Since
1994, Amata (Vietnam) decided that its main mission is to develop industrial
estate going along with living community in Vietnam. In order to gain the
mission, many projects have been invested by Amata (Vietnam). Those projects
are office building, factory for lease, traffic road, water supply system, drainage
system, wastewater treatment system, electricity, telecom system, etc. Based on
the record of these developing projects, Amata (Vietnam) has experienced common
project failures such as project delay, cost variation, useless and ineffective
facilities of project investment, etc. These problems initiate a research study
to find out the root causes as well as remedy methods of the project failures.
Mr.
Nguyen Van Nhan made a research to learn about the project governance framework
which has been applying by Amata (Vietnam) for developing projects in
comparison with models of effective project governance developed by Gross
Garland, 2009. Learning from the comparison, the research study found root
causes of project delay, cost variation and useless and ineffective facilities
of project investment. Resulting from the study, an applicable project
governance framework is proposed for developing industrial estates.
Conclusions
1. Weaknesses
found from the current project governance framework
Applicable
project governance framework is required for developing projects successfully.
Therefore, the industrial estate developers need to study project governance
frameworks which are suitable to their organizations. Analysis of the five case
studies found weaknesses of the current project governance framework with
regard to the four principles of effective project governance. Besides, the
validation interviews also contributed more points on weaknesses of the project
governance framework that the researcher did not get from the case study
analysis. Those mentioned weaknesses can be summarized as the following:
The project
owner
- One of the first weaknesses related to the project owner found from the
research study is unclear accountability for project’s success. Accountability
of the project owner was not clearly defined for the success of project
delivery. The project owner should be the single one person who chairs the
project board, however, this role was sometimes held by the key stakeholder.
Besides, the project owner shared their decision making role to the senior user
of the project board, therefore, confusion and ineffectiveness happened during
the project decision making process.
Another
weakness related to the project owner which the research study found is the
project owner could not have adequate arrangement to both chair the project
board and hold the president of the organization. Both roles are key important
roles with very heavy workloads. Moreover, the project owner was appointed to
hold the role of project owner for many projects under parallel executions. The
project is unavoidable to be in the situation that slow and ineffective
decision making activities of the project owner.
The project
director -
Similarly to the project owner, the research study also found weakness of the
current project governance framework relevant to the project director. The
project director joined the project board to keep the role of coordination
between the project board and the project manager, however, the project
director at the same time held other position of department manager of the organization.
Moreover, the project director was assigned to hold the role of project
director for many projects under parallel executions. The project is
unavoidable to be in the situation of slow and ineffective decision making
activities of the project director.
The senior user - The presence
of the senior user was not available from the early stage of project execution.
Project investment was aimed to deliver services to customers who were not
defined since the beginning of the project. Therefore, the project board did
not have adequate information of the user’s demand in order to deliver the project
appropriately.
The strategic
advisor’s group
- The strategic advisor’s group is necessary to support the project board in
delivering projects of new business investment. Without support of the group,
the project board did not make appropriate study on service delivery of project
2. Conclusion on
the proposed applicable project governance framework in compliance with the
four principles of effective project governance
The
research study proposed an applicable project governance framework to the organization.
It basically kept structure of the current framework and proposed some additions.
The below discussion concludes on the proposed applicable project governance
framework in compliance with the four principles of effective project
governance framework.
The project
owner
- The position of project owner is held by the president of the organization.
Following the principle 1 of effective project governance, the project owner is
accountable for the success of the project delivery. They keep the role of
preparation for project plan such as budget, schedule, etc. and appointing
other members of the project board including the project director, the senior
user and the senior supplier. The project owner prepares for the guidance of
project’s target from the early stage of the project. The project owner chairs
the project board to find solution of any conflicts within the project board.
The project owner reports directly to the investment decision group (the board
of directors). In order to fulfill the principle 4 of effective project
governance, the project owner empowers the project director to act as the
coordinator of daily project activities. This way helps the project owner to avoid
heavy workload influenced by both the organizational governance and the project
governance.
The senior user -
Following
requirements of the principle 1, sales, after sales or operation and
maintenance divisions may hold the position of the senior user. These divisions
make surveys on user’s demand to provide information to the project board and
prepare user’s manual of the project. The senior may consult the strategic
advisor’s group to update and complete information of user’s demand. The
present of the senior user is one of the additions to the current project
governance framework of the organization. It is necessarily required for
delivering project successfully.
The senior
supplier
- It is kept the old process of selection for the senior suppliers through
bidding or nomination. Project owner or the project board must award qualified
senior suppliers professionally in delivering the projects. In some special
cases which the project is new business investment of the organization, the
project owner needs to consult the strategic advisor’s group in selection the
senior supplier.
The project
director
-The project director is still recommended from manager of the engineering
department. It is recommended that the project director should be appointed
from internal organization to gain more effective cooperation with other
members who were also selected within the organization. The project director
should be expertise in construction management to assist the project owner. The
project director sits in the project board to report directly to the project
owner as well as the coordination between the project board and the project
manager. As the project director is empowered by the project owner, the project
director checked and approval for project partly execution and completion and
report directly to the project owner. The project director and the mentioned
project engineers are responsible for daily activities of the project
execution. In order to fulfill the principle 4, it is required that the project
director must assign suitable project engineers to support him in detailed
project activities so that the project director can balance the requirements between
the project activities and the organizational activities.
The project
board
- The project board is structured from the project owner, the project director,
the senior user and the senior supplier. In compliance with the principle 1, the
project board is chaired by the project owner. Within the project board, the
project owner takes priority in decision making. As the project board has
periodic meeting for project decision making, size of the project board should
not exceed 6 members. It is to comply to requirement of the principle 3. This compliance
will avoid the project board to suffer from stakeholder meeting.
The investment
decision group
- The investment decision group is maintained with its structure of a chairman,
a vice chairman and six directors. Main role and responsibility of the investment
decision group is to consider and approve for project plan such as budget plan,
project delivery plan, etc. as well as changes on the original plan.
The strategic
advisor’s group - The establishment of the strategic advisor group is required
for cases of new business investment. The group is responsible for consulting
on the tendering preparation, technology selection as well as selection of the
senior supplier. It also helps the senior user to complete information of
user’s demand as required in the principle 2 of effective project governance. The
project owner is still recommended to chair the strategic advisor’s group.
Other members of the strategic advisor’s group are from the organization and
the superior organization and external experts from professional consultant.
The project
manager
- The project manager is appointed by the senior supplier. This position is
changed respectively to the project stages change. The project manager is
responsible to deliver project within limitations of time, cost and quality
stated in contract signed between the project owner and the senior supplier.
The project manager works closely with the project director to make sure that
the project delivery meets the project’s owner’s needs. It is important to have
qualified project manager for well coordinating and supporting with the project
director.
The project team - The project
team is normally from the senior supplier’s side. It includes engineers in the
fields appropriate to the requirement of the project. The members of the
project team work and report directly with the project manager.
3. Conclusion on the validation
interview
From
the validation of interviews of both internal and external organizations, the
research study concludes on important points regarding to the proposed
applicable project governance framework. Research study on the five project
cases was endorsed and the proposed applicable project governance framework was
recommended as a useful framework and supported to apply for the organization
in developing project.
-
The project owner was suggested to be accountable for the project’s success.
However, it is required for the organization to choose the right project owner
for driving the project successfully. In order words, the project owner must be
capable in coordinating the project board for project decision making process.
-
The project director should be appointed by the project owner to the person
from internal organization rather than from external organization. The project
director is recommended to be the center of the project board. The
recommendation replaced the role of the project owner by the project director.
Hence, the research study may consider this recommendation as the project owner
should provide more empowerment to the project director for detailed project
activities. There was one question about number of projects which a project
director can handle effectively. The question may initiate more study on the
project director.
-
The senior user must be correctly appointed from the sales, after sales or
operation and maintenance division. Those divisions shall need to make survey
on user’s demand.
-
The strategic advisor’s group is chaired by the project owner to help the
senior user fulfilling information of user’s demand. Other members of the group
are from internal experts, experts from superior organization or external
experts to contribute better innovative expertise.
-
Others: the research study should consider on other causes of project failures.
Besides, the four principles are probably not enough for developing project
effectively. Option of seven enablers was recommended to apply for the proposed
project governance framework. They are gate process, clear deliverable, clear
governance, holistic organization, competence team, adequate resource, feedback
to the next project. The recommendation raised more study on the effective
project governance framework and the four principles.
His
thesis abstract is copied below.
Infrastructure
such as traffic roads, electricity, water, drainage, wastewater treatment
plants, office buildings and factories are necessarily required in developing
industrial estate. As per the requirement, this research study has developed an
applicable project governance framework for industrial estate developers. An
industrial estate developer named Amata (Vietnam) Joint Stock Company was
selected to study on its developed projects in Amata Industrial Estate and
Amata Commercial Complex in Long Binh ward, Bien Hoa city, Dong Nai province,
Vietnam. The research study analyzed data of five project case studies taken
from record of project executions to find root causes of project failures. Data
analysis was based on theory of effective project governance and its four
principles. Cross analysis was done for the five case studies to find common
causes of project failures. Through the common causes of project failures, the
research study proposed an applicable project governance framework in which
contributed remedy methods to the current project governance framework of the
organization. The proposed applicable project governance framework for industrial
estate developers is probably only suitable for Amata (Vietnam) Joint Stock
Company. The researcher suggests more case studies from other industrial estate
developers to complete the value of the proposed applicable project governance
framework for widen use. Moreover, further study is recommended as project
failure can be from other causes which were not studied in this research.
Keywords: Project decision
making, accountability, service delivery ownership, project ownership,
stakeholder management, project governance and organizational governance.
11 comments:
It is just what I was looking for and quite thorough as well. Thanks for posting this, I saw a couple other similar posts but yours was the best so far. http://www.promptessay.com/The ideas are strongly pointed out and clearly emphasized.
Loved to read your blog. I would like to suggest you that traffic show most people read blogs on Mondays. http://www.ukessaywritingservice.com So it should encourage blogger to write new write ups over the weekend primarily.:-!
This is very much a work in progress whenever I find out about one who is more beautiful than any of these I will add her andhttp://essays-writings-service.net/
kick out number ten Thanks for sharing the informative post.
Regards
))
Thanks for your post. http://online-essay-writer.org/ I'll share it with friends.
Very interesting project on my opinion. http://online-essay-writer.org/ I am grateful for information about it!
There is a also amazing type of ad, or maybe fine sufficient company, that almost all text message as being a stone this i doubt any truly does budge. That thinking infects but additionally you feel most of us, being a goliath could help you one thing - also it is apparently induces i if you would like fresh anything at all, caused to me sensible rather than disregard the residential.
I am thankful to this blog for assisting me. I added some specified clues which are really important for me to use them in my writing skill. Really helpful stuff made by this blog.
บริษัท รับ เหมา ก่อสร้าง
Mostly I use to wait for informative article on daily bases to get something new, but today i found your blog very interesting and unique, providing the information helpful to others. Keep it up and waiting for your new updates thanks. We offer multiple services in digital marketing, some of our services are:
Digital marketing Company in Delhi
SMM Services
PPC Services in Delhi
Website Design & Development Packages
SEO Services Packages
Local SEO services
E-mail marketing services
YouTube plans
Digital Marketing Service in Delhi
It’s a pity to see such a huge investment going to waste because of some people’s carelessness. Even though I’m a professional writer and only a few bucks are given to me by students who buy essay service from https://www.usessaywriter.com/essay-writing-service-in-san-francisco/ but still I give my 100% to provide the best writing services.
Such an informative post. The article is really helpful. Thanks for sharing the knowledge and experience.
Thriller Michael Jackson Blue Leather Jacket
Marshmello White Bomber Jacket
Rare Marlboro Man Formula Racing Motorcycle Leather Jacket
Where To Cut Led Strip. Cut with a pair of scissors. The ideal place to cut in a led strip is the copper connections located at every two inches of the led strip.
Post a Comment