OWNER’S PROJECT SCHEDULING STRATEGY
A
CASE STUDY OF
SHB
- DA NANG F.C SPORTS AND TRAINING COMPLEX CENTRE PROJECT
by
Vuong
Hoang Thang
Abstract
A successful construction project
is the one that completion within destined time, budget and quality. Project
scheduling and project scheduling management are very important parts of any
project as they provide the project team, sponsor, and stakeholders a picture
of the project’s status at any given time.
The Project schedule is the
roadmap for how the project will be executed. A successful construction project
is also meaning a successful project scheduling and it is executed in the
boundaries schedule's creation.
This report review project
scheduling and management theory, time management functions and delay risks
address into scheduling management commonly applied in developed countries and
developing countries and Vietnam.
The report study the scheduling
and management strategy applied in a construction project in Danang city,
Vietnam. From the study case, the report identifies and analyses the practical
application of project scheduling management functions and strategy. Then,
reviews practices of the project scheduling management and suggest some
improvements strategy can be applied
Executive summary
Rationale of research
This research has been conducted to identify scheduling
problems and propose good project scheduling practice and strategy for the
owner.
Objectives of study
To identify project delay and risks of project delay in
construction stages, and approach to schedule creation to propose owners
strategy for project scheduling management.
Methodology
The exploratory research method is used to study delay and
understand factors that affect project scheduling management.
By undergoing into project case and practice implementing in
scheduling management .
Findings and conclusion
The administration of schedule is
the most significant concerns of project management for project owner, as an investor, mainly
concerned about the profitability of investment.
The project scheduling management
is resulted from the frame of project management planning and related directly
to time aspect in each project.
considering the review of project
schedule management, analysing the practice in Project of SHB-Danang Sports and
Trainings Complex Centre, 1st phase, a project sponsored by
non-state owner resources. The learning from the study is that from the initial
stage up to now this project is applied some project management tools and
methods to manage cost, time, procurement, etc. And the same to other common
projects in Vietnam the scheduling management and time management is always a
big challenge to the Owner.
The Owner of project (SHB) wished
of completion construction and moving the club into new centres at the end of
September 2012 latest. The construction duration is planned maximum of 8,5
months from the earth works till completion the 1st phase. However,
the actual performance is slow than schedule and now estimated delay about 5
months hopefully.
The project was traditional
design bid and built, each participant team was working well at their
responsibility and used computer tools to reduce risk.
But the major problems were in
communication and decision making which caused delay and un-professional
attitude from owner side.
The team got some unrealistic
milestones but overall project management unit from owner side is weak.
Recommendations
To
put project schedule on realistic channel owner should focus on following
points
·
Set
& manage Buffer in the time frame and activities duration.
·
Reduce
dependencies by applying tools and methods such as: WBS, OBS, CPM, LSM, PERT
and delay risk management.
·
In
the estimation of task / activities, should focus on the Critical path, LOB.
·
Develop
communication and report mechanism with some tools such as EV, SV, in order to
update and adjust baseline making decision of the Owner.
·
Set
penalty/ award provision in the contract both to the contractor and the
designer.
·
Put
realistic milestones into the contract and general time frame and bound to all
the project's stakeholders (Owner, PMU, PMC, and contractor, and consultants,
designer).
No comments:
Post a Comment