This is a blog managed by Construction, Engineering and Infrastructure Management (CEIM) at Asian Institute of Technology, Thailand. In this blog, CEIM shares our activities in providing excellent professional project management education at Master and Doctoral levels in Thailand, Indonesia and Vietnam. http://www.set.ait.ac.th/ceim/
Friday, 29 November 2013
PROJECT FINAL EXAMINATION
MPM HO CHI MINH CITY - INTAKE 2012
16th - 23th November 2013
MPM program successfully organized Project Final examination
for MPM students at AITVN in Ho Chi Minh city, Ha Noi and Can Tho city from 16-23 Nov 2013. Committee members
were Dr. Hadikusumo, Dr. Chotchai, Dr. Santi and Dr. Santoso.
Students who have passed this exam and fulfilled all graduation requirements will attend the Graduation ceremony at AIT Thailand on 17 December 2013.
Final report presentation in Ho Chi Minh city |
Final report presentation in Ha Noi |
Final report presentation in Ha Noi |
Thursday, 28 November 2013
Owner’s Project Life Cycle Approach
In
recent years, VRC has invested big amount capital for expanding rubber
plantations and upgrading rubber processing facilities both domestic and
outside the country. VRC has been carrying many rubber plantation projects in
Cambodia, Laos and has been negotiating with Myanmar government. For VRC, the
concept and practice of owner’s project life cycle have been used in rubber
plantation projects. Nevertheless, VRC has not built a type of project life
cycle appropriating with its specific characteristics; therefore, some projects
meet with serious difficulties during performance. Although Cambodia projects
are now just in middle of project life cycle but many problems happened like
the costs balloon out of control, the
scope expands beyond reason, the project slips behind schedule, and the
deliverables do not possess expected value in Cambodia projects.
According
to internal audit and the report of situation of the project management in
construction of VRC in the period of 2007-2010, it shows many problems
happening with VRC’s oversea rubber projects, especially cost and schedule. The
problems, according to reports that VRC’s projects encounter as follows:
-
Cost
overrunning or over budget;
-
Projects
are prone to delay;
-
Project
quality uncontrolled;
-
Project
scope creep.
Also
according to this report, VRC recognize
the bad results in Cambodia are created by many reasons; however, poor
management of the project life cycle is one of the reasons brings about serious
consequences including the followings:
-
No
establishing a framework of project life cycle;
-
Project
proposals and business cases and project selecting process in the first phase
were carried out incautiously have impacted to all remain phases of the project
life cycle;
-
Some
projects do not have a strong project management team;
- Inadequate
delegation from VRC’s head quarter and the project organization is not
properly;
-
Lack
of managerial skills and competencies as well as the internal capacities of the
owner
VRC
consider that the result of poor management of the project life cycle is one of
the causes impact to the projects negatively. They are the critical problems
which VRC and other related parties to Cambodia projects need to consider
cautiously.
Do Huu Phuoc made a case study to study Vietnam Rubber
Company’s project life cycle approach, analyze situation and develop a
framework of project life cycle of a rubber plantation project and guideline to
possibly ensure the projects deliver on time, on budget and to the level of
quality expected.
Conclusion
for VRC’s project life cycle approach
There
is no single best approach in organizing project management throughout a
project's life cycle. All organizational approaches have advantages and
disadvantages, depending on the knowledge of the owner in project management as
well as the type, size and location of the project. It is important for VRC to
be aware of the approach which is most appropriate and beneficial for a
particular project. In making choices, VRC should be concerned with the life
cycle costs of planted rubber trees, constructed facilities rather than simply
the initial costs.
Saving
small amounts of money during construction may not be worthwhile if the result
is much larger operating costs or not meeting the functional requirements for
the new facility satisfactorily or the objective is not align with the scope.
Thus, generally a project or particularly a rubber plantation project wants to
finish successfully it must be very concerned all the phase of the project life
cycle.
Recommendations
With so many ongoing
projects like situation at present, VRC may encounter difficult for all
projects to get adequate support, or even the attention of top managements. The
particularly common problems when trying to manage multiple projects
concurrently may be:
a. There
is no time for summary experience lessons so the mistakes from a project can
repeat to all projects.
b. Delays
in one project may drag other projects delay because of common resource needs
or technological dependencies;
c. The
inefficient use of corporate resources results in hills and valleys of resource
utilization;
d. There
are unwholesome competitions between project teams to get support, or the
attention of top managements;
VRC
should consider a temporary stopping with the current projects to review all
the problems happening. The lessons learn from projects should be analyzed,
critiqued and documented for later use by the future projects and any other
projects will be performed by VRC in Cambodia or other countries in the future.
This study has concentrated on owner’s approach in
managing project life cycle to an agriculture project. However, there are many
aspects relating to the project management. Further studies should be carried
out to find out the approach of owner for agriculture project management.
Abstract
Project life cycle is an approach that links
the phases, which can lead to significant results required for completing a
project. As the owner has the most authority in enforcing the implementation of
constructability, the owners' awareness of the benefit of the project life
cycle is the most important. Project owners must be aware that the decisions
that are made in the stages of projects are difficult and costly to change once
construction begins.
Owners should recognize that there is no
single best approach in organizing project management throughout a project's
life cycle. All organizational approaches have advantages and disadvantages,
depending on the knowledge of the owner in project management as well as the
type, size and location of the project. It is important for the owner to be
aware of the approach which is most appropriate and beneficial for a particular
project. In making choices, owners should be concerned with the life cycle
costs of constructed facilities rather than simply the initial construction
costs. Saving small amounts of money during construction may not be worthwhile
if the result is much larger operating costs or not meeting the functional
requirements for the new facility satisfactorily.
However, the traditional approach to project
life cycle limits their option for involving in the phases of the project. The
general lifecycle model that an organization use will probably be similar to
one that has been used dozens or hundreds of times at other organizations.
There is no reason to reinvent everything for your own project. It just takes
longer and contains more inherent risk. The better approach is to utilize a
standard set of lifecycle processes, techniques and templates which to be used
in the same industry.
Wednesday, 27 November 2013
Planning for Improving Efficiency of Housing Project’s Development Process
According
to the Governmental Investment Project Assessment Report for the year 2009 by
Ho Chi Minh City People’s Committee, there are 1,177 projects completed until
end of the year 2009 (which are currently equal to 20% of 5,886 operational
projects in Ho Chi Minh City). However, 65% of the projects were delayed and 20
projects only achieved up to 30% of the target progress. This is due to the
following reasons:
(i)
Weak financial capacity of the project owners.
(ii)
Lack of experienced project managers and project management human resources.
(iii)
Long period for authority submission and lack of transparency of Vietnam law
and regulations.
(iv)
Land clearance and resettlement.
Bui
Quang Huy made a case study which main objective is to investigate the basic
requirements by Vietnam law and regulations, the common practice of housing
development projects in Vietnam complying with Vietnam law and regulations; and
to find out a more efficient process for developing a housing project in
Vietnam.
Conclusions
The
housing development industry has its own characteristics. Every single activity
in the project development process has to comply with local law and
regulations. Hence, the good understanding about local law and regulations is
very useful for developers in their business. The success of the case project
in this study also depends very much on the understanding about local law and
regulations beside the project management knowledge.
The
old practice of housing project development process complying with Vietnam law
and regulation is not efficient, it takes 60 – 78 months to finish the project
from the feasibility study and planning phase to handing over and obtaining the
ownerships for the house buyers. The longer the project development period is,
the more costly the investment in housing projects is. Besides, Vietnam
population and housing demand are developing very fast; the supply could not
satisfy the demand. Hence, the housing price could not be reduced and a major
part of people with low and medium income do not afford to buy houses. It
causes a lot of social issues in Vietnam.
With
the improved housing development process proposed, it takes 45 – 57 months to
finish the project. If we only consider the Project Launching Preparation
phase, the saving is 15 – 21months, it takes 12 -15 months in the improved
process instead of 27 - 36 months of the old process. This is a valuable improvement.
The investment in housing project becomes more efficient when the developers
can recycle their investment faster and cut down financial cost in housing
projects. It helps to increase the supply of housing products and reduce house
price.
Besides
the understanding about Vietnam market, the knowledge from lean production and
last planner theory also offers a basis for evaluating the whole development
process of housing projects and identify waste times in the process. The
project manager/ planner should examine and schedule the project with all
constituent and continuous activities as a whole. By implement that, it will
make the timing of whole project period more efficient, rather than only taking
care of shortening the period of its individual activities. The application of
lean theory is absolutely suitable for the current situation of Vietnam housing
market. It helps to shorten the project development period and make the process
more efficient by ignoring waste time. There are no additional costs to apply
these theories.
Recommendations
In
general, when the understanding about local law and regulations is very
important in housing project development, the developers should continuously
update and study local law and regulations, especially, the new issuances.
A
good relationship with government also helps developers in their submission
works. This relationship could be created by contributing to society and
maintaining the good image in the local market, the developers should properly
deliver what they committed to the government and buyers.
The
developers are recommended to maintain their efforts in evaluating the working
and project development process to find any problems for improvement, not only
waste of time, but also any other wastes such as cost, manpower, etc.
Lastly,
the good schedule should never achieve the good actual result if it is not well
controlled. The control system also needs to be established to monitor the
execution of the project to ensure it is carried out in accordance with the
plan.
ABSTRACT
Vietnam
is a developing country which means that the country need a lot of knowledge
for development, especially in the field of construction project management.
Some
“old men” think that all the construction projects are similar, about the
process, technology and method, especially housing development projects. They
are actually not similar, there are many projects carried out in such a way of
wasting time and cost; and achieving bad quality.
In
this study, a more efficient process for housing development project is
introduced. Hopefully, it could help the project managers / planners schedule
and execute their projects strictly complying with the local law and regulations,
in shorter cycle without any additional costs for advanced technology and
materials.
This
study also affirms that there is always un-efficiency in project development
process of every construction projects. The project managers should always spend
enough efforts to identify wastes and improve them. This is helping the
projects, the company and the country, in a wider angle of view.
Tuesday, 26 November 2013
Engineering, Procurement, Construction (EPC) Contract Management
Engineering, Procurement, Construction, Pre-commissioning,
Commissioning for the well, wellhead platforms, offshore facilities are
considered to be very risky because of their complications and large money
required, therefore we need good contract management to check whether the
obligations, rights, specification, performance, commitment and so on are met
properly and to optimize contract performance, eliminate risk involved in EPC
contract throughout the lifecycle.
Not having a good contract management process in place has
consequences both to the Client and the Contractor as well as to Consultant
Company, Vendor, and Sub-contractor (if applicable). If the Contract Management
is not managed, controlled, monitored, and implemented properly, the parties
are likely to fail to meet its goals that they had for the project associated
with the contract. Such failures may include delayed schedule, cost overruns,
quality, safety and more.
EPC
contracts have been used in both medium and complicated large scale oil and gas
projects in Vietnam since 1990s. Phan
Tuong Liem made a research by studying
EPC Contract Management of his own project (Rang Dong Full Field Development
Project Block 15.2 Offshore Vietnam). The objectives of his study were to:
1. study
implementation of JVPC EPC contract management.
2. state problems that occurred in the execution of
EPC project.
3. give out some recommendations to EPC contracts.
4. learn lessons from JVPC
project.
Conclusion
In order to have a successful project, contract management played
an important role. During the administration of a project, any major or minor
activities involved a sequence of activities that were covered by different
Clauses and Sub-clauses in the Contract.
However, in reality not all Clauses/Sub-clauses covered all activities
without unchanged, unrevised. Because of modification and design change which
were not fully mentioned in the Contract, as well as cost of extra work and so
on.
The contract usually had at least three copies to be distributed:
original copy for The Client, Contractor and filed Field Contract Manager to
follow.
Contractor knew how to allocate manpower, material, and
equipment to meet the project target. Any personnel involve in the project
especially key personnel had their profiles to show that they were qualified,
competent and approved by the Client.
Abstract
Contract Management is the process that enables both parties
to a contract to meet their rights, duties, obligations and responsibilities
(i.e. allocate the risks) in order to deliver the objectives, services,
required from the contract.
It also involves building a good working relationship
between the customer and provider in general, and between Owner and Main
Contractor or Main Contractor and Subcontractor so on. It continues throughout
the life of a contract and involves managing proactively to anticipate future
needs as well as reacting to situations that arise.
The main purpose of contract management is to obtain the
services, performance, commitments as agreed in the contract between the Client
and the Contractor. This means optimizing the efficiency, effectiveness and
economy of the service, the performance, or relationship described in the contract,
balancing costs against risks and actively managing the Clients/Owners and the
Contractors relationship. Contract management may also aim for continuous
improvement in performance over the life of the contract.
Friday, 22 November 2013
Investment Risk Factors in Foreign Oil and Gas Investment Projects.
the content of this page has been moved to
Thursday, 21 November 2013
Sub-Contractor Management in Gas Projects
Most of the general
contractors are not paying attention with explanation on interfaced scopes
between sub-contractors, selection contractors, and setting the agreement with
sub-contractors.
Based
on the contract type, contractor for projects managed by PMC -PV Gas is divided into some types such as:
1. General
contractor for Engineering, procurement and construction.
2. General
contractor for engineering and construction and sub-contractor for supplying equipments and commissioning.
3. General
contractor for construction, sub-contractor for engineering, supplying
equipments and commissioning.
Therefore, sub-contractor
management in Projects is the challenge of project management board for
on-scheduling, on-quality, safety and in budget.
If management board does
not pay attention with sub-contractor management, it will be caused the chain
of effects in delaying schedule, poor quality and cost impact for the whole
project.
One research revealed that
the cost of rework and change of sub-contractor is 12 times higher of previous
cost.
Therefore,
pre-qualification and monitoring performance of sub-contractor is the most
important in success of General Contractor and Projects.
Phan Thi Hai Giang
made a research to study the management method applied
for sub-contractor in engineering, supplying equipments and commissioning. His
study started from pre-qualification and monitoring performance of
sub-contractor.
The purpose of this study was to quantify the importance of
sub-contractor management in construction management especially in EPC contract, its effectiveness with general
contractor in schedule, quality and cost.
This research started from bidding stage, performing project
of sub-contractor in pipeline projects. The objectives of this study were to:
1. Evaluate the relationship between the subcontractor and
general contractor in scheduling management, quality control and cost control
in EPC Contract.
2)
Identify some problems in subcontractor management that can be improved by the
general contractor.
3)
Investigate the effect of implementation subcontractor management in early
stage of construction management.
With the strict management
and good coordination between Owner, general contract and sub-contractor, the
Project is completed on schedule for first gas from Nam Con Son pipeline that
is the best benefit for Owner. With on-time schedule, any Parties from General
contractor to sub-contractor/Vendor also have their own benefits from their construction
works.
The key factor of project
shall be identified in the beginning of Project and general
contractor/sub-contractor must be followed and tried to archive this goals. In
this case study, the key factor of Project was scheduled. The success of
project is good co-ordination with general contractor/Owner such as:
1. For quality management:
- All agreement between general
contractor and sub-contract will be submitted and approved by Owner
because Subcontracts should be made to conform with the prime contract
between the contractor and the project owner, and must be revised in
accordance with the changes made to the prime contract throughout the
course of the project
- Tight and clear specification
- Dedicated QA/QC Manager
- On-site Vendor Inspection
- Continuous improvement quality
management system
- Rigid control change order in design stage and in Site
2.
For the cost management:
- General Contractors prefer to
structure subcontracts so that the contractor pays the subcontractor only
if the contractor receives payment from the owner, arguing that they
should not be stuck with paying bills that the owner doesn’t pay them for.
- Accurate cost tracking, analysis
and forecast
- QA/QC to prevent and detect defects earlier
3. For schedule management:
- The good planner and updated
schedule for all Site work and procurement work that will affected with
on-time schedule of Project.
- Tight project control system and
dedicated project controller.
- Given appropriated solution for
long-lead item.
4. For safety
management:
- Good safety procedures with
appointed safety manager will be monitored all construction works at Site.
- Risk response plan, emergency response plan and risk assessment applied for safety management of Project.
Benefit of
project sub-contractor management
In
almost all projects, general contractor cannot perform their construction works
with their own force, they tried to share responsibilities and risks with their
sub-contractor/Vendor.
From
the above case-study, the good communication between general contractor and sub-contractor
had distributed to the success of Project. It can be described in the beginning
of the contract. The content of the service which sub-contractor is to provide
for the general contractor must be described; and it also articulates the
general contractor's procedure of awarding the subcontractor.
The general contractor assumes their role and
contracts out the construction work, some detail design works to various
specialty subcontractors in order to control risk and transfer construction
risks. Through sub-contracting, the general contractor can minimize its capital
investment and reduce the size of permanent staff.
The
general contractor did not understand clearly the local regulation, work permission
with existing gas facilities. So they use local sub-contractor to transfer
their risks.
With
good management of sub-contractors, the general contractors will have a successful
project in manner of quality, safety, schedule and cost. And local
sub-contractor can become more professional through tight control from general
manager.
General
Conclusion
This project is successful in the manner of subcontractor's
management. According to discussion from the previous chapter, it can be
concluded that subcontractor control management in terms of procurement and
cost from local contractor has been aligned and organized, but, in terms of
schedule, quality and safety aspects, it has been yet organized. Major
improvements are needed for the subcontractor control strategy in order to
improve the subcontractor management performance. In contrast, it can be
concluded that subcontractor control strategy has been aligned and organized in
all aspects. However, there are some major points, which need to be improved in
order to strengthen and continually improve the strategy performance.
1. Recommendation for sub-contractor
management improvement
After learning on how main
contractors managed their subcontractors together with the strength and
weaknesses of each strategy, recommendation for improvement can be reliably proposed
as follows:
i) It is important to have formal
procurement standard for subcontractors. It helps main contractors to make
decision easier and faster whether the subcontractors are qualified with the
main contractor’s commitment.
ii) Always have two-way lead times
built into subcontract agreements. Two-way means that the main contractor and
subcontractors agree on an appropriate time for the main contractor to notify
the subcontractor when to begin work and an appropriate amount of time for the
subcontractors to inform the main contractor of any conflict. Main contractor
should monitor subcontractor’s schedule by developing a system or adopting
advanced technology software that allows main contractor to track causes of
schedule variance.
iii) Top management should take a
leader role in commitment toward quality. There should be quality policy and
activities performed in an effort to implement the quality policy.
Subcontractor should understand the quality policy and follow it as a quality
standard of the work. The problems related with low quality can be prevented.
iv) By establishing a
subcontractor database, main contractors are able to know the information about
subcontractors. It helps main contractors to have better understanding
subcontractors’ performance.
v) Main contractor should develop
comprehensive project safety policy and safety programs which make provisions
for subcontractor safety. Subcontractor has to obey the main contractor’s
safety policy and follow the main contractor’s safety programs by the inclusion
of specific language to that effect in their contracts.
vi) Main contractor may consider
employing subcontract coordinator in order to improve coordination and
communication with subcontractors.
2.
Recommendation for further study
i) This research was concentrated
on main contractors’ behavior in managing subcontractor. However, there are
owner, consultant, and subcontractors whose self involving in the construction
project. Further study should be carried out to find the influence of owner,
consultant, and subcontractor itself for subcontractor management improvement.
ii) Due to time limitation, only
one international contractor was included in this study. Further study should
include more contractors in order to get better result.
iii) It is highly recommended for
further study to investigate the effectiveness of each strategy by quantitative
data.
Abstract
Because of the increased project complexity and the
highly competitive nature of the construction industry, a construction project
often is executed by several subcontractors. Hence, effectively managing the
numerous subcontractors involved in a construction project becomes a crucial
challenge for the general contractor in ensuring timely project completion with
acceptable quality.
Managing subcontractors does not simply involve asking
them to allocate resources (labor, material, and machinery/equipment) into the
jobsite whenever an activity is scheduled, and then pushing them to speed up the
work without a clear consciousness of schedule risk. Factors (or uncertainties)
such as weather, labor, site conditions, material delivery, and equipment
breakdown can influence the time performance of subcontractors, affecting total
project duration.
But almost General Contractor is lack of management
sub-contractor and it caused many difficulties and conflicts during
performance, management of projects.
The most difficulty of sub-contractor management is
deviation scope of work between sub-contractors, controlling schedule and
interfacing between subcontractors.
In managing project subcontractors, a general
contractor must determine the items of work to be subcontracted, select
subcontractors, set subcontract agreements, and control the subcontractors
during construction.
Wednesday, 20 November 2013
Matrix Structure in Small Scale & Fast Track Construction Project
Vietnam is a
developing country which needs a large amount of investment especially in
infrastructure and construction industry
from ODA and FDI. In infrastructure and construction industry, the technology
of Project Management is one of the most important factors leading to
successful projects. Most of these projects in Vietnam are under the Project Management
Unit of a state company (PMU), and PMU will be released after the project has
finished. If there is a new investment, a new PMU has to be set up which wastes
human resource, time, cost and accompanied with that is most of the large scale
projects in Vietnam now are usually late in delivery and over budget, while productivity
& effectiveness are common goals of whatever modern project management
process. The unsuccessful resource allocation of large scale projects in Vietnam
now is also a problem.
The lack of
skilled persons to meet the requirement of construction projects in an emerging
market as Vietnam is a big issue especially in small and medium companies which
proceed small scale and fast track projects. The functional organization is not
suitable for Project Management in construction because of not using & not
salvaging all capability of white collar worker. Pure project structure is also
not suitable because it has hard structure and it is unflexible in temporary
sharing human resource, and experience. So, the project matrix structure which
is more efficient using resource than other single hierarchy is a new model
which can be reviewed and considered as a suitable model for Vietnam situation
now especially in medium & small scale companies, accompanied with small
scale and fast track construction project.
Nguyen Phong made a case study which focused on the following:
1. Study
the literature of Project Matrix Structure in construction project
2. Analyze a
Case Study in application of Project Matrix Structure in Small Scale and Fast Track Project in Vietnam
Conclusion
Most of the private
businesses in Vietnam have just established around 15 years, a short of time
compare with international business, so the application of a new concept in
management is a risky selection. Project Matrix Structure was applied all over
the world but it is still a new concept in Vietnam especially in small scale
and fast track project.
The changing
from functional structure to Matrix Structure is a process of deep thinking and
careful selection which need a lot effort of all members and long time in restructure
organization. Furthermore, the discussion and analyses revealed that Matrix
Project Structure is a good choice to bring out a great successful organization
in Vietnam in which TTT Corporation is one of the most successful. From a
no-name contractor in Vietnam, TTT Corporation now becomes a well-known
contractor in small scale and fast track project specifically in fitting-out
and interior areas.
Matrix structure
is not only suitable for organization development but also in helping
organization members in self-study and self-development. Project Matrix
structure is a good model apply in fast track project in Vietnam which come out
a lot of advantages in labor force allocation, project team allocation and
major improvement of team productivity.
Recommendations
Besides the success of this model in TTT Corporation, there are many issues happened that need improvement in software
application, in system buidling and in human resource usage. Below are some recommedations:
1.
In general
i. Experience
sharing needs enforcement to become company policy, and proceed each quarter
including reward to the best
ii. Improving
existing norm, regulation and organize training course to team member update
knowledge on sharing is not fair
iii. Develop
individual assessment form for functional manager, project manager and proceeds
the assessment immediately after project hand over.
iv. Training to
increase perceive communication management
v. Report overview
is a part of project bonus to encourage PM, have right evaluation sent to
supervisor, not popular to project team
vi. The
increasing of internal project information is a problem. The way end user
transfer & discussion the information on CRM need to be reviewed and be
classified suitable with business strategy not a forum.
2. Human
resource
i. Minimize the amount of virtual project
manager and increase the number of professional project manager to take care
bigger projects.
ii. Support
project manager to have more training course on approach with new technology
and new concept in project management.
iii. Training of
project manager on technical knowledge related with project because small scale
and fast track project need by the project manager to understand not only in
project management but also all technical issues of project. This understanding
helps project manager in making decision in short time.
iv. Training
about communication management, which help project manager and each member
understand the importance of communication and classify it in a right way which
support to long term goals of organization.
3. System
1. CRM is a soft
ware for customer relationship management, not suitable for project management
although it is a very good support for project management process: it supports
for centralize project information, clients information, integrating with other
soft ware (ERP, Share Point…) helping board of director in controlling,
monitoring and reviewing most projects but only the project milestone and not
the general progress of the project. So Central Project is a recommendation for
developing and application in some next years.
2. ERP is a soft
ware suitable for manufacturing and not for design & built project, so the
application is just for production department or apply ERP software for
construction area and ERP department should be a department to manage and
control ERP and support to others.
Project Matrix Structures are applied in
large scale projects & long term projects in many western countries and
comes with many successes. How it can apply for small scale & fast track
projects in developing countries as VN?
There has been a tendency in recent
years to manage more activities in more application areas using project
management. More organizations are using “management by project.” This is not
to say that all operations can or should be organized into projects but the
real efficient of the management by project can be the good answer.
This Project Report has taken a general
view of Project Matrix Structure in theory & application in developed
countries then finding out the case study that applied in VN with a relative
successful to propose some recommendations to improve & change in suitable
with practical condition of VN.
Office Fitting-out has started in VN
around 15 years from the time VN did the “Open Policy” to open the country and
to set up relations with other countries & receiving FDI and ODA. By FDI
and ODA from developed countries and International Institutes – Office
Fitting-out works are developed very fast in VN with high requirements in doing
the fast-track project including high quality of finishing, keeping reasonable
cost & schedule.
The adoption of “management by project”
is also related to the adoption of an organizational culture that is close to
the project management culture but this is outside of this report.
Tuesday, 19 November 2013
Quality Management in Construction Projects
Construction
activities involve quality management systems, but in
practice there are a lot of poor works that worries the owner because it usually
resulting to waste of money and also cause danger to people.
To ensure the effective application of quality management
for construction projects, it requires the strong commitment of business
leaders and implementation of multiple solutions. Apply effective quality
management that will bring many potential benefits for businesses. Le Van Thong made a case study which
objectives were summarized such as follows:
1. Determination of quality management
activities in the construction in the Oil and Gas Company
2. To discuss and review the
effectiveness of quality management in construction of the Oil and Gas Company
Conclusions
Quality management system has been
applied by PTSC companies in their projects. It brings success to the company
for many years now, and became a famous company in the international market in
oil and gas technical services industry in Vietnam. They are the useful tools
to avoid and mitigate problems and to improve quality performances of their projects.
They are the principles that management use to achieve effective cost control,
quality control, schedule control etc. Many civil and industry construction
Corporations, companies in developed countries have been applied the successful
Quality Management and got more profits and reduced lost time, and cost for
reworks. They recognize the importance of the Quality Management and have
responsibilities to identify, assess, prevent and manage all breakdowns and
risks to projects, damage to property and working environment.
The quality improvement programs
establish actions for achieving the objectives and targets, in line with the
policy commitment of continuous improvement. When establishing targets, the
following will be taken into consideration:
1. Who do? How? Who supervise the
provision of information; as executive / coordination / control is assigned in
advance and all agents involved must comply.
2. The system clearly and closely
flexibility have created a positive consequence of works completed on schedule,
ensure quality and safety.
Effectiveness of the implementation quality
management
After implementation
of the quality management, there are some achieved results such as
below:
1. Quality
Assurance is to obtain completed construction that meets all contract
requirements. Assurance is defined as a degree of certainty. Quality assurance
personnel continually assure that the contractor's works comply with contract
requirements.
2. Quality
Control is the successful execution of a realistic plan to ensure that the
required standards of quality construction will be met. In QC, the contractor
defines procedures to manage and control his own, designer of record,
consultant, architect-engineer, all subcontractor and all supplier activities
so that the completed project complies with contract requirements. For design-build contracts this includes
providing and maintaining a Design Quality Control plan as a part of the
overall contract QC plan. This plan, as
a minimum, must assure that all documents are reviewed by a technically
competent, independent reviewer specifically named in the plan. This review cannot be performed by the same
designers that produced the product. The
design QC plan must be managed by a Design QC Manager who has verifiable
engineering or architectural design experience or is a registered engineer or
architect. The Design QC Manager is
under the supervision of the QC Manager.
Recommendations
1. The
performance of Quality Management must be carried out permanently in the
company to prevent all budget overrun, progress slow, reworks maybe happening
from the existing projects and future projects.
2. The
performance of Quality Management must be concerned from the top management to
everybody in the company.
3. Examine
the quality control methods being used to determine if the contractor is
properly controlling design activities in design-build contracts.
4. Examine
the quality control methods being used to determine if the contractor is
properly controlling construction activities.
5. Make
certain that the necessary changes are made in the contractor's QC system, if
excessive construction deficiencies occur.
6. Assist the
contractor in understanding and implementing the contract requirements.
7. Examine
ongoing and completed work.
8. Produce
the quality specified in the plans and specifications and for design-build
contracts in the Request for Proposal, as well as the contractor's accepted
proposal.
9. Develop
and maintain an effective QC system.
10. Perform
all control activities and tests.
11. Prepare
acceptable documentation of QC activities.
In an organization or business will have a lot of
construction projects, any project also is importance. Ensure the quality of the
project is very important for each organization. Aware of that, the quality
management has been applied widely in their construction projects. But how
apply the successful model of quality management for a construction project
that is still a big question.
Organizations
in Vietnam as some other countries, in face, the signers disclaim the
possibility of anticipating and detailing everything in the construction
documents. Second, it is unstable for the construction environment. The
complexity and size of project vary. Working conditions cannot be somewhat
control. The employee is variable; its composition, motivation and size change.
Cooperation between contractor and subcontractors is problematic. Those will
affect the quality management of construction projects and it makes the project
to delay, re-work and increase cost.
So, how to
manage the quality of the construction project effectively? This thesis will
research about quality management in construction project through theory and
real case that is applied in PTSC Production Services Company.
Friday, 15 November 2013
Seminar in Can Tho: Managing Megaprojects in Developing Countries
Seminar
MANAGING MEGAPROJECTS IN DEVELOPING COUNTRIES
Prof. Christian Brockman, University of Applied Science, Bremen, Germany
14 Nov 2013
AITVN, Can Tho city, Vietnam
MANAGING MEGAPROJECTS IN DEVELOPING COUNTRIES
Prof. Christian Brockman, University of Applied Science, Bremen, Germany
14 Nov 2013
AITVN, Can Tho city, Vietnam
On 14 Nov 2013 at AITVN Can Tho city, Vietnam, the Professional Master
program in Project Management in Construction (MPM) organized the
seminar MANAGING MEGAPROJECTS IN DEVELOPING COUNTRIES, presented by
Prof. Christian Brockman. Similar to Ho Chi Minh city, the seminar received the interest of many participants come from construction companies and organizations within and outside Can Tho city.
Once again, we
would like to send the thankfulness to Prof. Brockman for his sharing to our participants in Mekong Delta provinces and all participants for your coming and contribution to
the success of our seminar.
Subscribe to:
Posts (Atom)