Many large scale building projects in Vietnam have common issues relating
to budget overrun, lost revenues or other benefits and quality non-achievement.
Delays bring negative effects to the Owners in terms of lost time lead to lost
money, lost business chances and even lost company reputation.
Delays are often caused by slow decisions, miscommunication,
unanticipated reviews before and approval, or rework to correct planning and
implementation errors. Delay may be at least partly due to underestimated
durations or poorly conceived schedule logic.
Other causes of problems are:
- project size and complexity;
- unforeseen technical difficulties;
- schedule changes;
- poor contract administration and policies
- poor project definition;
- labor problems and equipment/materials resources;
- government policies changes, etc..
Aside from these, there are pressures from the market to the Owners to
shorten their project duration to catch the demands.
Mr. Le Viet Hoai made a study to figure out some key factors to complete
building projects successfully without a major effect on the budget and without
sacrificing quality. The objectives of his study were to:
1. identify key factors of
effective fast-track projects applying for high rise building projects;
2. identify problems and also
advantages during project delivery with fast-tracking.
1. Key factors of effective fast-track
building projects
Based on the literature review, a successful project from the perspective
of the Owner is to meet intended purpose, within financial, time and regulatory
constraints. There some factors to be concerned during delivery of fast-track
building project effectively:
(i) Selecting of project delivery
method to achieve the required result is important to project. Selected
delivery method determines the contracts between the various parties, and the
practices needed to form and administer the contracts as well as risks are
assigned. Selection needs to be carefully made on each project which based on
specific conditions, and primary constraints of the project. Mixing of more
than one of the theory delivery methods to be our own appropriate hybrid method
as in this project report is encouraged.
(ii) Fast-tracking not only refers
to overlapping activities between design and construction work. The extent of
fast-track can be extended to the early stage of project. Fast-tracking can
apply between development stage and detail design by stating detail design
after finalizing preliminary design while feasibility is in progress. Hence,
construction work can earlier start accordingly.
(iii) Fast-tracking can also make
inside each package of construction work where typically follows the
traditional process design – bid – build. Invitation to Bidders can be earlier
issued to Contractors without waiting for the whole detail design and estimates
are complete. Construction of the package can start earlier or even when
contract award is in progress (if you had a general agreement to cover whole
project before).
Total process in fast-tracking
using strategy is illustrated in figure
below. If well managed,
overall process can reduce 2-3 months of project duration.
By step by step contracting to
Contractor combined with carefully monitoring package estimates and regularly
updating to project budget can be useful to the Owner to avoid budget overrun.
2. Problems and also advantages during project delivery using fast
track
By using fast track project, the project owner can take a main chance by
catching up market demand. Gain benefit from earlier project completion
equivalent with earlier revenue, and financial return. Besides that, some
beneficial changes in designs can be feasible made during delivery. In other
hand, less debt financing due to early completion. Furthermore, risk on
construction can be earlier transferred and company reputation can be following
proven on real estate market.
Although that fast track delivery is popular used as a strategy, there
are many problems that can occur when fast track delivery due to lack of
knowledge and inexperienced consultants as well as project management teams.
Therefore, the negative effectiveness of unsuccessful fast track projects is
significant and can lead to more delay and cost.
The challenge for most fast-track
projects is construction contract negotiation. Pricing disputes often occur in
each trade on which price is reasonable or comparative. The Owner doesn’t have
much advantages in this case and process may last for long time.
In addition, fast-tracking is
likely to face with that coordination is more complex, being compressed into a
short time, and requiring especially capable coordinators to maintain priorities.
On the other hand, drawing
control is more difficult because there are more revisions, even if only to add
the detail not available at first issue. These adjustment revisions may be
considered as design changes justifying additional money and time by
contractor. When there are too many of these differences to resolve in
compressed time frame, accumulating conflicts may damage the cooperation.
A fast track project method is not a must for all projects, as it depends
on each project type and business strategy. The project owners should carry out
a benefit analysis and have a business target to decide which strategy is
suitable for their case.
Therefore, experienced consultants and project managers should provide a
suitable plan for project owners based on analyzed and feasibility studies.
His thesis abstract is copied below.
Abstract
The frequent market imperative for minimized project durations to catch
the demand has brought the Owner to better facilities for project to be
delivered in less time, at less cost, and with fewer risks. Fast-track is
certainly selected to meet these demands and become popular. With fast
track project delivery system, a stage can start before the prior one is
complete, especially the overlap between design and construction works, which allow
project earlier completion than with traditional method. There no doubt that
fast-tracking offers many advantages and benefits, such as an earlier project
completion, earlier operation, earlier financial return and earlier transfer
risk to construction. Therefore, fast
track project delivery in building projects becomes applicable strategy. In
order to understand how fast-track is implemented and key factors of effective
fast-track project together with problems and advantages, a case study is
explored by approaching its documentations, interviewing involved persons. The
results show that fast-tracking not only refer to overlapping activities between
design and construction but also can extend to development stage or even inside
each construction package effectively. Their application is widely during
project stages. However, fast tracking can become a threat to quality, cost and
even schedule if not done carefully. Therefore, in order to apply fast track
project successful, owners should have proper plan.
Keywords: fast-track, fast-tracking, strategy,
building project, delivery method, key factors, effective project.
2 comments:
I think this is an informative post and it is very useful and knowledgeable. I have a sheet all your articles. Thanks for this best post.
Global Assignment Help
ฉันคิดว่ามันอยู่ในประเทศไทยหลายอย่างที่น่าสนใจขึ้นสวรจะเห็น ตัวอย่างเช่นบน ThmoviesHD.com คุณสามารถดูหนังสำหรับอิสระ! นี่คือมากกว่าที่น่าสนใจมากกว่าที่จะเข้าใจบางซับซ้อนการคำนวเชื่อฉันสิ
Post a Comment