BUSINESS
PROCESS MODEL OF THE PROJECT MANAGEMENT
PROCESS:
A CASE STUDY OF WATER SUPPLY CONTRACTOR IN VIETNAM
By
Nguyen
Thanh Tung
Abstract
In a developing national like
Vietnam, the infrastructure system has not completed to support the demand of
people in the country. Thus, the government of Vietnam has invested a huge of
money to build and upgrade the infrastructure system. However, the infrastructure
project are usually delayed and cost overrun, especially water supply system project.
Almost those projects are delayed and cost overrun because of lack management, detail
planning and schedule. Besides, a lot of water supply projects, those have
built recently, got suffer design or construction fails due to lack of
appropriate equipment and material, management skills or financial source. All
the causes were led by inappropriate project managements and the tasks delivery
during whole life of project. However, there is no research to find out the
business process model of project management and the tasks delivery during
whole life of water supply project.
Concerning the above issues, the
research concentrated on three main objectives: (1) To map the business process
model of project management in water supply projects; (2) To study efficient
tasks delivery and find out the main cause of the inefficient tasks in water supply
projects; (3) Suggest the solution and recommendation for making work being
more efficiency.
Executive summary
Rationale
of research
This research has been conducted to develop business process
model for water supply project contractors.
Objectives
of study
To map project management tasks
in water supply projects and efficient tasks delivery in water supply projects.
To find the problem in the
process providing solution for making efficient process.
Methodology
The study will start with the
problem statement that was defined by study the practical statement of water
supply projects in Vietnam. And then, the literature review of project management
process during construction and business process management are studied to find
out the main activities and its tasks to support the next stages of the
research. During Data collection stages, the typical case study is collected
from Vietnam.
Findings
and conclusion
- The business process model of project
management in water supply project of contractor
The business process
model of project management in water supply project was mapping to help
understand the business process of contractor. In which, the management tasks
map illustrated the activity of contractor from bidding process to project
handover. Furthermore, the relationship between each tasks and the input and
output of each tasks were also found out and described on the map. Besides, the
individual group and person who have responsibility for each task also were
determined. It helped the researcher could see the mistake and inefficiency of
each tasks or progress come from where and who have the responsible for them.
To draw the model, a lot of interviews have done with key people of project to
get the detail information supporting for the mapping work.
- Inefficiency tasks delivery of contractor
in water supply project
According the case study,
the project delayed in a lot of work section and cost overrun.In this study,
the researcher had determined at least seven inefficient processes as
following:
1. Inefficiency of
estimation process.
2. Chose wrong the
construction teams, subcontractors.
3. Shortcoming of
preliminary processes before executing the project.
4. The inefficiency of
executing on site of subcontractors and construction teams.
5. Lack of management and
observation of Site management Board
6. Inefficiency of observation
and inspection from Planning and Economic Dept.
7. Inefficiency of
payment management, Inefficiency of doing final document works
In which, the executing
on site of subcontractors and construction teams was the most major process
that significantly affected time, cost, quality of project. In this process,
every mistake and error occurred that led a lot of delay and cost overrun in
the project.
- The main Causes of inefficiency in project
management of contractor in water supply project
After analyzing project
document and discussing with key person, the researcher found out some main
causes that led the project got problem during bidding, construction and handover
process. It includes:
1. No concrete
regulations on contract management among main contractor, subcontractors and construction
teams.
2. Conflicts of
responsibilities
3. Lack of qualified
staff and labors
4. Inappropriate work
planning of subcontractors and construction teams
5. Contractor’s poor site
management
6. Inadequate experienced
construction teams and subcontractors
7. Problem with
subcontractors
8. Lack of implementation
equipment and material
In which, inappropriate
work planning of subcontractors and construction teams were one of the most
popular cause in the case study.
Recommendation and solution to improve the efficient
project management
To improve the efficient
project management, some recommendation and solution were provided to deal with
the problem remaining in each process. All recommendation and solution were
suggested after not only discussing with experts and key person in the project
but also finding from journal and book to get the best solution. The researcher
had recommended and proposed the solution for each inefficient process or task
to improve the efficient project management of contractor.