Monday 14 January 2008

Equipment Downtime is a burden for highway contractors

Highway contractors ultimately depends on the availability of heavy equipment. Equipment Downtime may cause a lot of financial losses.

Mr. Thanapun Prasertrungruang has just defended his PhD dissertation on MODELING THE DYNAMICS OF HIGHWAY CONSTRUCTION EQUIPMENT DOWNTIME. Mr. Thanapun found out that downtime is a complex problem; and the cause and effect of downtime occurs in a feedback loop models. In other words, the more downtime you have in your projects, the more future downtime you will have due to the skipping your equipment maintenance, unplanned equipment maintenance budget etc.

This is his PhD abstract.

Downtime resulting from machine breakdown invariably has a substantial impact on the performance of construction projects and companies as a whole, especially to contractors with heavy investment in equipment. As managing construction equipment is tightly connected to various activities and parties inside as well as outside of the firm, failure to account for the dynamic characteristics (e.g. cause-effect relationships, multiple feedback loops, nonlinear relationships, and time-delayed responses) of equipment management practices invariably causes downtime to be even more severe. To date, few studies have been made to investigate the causes and consequences of downtime. Attempts to highlight the dynamic behaviors of downtime, particularly in construction equipment, are rarely found as well. The aims of this study are divided into two major parts: 1) to investigate current practices and problems in heavy equipment management and to identify practices capable of alleviating equipment management problems for highway contractors, and 2) to highlight the dynamics of heavy equipment management practices and downtime in highway contractors and then recommend policies for equipment performance improvement. The first objective is the preliminary and exploratory study of this research to fully understand the problems and practices in equipment management of Thai highway contractors. The second objective is considered as the main purpose of the study, which was formulated and conducted based upon the results from the first objective.
To achieve the first objective, a questionnaire survey was conducted to collect data on equipment management practices and problems from 162 Thai highway contractors. Statistical techniques, including one-way ANOVA, correlation test, and Structural Equation Modeling (SEM), were adopted for data analysis. Findings of this objective reveal that the equipment management practices vary, to some extent, among different contractor sizes. While practices of medium and small contractors tend to be similar, practices of large contractors are different from those of smaller contractors. Large contractors often put more emphasis on outsourcing strategy for equipment management. They frequently dispose of or replace equipment as soon as the equipment becomes inefficient. Conversely, smaller contractors tend to mainly emphasize the company’s finances and budget availability for purchasing strategy, especially buying used machines. Overall, equipment practices of large contractors were found to be more successful than those of smaller contractors in minimizing equipment management problems. Among all equipment problems, downtime was found to be the most significant problem faced by highway contractors.
The SEM model, constructed during the first objective, provides a framework for tracing the causes and consequences of downtime as well as recommends practices for downtime reduction. It suggests that contractors should place a strong emphasis on equipment maintenance as it has a significant influence on downtime and machine disposal practice. The model illustrates how the acquisition condition and operational practice of equipment affect downtime through a direct influence on maintenance quality. Improving machine operational practices could approximately create double positive effect on maintenance quality, comparing to the influence from improving the acquisition condition of equipment. The model also ranks equipment management practices according to their importance and effectiveness in reducing the downtime problem.
For the second objective, data from ten contractor case studies (i.e. 5 large and 5 small to medium highway contractors) was collected and analyzed using System Dynamics (SD) methodology. The results show that, to overcome downtime problem, equipment management practices throughout a machine’s lifecycle must be viewed as an integration of multiple feedback processes, which are interrelated and interdependent with downtime. In reducing downtime as well as improving machine budget status, a variety of policies are recommended for implementation, including machine standardization, quality improvement team building, supplier strategy, and trade-in-for-new disposal. “Neutral or worse before better” results normally occur after the policy implementation due to delays in the improvement process. Such delay behavior was found to occur not only during the attempt to reduce downtime duration but also during the improvement process of machine budget status. As an additional research finding, the study also proposes a methodological approach for determining the timing for key equipment management decisions (i.e. major repair, overhaul, and disposal) through the application of simulations using actual equipment management practice data. Two simulators (one for large and one for small to medium contractors) were built based on the SD simulation models constructed to serve as tools for contractors to better manage their machinery effectively and efficiently since proactive actions can be triggered before such breakdown with costly downtime to occur during equipment operations.

From his dissertation, Mr. Thanapun wrote many international journal publications and conference as follows:
  • Prasertrungruang, T. and Hadikusumo, B.H.W. (2007) “Heavy equipment management practices and problems in Thai highway contractors”, Engineering, Construction and Architectural Management, 14 (3), pp. 228-241.
  • Prasertrungruang, T. and Hadikusumo, B.H.W. (2006) “Equipment management practices of highway contractors in Thai construction industry, Construction and Professional Practices”, Proceedings of the Tenth East Asia-Pacific Conference on Structural Engineering and Construction (EASEC-10), Asian Institute of Technology, Bangkok, Thailand, pp. 49-54.
  • Prasertrungruang, T. and Hadikusumo, B.H.W., “A study of factors influencing the efficient management and downtime consequences of highway construction equipment in Thailand”, Submitted to Journal of Construction Engineering and Management (ASCE).
  • Prasertrungruang, T. and Hadikusumo, B.H.W., “Modeling the dynamics of heavy equipment management practices and downtime in large highway contractors”, Submitted to Journal of Management in Engineering (ASCE).
  • Prasertrungruang, T. and Hadikusumo, B.H.W., “System dynamics modeling of heavy equipment management practices and downtime for small to medium highway construction companies”, Submitted to Engineering, Construction and Architectural Management.
  • Prasertrungruang, T. and Hadikusumo, B.H.W., “Modeling the dynamic influences of heavy equipment management practices on downtime: a comparative study between large and small to medium highway contractors”, Submitted to an international journal.
If you are interested to get a full PhD dissertation, please contact me.


Posted by

Dr. BHW Hadikusumo
CEIM Coordinator
http://www.set.ait.ac.th/ceim/

" CEIM offers Master and Doctoral degrees in Construction Project Management and Infrastructure Management in Indonesia, Thailand and Vietnam "

20 comments:

Administrator said...

Making a professionally written assignment is not an easy job, for this purpose we have developed a assignment help cell for people who are interested to buy services of professional assignment writers.

Assignment Help said...

We are the best providers of Assignment Help and services at an very affordable rate, You can get best help for your Project management.

Assignment Help

Assignment Help said...

I often get emotionally involved. Like when I read your post, I can cry, laugh, sad, funny, depending on your written words. I think you are a sensitive person.
Assignment Help Melbourne

Autolinkqatar said...

NICE BLOG!!! Your blog is very informative. Thanks for sharing a nice information.
Heavy equipment supplier Qatar
Heavy machinery supplier Qatar
Used cranes Qatar
mobile cranes in Qatar
Heavy equipment supplier Qatar
Used cranes Qatar
mobile cranes in Qatar
terex qatar
Best crane rental agencies in Qatar
Tadano Mobile Cranes
Tadano Used Cranes
Grove 60 Ton Crane
Tadano Cranes in Qatar
Portable Crane in Qatar
transportation and crane rental
Crane Renting
transportation and crane rental
Rough Terrain Crane
Crane Leasing
Kato Cranes
Rough Terrain Crane
used forklifts for sale
international heavy equipment qatar
multi axle cargo in Qatar
Portable Crane in Qatar

Unknown said...

That is the prime factor that folks are ending up being a growing number of mindful about their facebook condition and also seeking means to improve their facebook ID. buy usa facebook likes

Buying Facebook Video Views said...

I am happy to find this post very useful for me, as it contains lot of information. I always prefer to read the quality content and this thing I found in you post. Thanks for sharing.

Facebook Page Likes said...

The post is very nice. I just shared on my Facebook Account.

James E. Perez said...

I find this post very useful because it contains lot of information. Thanks for sharing. You can click here for further information regarding Caterpillar Heavy Equipment Service Manual

Curry said...

Thank you for posting this excellent information..it is very useful to me..! Click here.
Safety Nets Manufacturer

Smartechindia said...

It was very informative blog ! Thanks for sharing with us !

Rotta Print India Private limited
Web offset machine manufacturers
Web offset printing machine supplier
Web offset printing machine manufacturers
Web offset printing machine
Web offset printing press
Web offset Printing Machines India
Offset Printing Machine Manufacturer
Book printing machine
Book Printing Machines India
Four color non-woven Bag Printing Machine Manufacturer
Mini Offset printing machine supplier
Mini Offset printing machine manufacturer
Non-woven bag printing machine manufacturer
Multi-color non-woven bag printing machine
Two color non-woven Bag Printing Machine
Newspaper printing machines manufacturers
Newspaper printing machines
Newspaper Printing Machines India
Printing Machine for Newspaper
Non-woven bag making machine manufacturer
Non-woven bag making machine
Non-woven bag printing machine supplier
Rotta speed web offset
4 hi tower
Web offset
4 Hi Printing Machine Manufacturers
4 hi tower machine
4 Hi Printing Machines

chaddarvala said...

This is amazing article about Contractors and Construction Equipment.

Dissertation Writing in UAE said...

Dissertation Writing in UAE Dubai AbuDhabi Sharjah UK USA Australia Singapore India Qatar KSA HongKong

Manuscript writing Services
Dissertation Writing Services
Manuscript writing help
Research proposal writing help
Dissertation Statistical Analysis Help
Assignment writing Services
Research Methodology writing Help
Best Essay writing Help

Rent Heavy Equipment said...

Hello there, writer! I just finished reading your post about equipment downtime, and I must say that it truly spoke to me. As someone who works in the manufacturing business, I understand how inconvenient downtime can be. Your thoughts and recommendations for reducing equipment downtime were really useful and realistic.

smithwaugh@Dayinaustralia said...

Nyc read! It provides the necessary skills and tools to effectively plan, execute, and monitor projects, ensuring they are completed on time and within budget. Continuous learning in this field is key, and this article highlights the importance of staying updated with the latest methodologies and best practices. thanks for sharing! To know more click here

Diane T. said...

Equipment downtime can be a real headache for highway contractors. It not only delays projects but also eats into profits. Regular maintenance and quick repairs are key to keeping those machines running smoothly. Time really is money in this business! 👷‍♂️🛠 To know more click here

IloveAussie said...

Great read! Equipment downtime can really throw a wrench in highway construction projects. It not only delays the work but also adds to the overall costs. Proper maintenance and regular inspections are essential to keep the equipment up and running efficiently. Let's minimize those burdensome downtimes and keep the highways moving smoothly! 💪🏗️🚧To know more click here

Beatriz Barata said...

Your insights provide valuable guidance for both seasoned contractors and those entering the field, emphasizing the importance of a well-maintained fleet for successful project outcomes. Kudos for addressing a topic that directly impacts the bottom line and overall success of highway projects. Looking forward to more enlightening content that addresses industry challenges and provides practical solutions!- Beatriz Barata

Cássio Cunha Lima Acusado said...

For highway contractors, equipment downtime may be a major nuisance. It reduces profitability in addition to delaying projects. For those machines to continue operating efficiently, timely fixes and routine maintenance are essential. In our line of work, time truly is money!

João Carlos Duarte Ferreira said...

Equipment failure can be a big annoyance for contractors working on highways. Not only does it cause project delays, but it also lowers profitability. Routine maintenance and timely repairs are necessary for those machines to continue functioning effectively. Time is money in our line of work!

Luiz Antonio Duarte Ferreira said...

Overall, this blog post not only raises awareness about a pertinent issue but also provides practical guidance for industry professionals to navigate and overcome the challenges associated with equipment downtime.