REWORK IN RESIDENTIAL CONSTRUCTION IN CAMBODIA
By
San Visal
Abstract
Nowadays,
Because of high demand of population, there are many construction projects is constructing
in Cambodia. In addition, rework in one of the main unavoidable problem in construction
project. Therefore, in order to understand of each impaction of each rework categories
and propose recommendation to reduce those rework, this research was conducted.
In order to achieve the objective of study this research was conducted by using
questionnaire survey from 30 construction project which 12 of high rise
concoction and 18 of low rise construction.
The
research show that concrete strength under requirement that rarely occurred is
high impact on time and cost in high rise construction and medium impact in low
rise construction. Defective in rebar cutting, low quality of plastering and
incorrect of erection form-work are the 3 rework categorize that is high
frequency occurrence in high rise construction. Defective in rebar cutting is
the rework categorize that is high frequency occurrence in low rise
construction.
Moreover, it was found that both
of rework happens in low rise and high rise construction cause by human
resource ability is the highest one. It was followed by engineering & review,
leadership & communications, material & equipment supply and
construction planning & scheduling respectively.
Executive summary
Rationale of research
This research has
been conducted to asses rework issues in Cambodian residential construction
projects.
Objectives of study
The objectives of
this study are:
To investigate the
rework categories which impact time and cost in residential construction in
Cambodia.
To identify the
important factors direct caused rework in residential construction in Cambodia.
To propose recommendation
to reduce rework in residential construction projects in Cambodia.
Methodology
The research methodology
that supported by literature was developed in order to achieve the objectives of
study. Methodology describes the method of data collection, data analysis and
data interpretation. Finally, conclusions and recommendation were conducted to
support this study.
Findings and conclusion
Rework was described
as an inevitable event in construction project. Its occurrence has strong
impact on project performance in term of time and cost. In addition, rework
that was considered low, medium and high impact on time and cost depends on the
type of rework and degree of its damage actually. On the other hand, some kind
of rework that is low and medium impact could be considered as critical item if
it happens quite often in construction project. Normally, change order, damage,
error, failure, omission and deviation are the source that could cause rework
occurring in construction project.
Moreover, different
rework categories that occurred in construction project caused from different
reasons that were categorized under 5 main groups human resource capability, engineering
& reviews, construction planning & scheduling, material & equipment
supply and leadership & communication.
Quantitative research
design of 30 construction projects was applied in this research. Among these 30
construction project, there are 12 high rise construction and 18 low rise construction.
The study is focusing on characteristic of each rework categories in term of frequency
of occurrence, time & cost and direct causes during construction phase. Rework
is an unavoidable event that occurred in construction project. In addition, it
could be dissatisfied to participant in the project such as owner,
sub-contractor and contractors.
In Cambodia, both of
low rise and high rise construction, human resource capability is the highest
factor that cause rework occurrence. It was follow by engineering & review,
leadership & communications, material & equipment and construction
planning & scheduling respectively. In addition, insufficient supervision
is the main factor under human resource capability that cause rework occurrence
in both low rise and high rise construction. Inadequate shop drawing details is
the main factor under engineering & review that causes rework occurrence in
low rise construction while inadequate shop drawing details and deviation from
drawing are the 2 main factors that cause rework occurrence in high rise
construction. Lack of communication between site supervisor and worker is main
factor under leadership & communication that cause rework occurrence in
low rise construction while lack of communication between contractor &
inspector is the main factor that cause rework occurrence in high rise
construction. Inadequate construction planning is the main factor under
construction planning & scheduling that cause rework occurrence in both low
rise and high rise construction. Low quality of equipment is main factor under
material & equipment supply that cause rework occurrence in low rise
construction while poor quality of material is the main factor that cause rework
occurrence in high rise construction.
Recommendations
Rework occurrence in Cambodian
construction projects is based on five main categories. Engineering and
reviews, human resource capability, leadership & communication, material
& equipment supply and construction planning & scheduling.
Therefore, the development
model was produced in order to reduce rework in construction project.