Faculty Positions in Military College of Engineering,
National University of Science & Technology,Pakistan
Qualification: Masters, PHD in construction management
For Pakistani Candidates
Please contact:
Dr Manzoor Hussain
Associate professor
Head of Department Transportation & Geo-technical Engineering
mhussain@mce.nust.edu.pk
This is a blog managed by Construction, Engineering and Infrastructure Management (CEIM) at Asian Institute of Technology, Thailand. In this blog, CEIM shares our activities in providing excellent professional project management education at Master and Doctoral levels in Thailand, Indonesia and Vietnam. http://www.set.ait.ac.th/ceim/
Monday 13 August 2012
Saturday 11 August 2012
PROJECT OWNER’S CONSTRUCTABILITY MANAGEMENT SYSTEM – A CASE STUDY
OF SOUTH RACH CHIEC RESETTLEMENT AND RESIDENTIAL PROJECT
By
Nguyen
Hong Thanh
Abstract
This report expresses
the main key issues in Constructability Management System that known as an
important part for any organization wants to study and develop the
constructability practices.
This report, which
refers to some theories and the standards system, has expressed the concept of
constructability practices in construction. These constructability theories and
practices are in organization, in the owner side, requires for the owner’s
constructability concept and practices in construction and its benefits. The
study and its concept have briefed the main factors that most effect to the
specific project studied from public reports and the key points to control
project constructability concept and practices from the conceptual planning
stage to construction stage. This report has introduced a constructability
concept to the developers for the purpose of amendment to the existing
constructability management system in order to obtain a complete
constructability management system for better managing project.
The case study
of this report is the case study on the South Rach Chiec resettlement and
residential project that established to run and deliver an international
project of the Keppel Land Vietnam. Via this project case study, the findings
on the existing constructability concept, constructability practices and the
application from the previous part to this existing constructability management
system for improvement will be the foundation of constructability management
system for toward Keppel Land’ projects.
Executive summary
Rationale of
research
This research has been conducted to identify constructability
issues in residential building projects in Vietnam.
Objectives of study
To study current approaches to constructability practices in a
complex functional project with high-rise building and commercial office,
determine the methodology to improve constructability practices during
conceptual planning stage, design and procurement stage, construction stage.
To study the problems occurring in constructability practices and
provide the solution to adapt constructability practices and recommendations.
Methodology
Initially five key
issues of constructability are considered. They are: developing the project
objectives and definition, project conceptual planning stage, project design
stage, project procurement stage, project construction stage. Each stage offers
a very important pros & cons opportunities for constructability
improvements during those phases.
Data collection and gathering
information from research theories. To develop comparison and applying those
theories to the existing constructability management system, in order to
improve it.
Findings and conclusion
Case study mentioned
the understanding of constructability concepts applied in reality with limited
acknowledgement of personal capacity. However, there are some observations from
findings that might need to review to improve the constructability concepts and
practices.
The company should
improve following matter to enhance constructability in specific project as per
discussion:
1. Contract Review
2. Selection of Consultants/Contractors/Suppliers or Procurement
3. Design Review
4. Process Control
5. Coordination and Communication
6. Control of quality
records
In order to conduct
constructability practices in the project successfully, the company would
develop proper training courses to operation level and management level to be
able to acknowledge the appropriate concepts of constructability.
Recommendations
- Improve
constructability concept and practices in project planning stage
- Improve
constructability concept and practices in project design and procurement
stage
- Improve
constructability concept and practices in project construction stage
Wednesday 8 August 2012
STRATEGIC
BEHAVIOUR APPLICATION IN MEDIUM-SIZE CONSTRUCTION: A CASE STUDY OF CAMBODIAN CONTRACTOR
By
Vannaro
Kao
Abstract
The research aimed to study the strategic
behavior application in medium size contractor in term of corporate strategies,
business strategies, functional strategies, project operational strategies and
strategic performance. Using an applied case study methodology, one road
infrastructure construction company interviewing the president, general
manager, each functional manager and senior project manager readjusted the
strategic behavior theory in Thai contractors applying in Cambodian contractor.
Under the case, the research findings of Hastheetham and Hadikusumo could be
validated in case of Cambodian contractor. Moreover, the case proposed that the
leadership style should be included as another component of project operational
strategy. The readjusted framework could serve as a systematical guideline to
develop integrated each level of strategic behavior and suggest the way of
choosing an appropriate strategy in a specific situation.
Key words: Strategic behavior, corporate strategies, business strategies,
functional strategies, project operational strategies, strategic result
performance, contractor.
Executive summary
Rationale of research
This research has been conducted to identify behavioural strategies of medium size contractors from Cambodia.
Objectives of study
The main objective of this
research is to analyse strategic behavior application in medium size contractor
in term of corporation strategies, business strategies, functional strategies,
project operational strategies and strategic performance.
Methodology
The methodology for qualitative study is formed by
instrument design, data collection, data analysis, and compiling the finding.
Qualitative study methodology (Case study) has its purpose to fulfill the
study’s objective which essays to study in medium size contractor of strategic
behavior.
Findings and conclusion
The
objective is to study strategic behaviour application in medium size contractor
in term of corporation strategies, business strategies, functional strategies,
project operational strategies and strategic performance. The literature review
had been completely conducted to synthesize the key terminology related to
strategic management in all level of the firm. The data analysis is purpose to
validate the case of Arthasith’s strategic behaviour framework which is applied
in Cambodia. To validate the data, the president and general manager of the
firm ‘A’ are the key respondents to choose, to recommend, to advise, to adjust
the attributes and provide more information the real firm practice.
Research Findings
The
research findings under the case of Cambodian contractor are significantly
valid the finding of (Hadikusumo & Hastheetham, 2011)
in the theoretical framework of strategic behavior in Thai construction.
·
Besides,
it is keen that the case in Cambodia proposed a very logical sense that company
should know itself about the internal strength and weakness. The case suggested
that expanding the horizontal growth whenever it intends to maximize the
strength while extending the vertical growth whenever it intends to overcome
its weakness.
·
Company
could not implement Knowledge management as to manager the project via
electronic media because of the limitation of communication infrastructure of
Cambodia.
·
Further
to another key finding that the case proposed is leadership style should be
integrated into the project operational strategy since it is one of the key
important success factors in the project.
Strategic behavior application in Cambodian medium
size contractor case
Key
implication of environment while the attributes finding stated below are the
Strategic behavior applied in each level of company’s case from the top level
management to the operational level. And it ends up with strategic performance
measurement. The information of each level strategy is analyzed in detail and the
framework which is applied and already adjusted by the case of Cambodian
contractor. The main factors found are:
·
Implication
of environment emphasizing on the internal and external environment
·
Corporation
strategy attributes are horizontal and vertical integration growth
·
Business
level attributes are mode and scope competition
·
Functional
strategy attributes include functional strategy, technology strategy, IT
strategy, procurement strategy, HR strategy, and marketing strategy.
·
Interestingly,
the project operational level attributes includes the leadership style of the
project management and followed by project focus, project structure, project manager
authorization, project knowledge management, and project communication.
·
The
strategic performance is subjectively and objectively measured.
Monday 6 August 2012
Construction Engineering and Infrastructure Management (CEIM) - AIT
International Study Visit to Ho Chi Minh city, Vietnam, 1st - 5th August, 2012
Construction Engineering and Infrastructure Management (CEIM) - AIT
CEIM students, AIT, had a successful study visit to HCMC visiting following sites
- North-South Expressway (Ho Chi Minh - Long Thanh - Dau Giay Section)
- Diamond Island project (District 2)
and attended Applied Project Management course in Public Infrastructure Projects taught by Prof. Gary Griggs, who come from Standford University. This course is offered by Professional Master Program in Project Management in Construction (MPM) in Vietnam (HCMC, Ha Noi, and Can Tho)
Meeting at Project Office, Ho Chi Minh - Long Thanh - Dau Giay Expressway Section, presented by Mr. Tatsuya Okamura (Nippon Koei), Project Manager.
Group photo
@ Long Thanh - Dau Giay Expressway site
Group photo at Diamond Island project - BTA Investment Management Ltd.
Presenter, Mr. Chau Anh Tuan, Project Director (left side) and Prof. Gary Griggs
CONTRACTOR’S
PRACTICE FOR MANAGING SUBCONTRACTOR: A CASE STUDY OF THE EVER RICH II PROJECT
IN HO CHI MINH CITY
By
Vo
Khac Kien
Abstract
In the recent
years, in most construction projects, particularly building projects prefer to
hire subcontractors. Consequently main contractor need to develop management
system standard in order to manage subcontractor rather than they will
undertake construction work by themselves. As a result, main contractor
concentrate on management strategies in term of tender process, type of
contract, schedule control, quality control, progress and payment, and
subcontractor safety.
In order to
understand how main contractor’s strategies manage their subcontractors, this
report was conducted through contractor documentation. The result shows
subcontractor control strategy in a local contractor. Major improvements are
needed for the subcontractor control strategy in local contractor in order to
improve the subcontractor management performance. However, there are some major
points, which need to be improved in order to strengthen and continually
improve the strategy performance.
Executive summary
Rationale
of research
This research has been conducted to identify Main Contractor’s
strategy for managing sub-contractors
within a project.
Objectives
of study
To
study management practices of contractors in contractor’s for managing
subcontractor in The Ever Rich II Project, Dao Tri Street, District 7, HCMC.
Find out strengths & weakness to propose recommendations.
Methodology
The
exploratory research method is used to study management practices in Vietnam.
Findings
and conclusion
In recent years, main contractor
have been trending to use subcontractor in specific area accordingly like as
specialist subcontractor, skilled-labor subcontractor and expertise provided by
subcontractor. Especially building project, it is common for 80 percent to 90
percent of the work to be performed by subcontractors.
However, there are many
subcontractors who do not have not enough expertise or skilled resources to
undertake work satisfactorily and, as a result, they are not able to bring good
services to clients or not reach their requirements. In order to resolve these
problems that main contractor needs to develop a strategy that allows
contractor to manage subcontractor effectively and efficiently.
According to the rationale stated
above, this study to conduct an investigation of main contractor’s strategy for
managing the subcontractor on construction project in terms of tender, unit
price contract, schedule control, quality control, progress and payment, and
safety.
Criteria Contractor’s
Strategy
Tender
o Experience in subcontractor tendering.
o Knowledge of material,resourses.
o focus on long-term relationship subcontractor.
o Time, quality of
performance, and price competitive are the project success measurement.
o Safety performance
plays important role in this project.
Contract
o Apply unit price
contract in order to save heavy cost of preparing many bills of quantity by the
subcontractor.
o Fair basis for
competition between subcontractors
o Changes in contract
documents can be made easily by the contractor compare to lump sum contract.
o Lower risk for
subcontractor compare to lump sum contract.
Scheduling
o CPM and Microsoft
Project was adopted as a toll for monitoring subcontractor’s schedule
o Using fast track
schedule in order to save the time.
o Weekly meeting and
monthly meeting in order to discuss the progress of subcontractor’s work
performance.
o Penalty for
subcontractor delay works.
o No bonus or
incentive for subcontractor early finish work.
Quality
o Developing quality
checklist to inspect subcontractor’s performance of each work.
o Materials enter in
and out site would be inspect and check using material record form.
o Weekly meeting
o Need worker
qualification standard for special works
o Requesting
subcontractor correct unacceptable works by a warming letter.
o Progress and
Payment
o Because of use unit
price contract so monthly progress payment based on actual quantity that
subcontractor done.
o Monthly progress
payment would be keep 5 percent retention that be paid on final progress
payment.
Safety
o Apply Environment,
Health and Safety requirements.
o Standard safety
policy.
o Providing PPE is a
obligatory condition during work at site.
o Conducting Job
safety analysis.
o Daily site safety
inspection by safety engineer
o Weekly meeting
would discuss safety issue and analysis site safety inspection report.
o Arrange safety
budget for safety program implementation.
Recommendations
·
Need
to develop standard for tendering for specialized sub-contractor.
· Main
contractor should arrange international formally contract in order to manage
subcontractor in terms of legal procedure.
·
Main
contractor should use IT to monitor progress.
·
Main
contractor should develop quality management process.
·
Main
contractor should record subcontractor database to be able to know
subcontractor information.
· Main
contractor should develop safety management system in order to analysis hazard
and minimize risk in subcontractor performance.
·
Main
contractor should develop long-term relationship with subcontractors.
Friday 3 August 2012
QUALITY
MANAGEMENT SYSTEM AND PERFORMANCE OF BUILDING CONTRACTORS IN VIETNAM
By
Bui Cong
Luan
Abstract
The study gives a thorough
description of the quality management system as practiced by the building
contractors in the construction industry. This function is shown as an
interconnected system that recognizes the main quality system management
activities. The documents and records used in these activities are also
reviewed. A model for high level quality system management is defined,
including owner, supervising consultants and contractors. The model depicts the
quality management system responsibilities and the roles in a scheme relating
to construction quality control, quality assurance, and the interface between
them. The scheme can be applied to any construction domain and quality
management structure of organization. The study advances the understanding of
how quality management is performed and engages participants at several
management levels. The use of quality management system in the construction
industry has greatly increased in recent years. Because the purpose of QMS
development is to manage the performance of building contractors in Vietnam, it
is is very important to assure quality in building projects and satisfy the
client as much as possible in the construction industry. The objective of the
quality management system is to improve the quality of construction projects
and to enhance the effect and productivity during the building project in order
to achieve client satisfaction. The research methodology is highlighted as the
main philosophy. Besides, different sources of data will be gathered in this
research, including project documents, reports from local government and
project agencies, newspapers, construction law and standards in Viet Nam etc.
An exploratory approach will be adopted by reviewing the available literature
to develop a quality management system framework for consultant supervision
building projects in Vietnam. Report the findings of a research study, which
was undertaken to examine the underlying factors affecting the quality of a
building project. It also aims to identify factors that show a strong
correlation to good quality performance. The ultimate goal is to provide
clients, project managers, supervising consultants and contractors with
information that can help them become more efficient with their limited
resources and, as a result, achieve better quality outcomes.
Executive summary
Rationale
of research
This research has been conducted to investigate quality
management system and performance criteria of building contractors in Vietnam.
Objectives
of study
To study Factors that affects the
implementation of QMS in building contractors in Vietnam. And effect of
implementation of QMS on the performance of building contractors in Vietnam.
Methodology
This research is based on a quantitative method with
a questionnaire developed for the data collection. This research framework
consists of four stages, namely conceptual stage, conceptual framework,
hypothesis development, questionnaire development, data collection and data
analysis in order to achieve the research objectives.
Findings
and conclusion
The research attempted to measure the
corporate performance though in term of NCR, Delay, Rework and Customer‘s
satisfaction. The analysis of means score has been employed to measure every
factor, sub-factor. In order to elucidate findings, the means have been
computerized to rank the factors and sub-factors as well. Particularly, the
means have been standardized into range scores to application quality
management system in practice. The main goal of this study is to finding the
effective factors that effect on the implementation of QMS in the building
contractors in Vietnam. This study also how to measure the implementation of
QMS to effect on corporate performance in terms Nonconformance records, Delay,
Rework, and customer‘s satisfaction. The purpose of this chapter is to
summarize the findings and to illustrate the conclusion from the above study.
The main findings
In this study the researcher study the quality management system
in building contractors in Vietnam, after literature review the researcher
found five main findings in this study as a conclusion in this study, it
includes as following:
1. In term of Culture the effective factors which have the highest
effectiveness to implementation of QMS is Benchmarking about quality of manager and Proud of technical competency.
2. In term of Administration the effective factor which has the
highest effectiveness to implementation of QMS is Clear job description.
3. In term of Leadership the effective factors which have the
highest effectiveness to implementation of QMS is Project leader is good in maintaining relationship with project
stakeholder.
4. In term of Strategy of quality the effective factor which has the
highest effectiveness to implementation of QMS is Focus on improving the quality of human resources.
5. The greatest impact
to the corporate performance that is the application of the procedures in the quality
management system.
In addition, the research also shows the
correlation between the application of quality management systems in the
construction contractors in Vietnam for the effect that the company achieved in
terms of the NCR, delay, rework, and the customer satisfaction. however, within
the scope of this study the researcher also pointed give some fundamental
processes in many of the quality processes that contractors can apply to their
company, and processes that was elaborated by the specific issues. And the
results are also given the relationship of each issue with the company's
performance at different levels. Also on the factors affects to the application
of quality management systems in Building contractors in Vietnam, the results
also showed that almost of the factors that research given has significant
positively to the quality management system, and what factors most influential
was pointed out .
Monday 30 July 2012
RISKS ON
SCHEDULE OF NUCLEAR POWER PLANT PROJECT IN
VIETNAM
By
Nguyen The
Phuong
Abstract
The research focuses on risks that can occur and
made Vietnam NPP project delay. The main objectives are following: (1) to study
risks which may affect to schedule of NPP project; (2) to study the difference
perception of three major parties in project, owner, consultant and contractor;
(3) what is most important risks in each stage of project; and on responsibility
of major parties in project.
At the beginning stage, all risks that are related
to NPP project in Vietnam searched. It is made though breakdown the procedure
for NPP project; collect schedule risks of NPP projects in the world; risks
from construction project studies and guide, experience from some international
experts. The questionnaire is built with 81 risks, divided into 11 groups: risks
relate to project decision - making stage; bidding stage; design stage; owner
and consultant in construction stage; contractor in construction stage;
payment; commissioning and pre-operation; human resource; government
management; regulation, approval; and external risk.
The quantitative method is used to assess the risks,
include level of likelihood and consequence of the risk. Respondents are
consultants, contractors, owners, experts who have experience in NPP and
knowledge about Vietnam investment environment. A total of 62 respondents
completed the questionnaires. After collecting the data, risks were ranked base
on likelihood, consequence and important mean in total the project and in each
group, in that delay in approval procedure for site selection is the most
important of the project.
There are differences in perception of parties.
Owners indicate that most causes of delay are related to contractor and regular
– approval; consultants agreed that problems relating to government and some of
owner are most important; while, contractors pointed out that important risks
are responsibilities of owner and some are of government. In assessing the level
of most important risks, mean of important risks is calculated by owner is the
lowest, and of contractor is the highest.
The result has indicated that the most important
problems of Owner that cause delay in the NPP project are regulation approval;
management; human. Most responsibility of contractor came out during the design
stage. While, Government has great responsibility related to regular approval
problem; finance; and human resource.
Executive summary
Rationale
of research
This research has been conducted to study delay risk in Nuclear
power plants projects in Vietnam.
Objectives
of study
Study risks which may affect to schedule of NPP
project and difference in perception of three major parties in project, owner,
consultant and contractor.
Rank most important risks at each stage of project; on
responsibility of major parties in project.
Methodology
The literature review of management process is
studied to find out the main activities, its tasks and risks in each task was
analyzed first. Finding schedule risks in construction, NPP project in the
world also on documents and from international experts, the owner, contractor
and consultant.
Data collection, information, opinion about the
risks had been collected from experts about NPP project.
Findings
and conclusion
Based on the world reports about the NPP project
practice, delay in construction project in
Vietnam, opinions of experts, partners’ relation to
the project, and researcher get 81 risks that can influence to schedule of NPP
project in Vietnam. The project was done for a long time. In addition, this is
the first time Vietnam builds a NPP project, so there are many new problems
arisen in human resource and regulatory. Total risks are divided into 11 groups
which include: risks relate to project decision - making stage; bidding stage;
design stage; owner and consultant in construction stage; contractor in
construction stage; payment; commissioning and pre-operation; human resource;
government management; regulation, approval; and external risk.
Responsibility of major parties
- Owner
Result has indicated that the first problem of Owner
that cause delay in the NPP project is regulation approval. Many great risks in
the area are delay in approval procedure for site selection and delay in
licensing procedure in the design process. The second problem of
Owner is management. The risks which are indicated
the most are poor management of owner in budgeting and scheduling, ultimate
cost of the plant exceeds original budget and funding expectations. Another
important problem of Owner is human resource. Owner’s lack of trained personnel
and lack of qualified professional in bidding stage are two risks indicated.
- Consultant
Consultant has the responsibility to assist Owner in
management the project. So, the responsibility about human resource should also
divide to Consultant. Besides, consultant is still warned with communication,
coordination between parties, conflict and lack of supervision in a number of
jobs problems.
- Contractor
Most responsibility of Contractor came out during
the design stage. The most problems occurred are late design completion and all
identifiable engineering before construction starts; and design that does not
meet the quality and safety standard. In addition, some other problems that can
influence to schedule of the project are shortage of experience, skill workers,
equipment’s, error in construction of sub-contractor, and machinery breakdown
in hot testing and commissioning phase.
- Government
Government has great responsibility related to
regular approval problem in the first NPP project. Delay in approval procedure
such as licensing procedure and lack of circular, and regulations are most
interesting to almost all parties. The second issue is about finance like delay
in state budget due to political decision associated to financial conditions
and difficulty in arranging foreign loans are ranked at high level. Third is
human resource problem that all parties are worried. In this problem,
regulation, training, and research agency’s lack of manpower is point out. The
last most important risks of Government are related to management problem, in
that, typical is lack of regulation and support agency relating to the project.
Subscribe to:
Posts (Atom)