EPCI contracts for the construction of oil and gas facilities have has a poor track record recently. As owners, Oil and Gas Companies want facilities delivered on time, on budget, and with high quality. For various reasons, contractors rarely reach performance goals set by the owner.
The Oil and Gas industry as a whole has seen a dismal failure of large EPC projects over the last decade. Reasons range from aggressive appraisal strategy by operators leading to poor definition of the project to sloppy performance by contractors whose focus is only on protecting profits and avoiding penalties.
Many owners have experienced massive losses due to time and cost overruns in their EPCI contracts, which in turn has made their profits less significant in the light of a discounted cash flow analysis.
Mr. Tran Dang Thuyet made a study which main goal is to learn owner’s EPCI Contract Management for Oil and Gas development project and to develop a guideline for Oil and Gas owner to perform EPCI Contract Management successfully and effectively.
Conclusion
1. Based on the result, the EPCI Project Contract Management of Owner is considered performing effectively if the following conditions are met:
a. Minimizing delay of the project
b. Minimizing overrun cost
c. The quality of facility met the requirement for the purpose of procurement
d. Build a good relationship between the owner and the contractor
2. However, minimizing the delay and overrun cost are difficult tasks which were rarely reached by almost owner of the projects, especially by Vietnam Oil and Gas project’s owner. And the Owner in this studied case was also not able to manage the contract effectively and successfully in order to minimize delay and overrun cost.
3. A key point is that business risk can never be transferred to the provider. Although the provider may be under severe financial pressure for non-fulfillment, this will not compensate the department for failing to fulfill its obligations and deliver key outcomes. Therefore selection of the right contractor and placement of right contract is very important, this is critical factor decide the success of overall contract management.
4. Installation barge for offshore project is a critical factor for success of an offshore development project. Selecting an appropriate contractor for an EPCI contract for Oil and Gas must base on their availability of the installation barge.
5. One fact that the cap of penalty of delivery liquidated damage as per Vietnam Construction Law which does not exceed 10% of the contract price normally does not cover the cost impact to the owner and the lost business interest causing by the delay.
Recommendations
1. Recommendations to Owner of the studied EPCI Project for the Improvement of Contract Management Process:
i) Select right provider (bidder):
• Bidder Pre-qualification and Bidder Qualification should be considered as important activities of contract management process.
• For the offshore development project, the availability of installation barge must be considered as a critical factor to select bidder.
ii) Place right contract:
• Risk: Analysis and allocate risks properly in the EPCI contract, for example: If the project delay cause by contractor side, all contractor’s claims relating to weather standby or company force account during the extension period will be rejected.
• Contract Form: Should develop flexibly standard EPCI contract form based on the experience of past projects.
• Clause and Conditions:
• Clauses and Conditions should be drawn basing on win-win negotiation strategy with involvement of experts in all disciplines.
• DLD should be increased to reasonable level (higher than 10 % of Contract price) to force contractor focus to the contract performance, especially to force contractor to provide the dedicated installation barge for the offshore development project.
iii) Maintain data record of completed project: The lesson learnt and project
data record should be recorded properly for future project.
2) Recommendation for Project Organization Improvement:
• Develop and reorganize the EPCI project organization.
• Get personnel to be trained properly.
• Use outside manpower resource (consultant service) if need.
3) Recommendations for Improvement of Procurement Systems
• Develop the procurement procedures and standard forms properly.
• Use consultant service in preparing procurement documents if need.
• Develop Procurement Data Record for each project.
• Develop and implement Lesson Learn after each project.
• Create, develop and apply the tool and techniques in selection sellers properly.
• Propose to the Government Office/Authorization to change and the bid evaluation laws and cap of penalty of Liquidated Damage which cause disadvantages to the owner (owner) of project (contract).
Recommendations to all Owners of Vietnam Oil and Gas EPCI Projects
i) The Owners of Oil and Gas EPCI project should get lesson learn from their previous projects as well as from other owner’s project.
ii) Create and develop their own procurement system, procurement documents and organization properly.
iii) For the owners who do not experience in EPCI project should use EPCI Management service.
iv) Study guidelines, standards, regulations and laws issued by Government to find out disadvantages causing to the owner of project to propose changes to these guidelines, standards, regulations and laws to the Government Office.
His thesis abstract is copied and posted.
Abstract
The primary consideration in the procurement of Oil and Gas Development projects is the need to obtain best value for money in the whole life of the service or facility. The design and operation of the facility should maximize the delivery of effective required services; this is most likely to be achieved through integration of the design, construction, operation and ongoing maintenance.
Engineering, Procurement and Construction, Installation (EPCI) Contracts are a common form of contract used to undertake construction works by the private sector on large scale and complex oil and gas projects. Under an EPCI Contract a contractor is obliged to deliver a complete facility to a developer who need only 'turn a key' to start operating the facility, hence EPCI Contracts are sometimes called turnkey construction contracts. In addition to delivering a complete facility, the contractor must deliver that facility for a guaranteed price by a guaranteed date and it must perform to the specified level. Failure to comply with any requirements will usually result in the contractor incurring monetary liabilities.
However, EPCI contracts for Oil and Gas Development project have has a poor track record recently. As owners, Oil and Gas Companies want facilities delivered on time, on budget, with high quality. For various reasons, contractors rarely reach performance goals set by the owner.
It is timely to examine EPCI Contracts and their use on oil and gas Projects and the problems impact to the Owner of the contract. In this study, the author focus on Owner’s EPCI Contract Management in order to find out the causes of problems occur and impact to the Owner Contract Management and also to find out the factors causing un-success and inefficiency of the owner’s EPCI Contract Management and through that, propose recommendations of solutions enabling the Owners of Oil and Gas project perform their EPCI Contract Management more effectively and successfully.
10 comments:
Thank you for your post :)
Thanks to author for this post it’s very easy to understand about the storage tank (pressure). Storage tanks are used to store hot and cold water, fuel and oil storage etc. Storage Tank- Manufacturer, Supplier and Exporter of Storage tanks in Delhi, Provides various types of storage tanks like pressure vessel, hot water storage tanks, propane storage tanks, plastic water storage tanks, fuel storage tanks and cold water storage tanks.
that's nice blog mentioned by you.Oil and Gas Malta is so good.
This article is so good for Malta Colleges.Oil and Gas Degree is so good.
Thanks for giving such a valuable post with us, and also check below for more details about contract ManagementContract Management Software
Hello, an amazing Information dude. Thanks for sharing this nice information with us.
Accounts Payable Software
Your blog is filled with unique good articles! I was impressed how well you express your thoughts
Get best contract management software for healthcare.
Thanks for sharing Good Information
contract management system
contract management software
I was scrolling the internet like every day, there I found this article which is related to my interest. The way you covered the knowledge about the subject and the 2 BHk Flat Ayodhya Bypass Road Road
was worth to read, it undoubtedly cleared my vision and thoughts towards B 3 BHk Flat in Ayodhya Bypass Road
. Your writing skills and the way you portrayed the examples are very impressive. The knowledge about 4 bhkflats in Ayodhya Bypass Road
is well covered. Thank you for putting this highly informative article on the internet which is clearing the vision about top builders in Bhopal and who are making an impact in the real estate sector by building such amazing townships.
This technical post helps me to improve my skills set, thanks for this wonder article I expect your upcoming blog, so keep sharing..
Procurement Management Software
Procurement Management System
e Procurement Management Software
Best Procurement Software
Procurement Software Companies
Post a Comment