CONSTRUCTABILITY
IMPLEMENTATION DURING CONSTRUCTION PHASE OF THE LARGE HIGH-RISE BUILDING
PROJECT IN VIETNAM
By
Nguyen Anh
Khoa
Abstract
Generally a construction project usually involves a heavy cost.
So, time and resources to play a leading role in determining project costs. In
general, the construction phase faces with many risks and uncertainties. As a
result, the project could be delayed, cost overrun, and poor quality. In many
previous researches all over the world, the constructability program was
suggested to become the effective tools to help the project team control the
project effectively. Although the constructability concept is not new with the
developed countries, the constructability application in developing countries
is still very limited. The study aims to identify the application of
constructability during the construction phase in the large high-rise building
projects in Vietnam.
Researcher uses two cases as the research design. The basic
factors will be identified by literature review and they would be verified by
the experts who have a lot of experience and management knowledge in
construction. The data collection will be conducted in Hochiminh city to
support for the data analysis activities to provide the understanding about the
constructability application in Vietnam.
Executive summary
Rationale
of research
This research has been conducted to study constructability to
make efficient construction process for high rise building construction in Vietnam.
Objectives
of study
To identify the factors affect constructability, to analyze and
evaluate the constructability application. Providing recommendations to improve
constructability.
Methodology
In this study, researcher decided to use
the qualitative method by using the case analysis as a key to obtain the
objectives of the study. In general, there are three main approaches when using
the qualitative method. (1) Participant observation (2) In-depth interview (3)
Focus group.
The advantages when using the
qualitative method is that participants have opportunities to response based on
their opinions rather than selecting the fixed responses. Moreover, qualitative
method provides the flexibility for the researcher by asking during the
interviews. The opportunities to find out the answers for the study will be
enhanced by getting the detailed information and data.
Findings
and conclusion
Constructability concept is no longer a
new concept especially for the countries which have the developed construction
industries. In order to improve the constructability, many researchers put
their efforts to achieve this purpose. Constructability application will become
the powerful and effective tool to help the project teams implement their
project successfully by increasing productivity, quality, and safety at
construction site. Moreover, the risks and the conflicts between every parties
involved in the project could be avoidable.
According to Vietnamese construction
industry, constructability has been begun use as a tool to manage the project.
Some contractors who have the big scale and reputations such as Coteccons and
Hoa Binh Corp realized the benefits of implementing the constructability. As a
result, constructability was used as a key tool to help them increase the
efficiency and the profits.
Recommendation
- Involving
finishing sub-contractors from the beginning:
In some cases,
involving finishing sub-contractors from the beginning could bring many
benefits such as reduce the reworks and avoid the interruption in finishing
activities. However, the possibilities to apply seem incredible because of the
long duration for tendering. Moreover, the traditional contract (DBB) is still
used very common in Vietnam. As a result, few experts (3/7) agreed that
involving finishing sub-contractors from the beginning is possible in reality.
However, the contractor and
consultant should provide their finishing engineers in the beginning to join
the project team. This action is also the good solution to consider.
- Capture and
transfer lesson learned from previous project:
Setting
up the lesson learn system (LLS) also enhance the constructability. The project
would be managed better. Project team capacity and knowledge could be
increased. The problems could be deal by using the learning captured from
similar projects.
Action should be considered:
§
Provide
seminar to train employees and transfer knowledge.
§
Record
database, provide meeting to analyze the previous project and learn the
experience.
§
Provide
checklist about common mistakes.
§
Provide
database of lesson learned for all employees.
- Consider possibilities about
using pre-cast concrete
- Pay more attention to the
innovative hand-tool and equipment usage.
Construction hand-tools:
§
Use
automatic hand-tools
§
Use
cordless power hand-tools
§
Use
new hand-tools or modification of the available hand-tools
§
Portable
hand-tools
- Construction equipment:
§
Use
microprocessor control and diagnostics devices.
§
Automatic
equipment.
§
Remote,
non-destructive sensing and inspection system.
- Using the innovative in
temporary facilities:
§
Consider
tent cloth to enclosure the structure and workplace
§
Centralized
supply network.
§
CCTV
to control the site.
- Using the
advance computer technology:
§
Building
information modeling (BIM)
§
Advance
software support for planning and control project or analyzing and simulating
the site activities and structures.
No comments:
Post a Comment