used by many PVN’s individual Management Boards that expected to gain the above Objective to PVN’s PPP management.
5 comments:
Very important information provide for improvement of organizational structure....
project management proposals
Kansas City pier masters Companies is a unique company in our industry in that we are not only just a construction company, but also a Professional Engineering firm in the state of Missouri, through our divisions of pier masters and pier masters MUDJACKERS. pier masters offer diversified, engineered structural support services and products. This site offers valuable information to our clients and prospective customers alike.
Our master mudjackers are the best We offer diversified, engineered structural support services and products. kcmaster.com offers valuable information to our clients and prospective customers alike about master mudjackers.
Reliability and consistency is a significant importance of renewable energy resources. Atmospheric conditions and geographical locations make a huge impact on the efficacy of these energy sources.
Power Plant Management Services
Find these organizational chart examples and templates drawn on various scenarios in the diagram community of Creately org Chart Software . there are many structure templates including hierarchy, matrix and flat. And they are free to be used!
Post a Comment