Engineering, Procurement, Construction, Pre-commissioning,
Commissioning for the well, wellhead platforms, offshore facilities are
considered to be very risky because of their complications and large money
required, therefore we need good contract management to check whether the
obligations, rights, specification, performance, commitment and so on are met
properly and to optimize contract performance, eliminate risk involved in EPC
contract throughout the lifecycle.
Not having a good contract management process in place has
consequences both to the Client and the Contractor as well as to Consultant
Company, Vendor, and Sub-contractor (if applicable). If the Contract Management
is not managed, controlled, monitored, and implemented properly, the parties
are likely to fail to meet its goals that they had for the project associated
with the contract. Such failures may include delayed schedule, cost overruns,
quality, safety and more. 
EPC
contracts have been used in both medium and complicated large scale oil and gas
projects in Vietnam since 1990s. Phan
Tuong Liem made a research by studying
EPC Contract Management of his own project (Rang Dong Full Field Development
Project Block 15.2 Offshore Vietnam). The objectives of his study were to:
1. study
implementation of JVPC EPC contract management.
2. state problems that occurred in the execution of
EPC project.
3. give out some recommendations to EPC contracts.
4. learn lessons from JVPC
project.
Conclusion
In order to have a successful project, contract management played
an important role. During the administration of a project, any major or minor
activities involved a sequence of activities that were covered by different
Clauses and Sub-clauses in the Contract. 
However, in reality not all Clauses/Sub-clauses covered all activities
without unchanged, unrevised. Because of modification and design change which
were not fully mentioned in the Contract, as well as cost of extra work and so
on. 
The contract usually had at least three copies to be distributed:
original copy for The Client, Contractor and filed Field Contract Manager to
follow.
Contractor knew how to allocate manpower, material, and
equipment to meet the project target. Any personnel involve in the project
especially key personnel had their profiles to show that they were qualified,
competent and approved by the Client.
Abstract
Contract Management is the process that enables both parties
to a contract to meet their rights, duties, obligations and responsibilities
(i.e. allocate the risks) in order to deliver the objectives, services,
required from the contract.
It also involves building a good working relationship
between the customer and provider in general, and between Owner and Main
Contractor or Main Contractor and Subcontractor so on. It continues throughout
the life of a contract and involves managing proactively to anticipate future
needs as well as reacting to situations that arise.
The main purpose of contract management is to obtain the
services, performance, commitments as agreed in the contract between the Client
and the Contractor. This means optimizing the efficiency, effectiveness and
economy of the service, the performance, or relationship described in the contract,
balancing costs against risks and actively managing the Clients/Owners and the
Contractors relationship. Contract management may also aim for continuous
improvement in performance over the life of the contract. 
 
2 comments:
Enhancing contractors and suppliers' performances as well as following all of the specified terms and conditions in the contract is guaranteed done in completing projects through contract management. Having someone to follow up and review on anything pertaining to design is possible with contract management experts.
contract management process
Thank you for this extremely brilliant blog! We really appreciate your blog post. There are actually a multitude of techniques we could put in to make really a good use of information without much efforts and financial resources.
Post a Comment