Monday, 30 November 2009

Heavy equipment management practices and problems in Thai highway contractors

Thanapun Prasertrungruang and B.H.W. Hadikusumo


Introduction

Highway construction business is a sector that relies primarily on high utilisation of machinery. Equipment is thus one of the key factors for improving contractor’s capability in performing their work more effectively and efficiently (Day and Benjamin, 1991). By utilising machinery, an extensive volume of work can be completed in a shorter period of time and within the project schedule. However, in managing construction equipment, contractors are invariably plagued with several difficulties such as huge capital investment in the acquisition phase, which usually constitutes a major financial burden. Procurement of major construction equipment not only costs as high as 36 per cent of the total construction project cost, but also causes a high delivery time uncertainty, which may disrupt the construction schedule (Yeo and Ning, 2006). In the operational phase, contractors are often faced with problems relating to high rate of equipment breakdown and accident resulting from unskilled operator abuse (Stewart, 2000; Edwards and Holt, 2002; Edwards and Nicholas, 2002). Poor training of equipment operators is often claimed as a major cause of equipment-related accidents (Gann and Senkar, 1998). In the maintenance phase, proper maintenance management of construction equipment is never over-emphasised since the cost and time that exceed the designated budget or schedule on projects are often resulted from poor machine maintenance practices. However, over-maintenance of equipment is undesirable as well (Vorster and De La Garza, 1990; Edwards et al., 1997). In the disposal phase, determining equipment economic life and timing for replacement is often problematic because such decision is influenced by various factors such as machine obsolescence and efficiency (Vorster, 2005).

Effective equipment management practices not only increase production time and equipment availability, but also maximise the company profit by reducing several costs such as those from costly downtime (Edwards et al., 1998a). However, researches in the field of equipment management practice, particularly in the construction context, have been rare (Edwards et al., 1998b). This research was conducted in order to investigate current practices and problems on equipment management as well as to identify practices that are capable of mitigating equipment management problems from Thai highway contractor’s perspectives. Since machine weight is one of the major indicators of equipment downtime and maintenance cost (Edwards et al., 2000a, b; Edwards et al., 2002), only five types of heavy construction equipment were selected in this study (refer to Table I). It is believed that a study on heavy equipment management practices would contribute great benefits for highway contractors in helping them manage heavy equipment successfully.

Contractor heavy equipment management practices
In this research, contractor heavy equipment practices have been categorised into four significant stages based on machine lifecycle, i.e. acquisition, operations, maintenance and disposal.

Equipment acquisition practice (EAP)

It is generally accepted that smart acquisition practices fuel company success. Contractors always have vested interest in ensuring that their invested equipment are properly used, maintained and managed (Mitchell, 1998). In practice, capital conservation is a major factor for most companies in deciding to buy, lease, or rent on an installment plan (Sutton, 2003). Most companies, regardless of size, tend to prefer a purchasing strategy than other alternatives (Stewart, 2002a). To fulfill short-term equipment demand, most contractors realise the importance of rental machine utilisation (Stewart, 2002b). In the case of high workload during a peak construction cycle, leasing approach, which may come as a package with maintenance services from dealers, may be deemed appropriate (Stewart, 2002c).

Equipment operational practice (EOP)

An equipment operator is the person in the construction organisation who has the most influence on equipment costs (Stewart, 2001). Quality output can be partly achieved through skilful operators working with machines that are in good operational condition, thus educating equipment operators is one of the most important policies and thus holds great cost-saving potential (Wireman, 1999). Better channels of training can be obtained from various sources such as dealers (Stewart, 1998) and external agencies (Edwards and Holt, 2002). Systematic record-keeping is another practice that can generate valuable management guidelines, particularly in equipment planning and maintenance strategy (Marquez and Herguedas, 2004). Contractors must continually evaluate machine records in order to determine what actions are needed.

Equipment maintenance practice (EMP)

Maintenance of equipment is essential to contractor’s profitability because it not only extends the useful life of the equipment but also controls the machine availability at a minimum cost. Nevertheless, equipment maintenance is the most neglected aspect. Successful maintenance management can be achieved through well-developed maintenance programs (Tavakoli et al., 1990; Shenoy and Bhadury, 1998). Maintenance programs can be classified into several forms based on their complexity such as corrective maintenance, preventive maintenance and predictive maintenance (Gopalakrishnan and Banerji, 1991). Maintenance should not be viewed as a cost, but as an investment that can be linked to the company’s future revenue growth (Sutton, 2001).

Equipment disposal practice (EDP)

The last stage of machine lifecycle is disposal stage, in which two major decisions concerning equipment have to be made, i.e. timing of replacement and equipment economic life expectancy (Douglas, 1975). There are various factors affecting the timing of replacement: machine efficiency, capital availability, investment costs, commencement of new projects, profits accrued from use, tax expense, depreciation, economic analysis, obsolescence costs, and downtime cost (Hinze and Ashton, 1979; Schexnayder and Hancher, 1981; Tavakoli et al., 1989).

Research method

Data collection
This research involves a questionnaire survey by mail to collect the necessary data on equipment management practices and problems of highway contractors in Thailand. According to the Department of Highways (DOHs) of Thailand, highway contractors can be categorised into five classes (i.e. extra first, first, second, third, and forth classes) based on construction experience and company resources (i.e. equipment, finance and workforce). For the sake of data analysis, it was decided to reclassify contractors into three groups (i.e. large, medium and small). Large contractor group represents the companies registered in the extra first class, medium contractor group includes those registered in the first and second classes and small contractor group comprises of companies registered in the third and forth classes.

At the first stage of the questionnaire development, a pilot test, using a semi-structured questionnaire, was conducted to test for the applicability of the tool. The selected samples for the pilot test comprise of equipment managers from ten different companies (i.e. four large, three medium, and three small contractors). Once the pilot test was completed, a valid questionnaire was then prepared and data collection was started. The questionnaire has been divided into three parts. The first part is an introductory section that includes questions related to the respondents and their company profile. In the second part, the respondents were asked to give a score on the frequency level for each of the 73 variables concerning equipment management practices (see Table I). Responses are on a four-point scale (never = 0, seldom = 1, often = 2 and always = 3). In the third part, the respondents were asked to specify the impact/significant level for each of the 20 equipment management problems that actually affect their companies on a five-point scale (not significant = 0, somewhat significant = 1, moderate significant = 2, significant = 3 and very significant = 4). Questionnaires were mailed to the respondents on a basis of random stratified sampling technique.

Conclusion

To some extent, heavy equipment management practices vary considerably among different highway contractor sizes. Large firm’s practices tend to be much different from those of the smaller firms, whereas medium and small contractors’ practices are more likely to be similar. Large contractor’s practices tend to be more successful in minimising equipment management problems. In order to diminish equipment problems, particularly downtime, the importance of performing preventive maintenance should be strictly emphasised. Adoption of professional services (e.g. maintenance and training) from external agencies such as dealers is also recommended if such tasks are not the company’s core competency. Moreover, equipment should be disposed of or replaced once it becomes inefficient or generates less productivity with high repair cost.

The foregoing practices could be considered effective because it significantly reduces major equipment management problems. Therefore, adaptation and implementation of such practices by contractors are strongly suggested. Nevertheless, this research focuses only on equipment management practices and problems of several types of large heavy machines for highway construction. Practices and problems relating to small machines or even equipment utilised in other industries are probably different from this study and thus could be the area for future research.
This paper was published in the journal “Engineering, Construction and Architectural Management Vol. 14 No. 3, 2007 pp. 228-241”. Full article is available upon request. Abstract is also posted.

Abstract

Purpose – This study is intended to investigate the current practices and problems in heavy equipment management as well as to identify practices capable of alleviating equipment management problems for highway contractors in Thailand.
Design/methodology/approach – Equipment management practices were identified and analysed by SPSS using a questionnaire survey. ANOVA test was used to reveal significant differences in equipment management practices among different contractor sizes. Relationships between equipment management practices and problems were also revealed.
Findings – The equipment management practices vary, to some extent, among different contractor sizes. While practices of medium and small contractors tend to be similar, practices of large contractors are different from those of smaller contractors. Large contractors often put more emphasis on outsourcing strategy for equipment management. Moreover, large contractors frequently dispose of or replace equipment as soon as the equipment becomes inefficient before incurring high repair costs. Conversely, smaller contractors tend to mainly emphasis on the company finance and the budget availability as they often rely on purchasing strategy, especially buying used machines. Overall, equipment practices of large contractors were found to be more successful than smaller contractors in minimising equipment management problems, including long downtime duration and cost.
Originality/value – This research is of value for better understanding practices and problems relating to heavy equipment management among different contractor sizes. The study also highlights practices that are capable of reducing problems relating to heavy equipment management for highway contractors.
Keywords Construction equipment, Construction industry, Thailand
Paper type Research paper

166 comments:

HEMM 4 Share said...

Good Article.. whenever U buy an heavy equipment = U get the equipment management responsibility to handled.

kevin said...

The machineries and equipments are the hearts of any of the industrial and innovative revolution. Here is the site that provide all type of New as well as Heavy Construction Equipment
the site has all other type of machinery

Resume Writing Service said...

Thanks for posting such useful items. I’ve been reading his blog with much interest. He’s certainly raised my awareness. This post is Well Organized and Informative.

Anonymous said...

Very nice information post by this blog owner I want to say thanks for it. I would be like to come again and again on this blog. Good job dear ! survey total station

Anonymous said...

Hmm that looks really very good, thanks for sharing such a nice and useful information...you have got a very nice blog ,i am having some new and used bobcat for sale check them out.

Skelton Sherborne said...

This blog is a great help to all of us.

Market Analysis said...

Your post really informative as well as helpful for my Construction Machinery Market Research and Development.

goraya said...

Equipment service management and rental (ESM&R) refers to equipment services management throughout the heavy equipment life cycle. Increased competition and slim margins in heavy equipment sales and rental place a heavy burden on manufacturers,
dealers, rental companies and service businesses to improve their service performance. Improving service in these conditions is critical to maintaining margins and growing profitability.Plantlocator is the home of new and used plant and machinery for sale.Read More

Unknown said...

thanks for the information of heavy equipment maintenance management...keep up the good work..

hemcoined said...

Great post. I found an effective article that carries all information regarding heavy equipments.

thanks!!
Loading Arm

Unknown said...

Thanks for the information regarding heavy machinery products. For the reason that a purchase can be minimal and there is no require for the large monthly tools costs every time one thing should go whether positive or negative using the business. doosan colombia

excavator for sale said...

Thanks a lot for enjoying this beauty article with me. I am apreciating it very much! Looking forward to another great article. Good luck to the author! All the best

Unknown said...

Equipment leasing is effectively

a lon which the lender buys and owns equipment and then "rents" it to a business at a

flat monthly rate. At the end of the lease, the business may purchase the equipment for

a fixed predetermined figure (or fair market value) or return it

Hydraulic Cranes Suppliers in Pune said...

This article gives the light in which we can observe the reality. This is a very nice one and gives indepth information. Thanks for this nice article.

Earthmoving Maintenance said...

A great post. Thank you for sharing.

We are a mobile field provider, supplying Earthmoving Mobile Maintenances, Repairing , Machine Servicing, Track Inspection, Bucket Inspection, and Machine Inspection
For more information on Earthmoving Maintenance go to http://www.earthmovingmaintenance.co.za/

Anonymous said...

This site is good because they give us a new thing and new ideas and new topic about Heavy equipment management practices and problems in Thai highway contractors. We should appreciate them because of these good thing. I know something information, to know you can Search Here

Scaffolding In Chennai said...

I like your post. My company is Aluminium Scaffolding Manufacturing Company. Share More Scaffolding related post its most useful to me. I like to share your blog to my friends.

Unknown said...

I think this is a good site, mostly for people like me who haven't heard much about leasing equipment. It's good to be able to come here and to be able to see and learn about what it is and what they can do for people. I can't wait to find out more about it. http://www.westarfin.com/en/heavy_equipment.html

Unknown said...

There are a few places around my cite where you can buy heavy equipment, and I have heard a lot of people comment on the different management styles. Some people I know won't even go to certain stores because of the way they're run. It goes to show that it's very important the kind of management you have.

Sara Welsh | http://www.rotatingservices.org/about

James Abram said...

I think the solution to this problem is simple. Find a reliable source of heavy equipment and trucks for sale Philippines.

Unknown said...

To work equipments long lasting especially heavy machines, it always necessary to keep them service. For this a proper SOP must be developed to manage and handle construction machines effectively and efficiently. Or UK plant hire companies guidance must be adapted to avoid unforeseen hazards and for good project management.

harry singh said...

Nice blog post about Construction machinery equipment. This is very informative post for me to know more about construction machinery. Thanks for sharing this informative post.

Unknown said...

I definitely find this article interesting. There are a lot of ways to be able to stay safe when it comes to heavy equipment. When I worked construction I know that there was a large management crew to make sure everyone was doing their job. I really like that about construction. http://sonsraymachinery.com/used-equipment.html

Unknown said...

I was recently laid off and need a new job soon. It would be nice to get my heavy equipment certifications, to help me be a bigger asset to myself. Are there standardized tests that I can take as part of the knowledge process? Hopefully, taking the certification tests will show companies that I am qualified to help them.
http://www.alltranstraining.com.au

Rudy said...

get the tips for heavy epuipment :)

Unknown said...

Highway construction is really a big investment but looking into the brighter side the output of this business will surely have a good ROI.

Construction Equipment Singapore

Earth moving equipments said...

The stuff written on the construction equipment have allured me.

Construction Equipment Manufacturers said...

Very amazing, Good Job, Thank you for presenting a wide variety of information.

Unknown said...

Very good blog. If you want to avail heavy equipment shipping services please contact us from the links below


The Over Sized Equipment Shipping company is undoubtedly the best thing which is necessary in the market in present time. There are many businesses that are taking the opportunity to shift goods and heavy vehicles from one location to another. The reliable rv transport company is all spreading in new areas as the demand and popularity is high.

Unknown said...

wow..Good explanation of your blog..!
Online Business Search Engine

Jobs said...


Hi Your post is really very Interesting about Hire Candidates .You can Find same type of the Online Job Portal to Hire Machine Operator ..... on Theincircle.com

Car Review said...

simple blog but inspired content

historypak said...

This is such a great resource that you are providing and you give it away for free. I love seeing blog that understand the value of providing a quality resource for free. Forklift Rental

Anonymous said...

I was reading your article and wondered if you had considered creating an ebook on this subject. Your writing would sell it fast. You have a lot of writing talent. Equipment Rental Emmett

Mutterfly said...

Nice Post., Mutterfly Providing the best equipment rental Service in Mumbai...

Waste Equipments said...

Solid Waste Management Equipments Supplier and Manufacturer in Noida, Delhi, Ghaziabad, India

Unknown said...

Aar aar enterprises is the one of them are manufacturer and provider aluminum extrusion industry in India has flourished for a long time product aluminium extrusion suppliers
http://www.aaraarenterprises.in

Unknown said...

I read your blog posts in the last hour. I really enjoy what you are doing here.Thank you for helping people get the information about heavy machines CNC machining center they need Keep up the great work!!!

safety professionals said...

We are providing on Nebosh certified training…

industrial safety course in Chennai
fire and safety course in Chennai
industrial safety courses in Chennai
fire and safety courses in chennai
industrial safety in Chennai
fire course

Anonymous said...
This comment has been removed by the author.
Anonymous said...


Very interesting read. Check out heavy equipment and Hitachi excavators for sale at Mico Equipment.

autolinkint said...

This is really an important blog with many helpful information. I have been searching for a long time for this types of content. Keep up posting more and thanks for your great staff.
Heavy machinery buy Dubai

Autolinkqatar said...

Thanks for taking time for sharing this article, it was excellent and very informative. Its really very useful of all of users. I found a lot of informative stuff in your article. Keep it up.
Heavy Machinery For Rent

Visrom Excavators said...

Excellent Blog post.
We are very thankful for your amazing and helpful services related to Construction Equipment.
This gives so much help to us.
Construction Equipment hire rates kenya

safety limited said...

safety courses in Chennai
safety course in Chennai
safety institute in Chennai.
safety academy chennai
safety training institute in chennai
Diploma in safety course in Chennai
safety course-safety professionals

Anonymous said...

Its a great thing if there is a rent to own option for you as it is more affordable and this is good if youre looking after to work long term with your future projects.
Heavy equipment rental Pakistan

Unknown said...

Als trailers is the best Highway trailer dealers in new & used RV Sales in Oregon along with finance option. We have all the brands of RV parts and Accessories.

Unknown said...

Impressive and powerful suggestion by the author of this blog are really helpful to reduce our hack-tic life. My own views are matching with author and I have experienced such.
เห็ด หลิน จื อ แดง ราคา

Anonymous said...

Good post. This is a very clear, informative and helpful post. Thanks for sharing. Will come to visit again.Click here to find more information....
Heavy machinery sale Pakistan

Unknown said...

best safety course in chennai
safety training institute in chennai
safety academy chennai
safety course-safety professionals

Unknown said...

best safety course in chennai
safety training institute in chennai
safety academy chennai
safety course-safety professionals

Unknown said...

Nice article with wonderful heavy machines,
I like this work. I used a website service for heavy construction equipment work, if you need so visit this
John Deere Excavator

Dozex Earthmovers said...

Hey thanks for writing such a nice blog on hydraulic Earth movers. Great work!

Dozex Earthmovers

babajagatshuttering said...

Great and informative post that briefs about constructions in details. I enjoys a lot this informative post. We also deals with the same niche as of your and provide world class scaffolding rentals services in India at reasonable price. Thanks for sharing this informative post.

JamesLynch said...

I really like what you guys tend to be up too. Such clever work and reporting! Keep up the great works guys I've you guys to blogroll. Heavy equipment repairs Miami

HBXG Bulldozer said...

Hi thanks for writing a nice blog on hydraulic earth moving machinery. Great work

http://www.bulldozer.co/

HBXG Bulldozer said...
This comment has been removed by the author.
HBXG Bulldozer said...

new bulldozer

Dozex Earthmovers said...

Amazing Post with wonderful heavy machines, i like this work. i used a website service for heavy construction equipment work, if you need so visit this -

Takeuchi Mini Excavator , http://dozexearthmovers.blogspot.in/

HowardGrace said...

I am curious to find out what blog platform you're using? I'm having some small security problems with my latest website and I'd like to find something more safeguarded. Do you have any recommendations? Heavy Equipment Rental Miami

Derrick Corea said...

Very nice blog. good to read this.
agricultural equipment design services

Unknown said...

I am very enjoyed with this blog. Its an insightful topic. It help me very much to fix some problems. Its opportunity are so fantastic and working style so speedy.Heavy Equipment Rental Miami

Autolinkqatar said...

Thank you for this wonderful article really…helpful…
click here

Unknown said...

iosh course in chennai
lead auditor course in india
courses offered
alagi blog
safety course in cochin
nebosh igc course cochin

sunshineprofe said...

And indeed, I’m just always astounded concerning the remarkable things served by you. Some four facts on this page are undeniably the most effective I’ve had.
safety course in chennai

gowthunan said...

Your very own commitment to getting the message throughout came to be rather powerful and have consistently enabled employees just like me to arrive at their desired goals.
nebosh course in chennai

fire and safety course in chennai

swissoffer said...

Are you looking for heavy equipment inspectionin construction and construction vehicles for sale? Call us today at International: +356 27781650, United States +1 3648886788.

Anonymous said...

One of the helpful blog on heavy equipment management on the highways. These practices are helpful for highway contractors.

ankit said...

Nice Post. It's really useful information. Whenever you buy Scaffolding & Shuttering in Noida Contact us -+91-8800813050

safety professionals said...


best safety course in chennai

best safety institute in chennai

best safety training institute in chennai

best safety training in chennai

safety course in chennai

safety courses in Chennai

safety training in chennai

safety institute in chennai

karthick said...

The blog information that you have posted is really nice. Thanks for sharing the blog with good information. Keep updating more.
Interior Designers in Chennai
Interior Decorators in Chennai
Best Interior Designers in Chennai
Home Interior designers in Chennai
Modular Kitchen in Chennai

stephen said...

Thanks for sharing. Great post very Informative, also checkout Quality Concre-Mix, Inc

Rahul Singh said...

Thanks to share these lines. Useful!
The major drivers for the Construction Equipment Rental market include the increasing demand for rental equipment due to various benefits, shift in trend towards rental, increasing infrastructure activities in emerging nations, and cost-benefits associated with the use of construction equipment on a rental basis rather than purchasing it.

James E. Perez said...

This blog was really useful and i got a lot of information about heavy equipment from this blog. Please keep writing about heavy equipment. Click here for further information regarding Caterpillar Heavy Equipment Service Manual

Mark Smith said...

Nice piece of information. heavy equipment rental

Winnipeg said...

We provides a best scaffold to all industries with the wide range of sizes from industrial building, towers to large scale applications.
chute for rent in thunderbay
Scaffolding contractor thompson

JackJohnson said...

forklift

Forklift Rental - We offer excellent forklifts Rent services in Singapore. Get the best forklift for sales and rental in Singapore at affordable price. Contact us now - +65 6519 6905

to get more - http://angequipment.com.sg/product/fork-lift/

Safety Nets Manufacturers said...

Thank you for posting this excellent information..it is very useful to me..! Click here.

Nemaram Punavat said...

Restaurant equipment financing company USA

How much does restaurant equipment cost? Best Restaurant equipment financing company in the US offering low interest rates on loans. Call: 201-960-8889

to get more - http://readyfinance.us/equipment-financing/restaurant-equipment-financing/

Capitalize Loans said...

Thanks for sharing your blog. It was very interesting. CAPITALIZE Loans provides equipment financing company in miami with easy procedures. Apply for business loans in Miami through our online application in under 3 minutes.

seosignup said...

It was very informative blog ! Thanks for sharing with us !

Rotta Print India Private limited
Web offset machine manufacturers
Web offset printing machine supplier
Web offset printing machine manufacturers
Web offset printing machine
Web offset printing press
Web offset Printing Machines India
Offset Printing Machine Manufacturer
Book printing machine
Book Printing Machines India
Four color non-woven Bag Printing Machine Manufacturer
Mini Offset printing machine supplier
Mini Offset printing machine manufacturer
Non-woven bag printing machine manufacturer
Multi-color non-woven bag printing machine
Two color non-woven Bag Printing Machine
Newspaper printing machines manufacturers
Newspaper printing machines
Newspaper Printing Machines India
Printing Machine for Newspaper
Non-woven bag making machine manufacturer
Non-woven bag making machine
Non-woven bag printing machine supplier
Rotta speed web offset
4 hi tower
Web offset
4 Hi Printing Machine Manufacturers
4 hi tower machine
4 Hi Printing Machines

Joseph Ruiz said...

Nice blog post about Equipment Rentals. This is very informative post for me to know more about Equipment. Thanks for sharing this informative post.

Babit said...

The post is written in very a good manner and it entails much useful information for me.
Heavy Equipment Packing

Stony Brook said...

This is very useful information for those people who are looking for Contractors and Construction Equipment.

Etisalat Yellowpages said...

Thanks for sharing this. It has a lot of information about heavy equipment rental OR construction equipment but if you want more details so please visit my blog.

sabir2434 said...

Amazing blog on this topic. It has a lot of information about construction equipment but if you want more details so please visit my blog.

zaara khan said...

Great blog on this topic, It has a lot of information about heavy equipment rental OR construction equipment but if you want more details so please visit my blog.

Techno said...

Amazing blog on this topic, Thanks for sharing this with us. It has a lot of information about heavy equipment rental OR earthmoving equipment but if you want more details so please visit my blog

Safety Equipment Direct said...

Nice Blog, Safety Equipment Direct provides top quality personal protective equipment and industrial products online at deep discount pricing. Our safety supplies include High Visibility Garments, Hearing Protection, Safety Glasses, Hard Hats, Hard Hat, Gloves, Winter Warming Products, Summer Cooling Products, Safety Mirrors and more. Safety Equipment Direct earns your trust by offering only the best value, top quality industrial safety product, and construction safety supplies with top-notch service before, during and after your purchases.

MajidAli01 said...

Yes, this is a good post without any doubt. You really do a great job. I am inspired by you, so keep it up!
Interior Design Equipment and Supplies | Interior Decoration Material Suppliers | Interior Designer Tools and Equipment

rustamkhan said...

cert equipment Singapore

United Resources - Get the best cert and respiratory protection equipment in Singapore, We offer the best cert equipment and respiratory protection equipment online at affordable prices.

to get more - https://unitedresources-intl.com/

jadafire said...

nice post..Fire Extinguisher In OMR
CO2 Fire Extinguisher

Unknown said...

If anyone wants free trading tips and I am so happy about your blog yor blog is amazing and greatfull Thank you for giving convenient information Pleas click here :-
Heavy Equipment Packing

max said...


ethereal precision to bring you the foremost professional results with each and each cut. However, because the Kapex is an unconscionably brilliant machine , it also tends to be the foremost . it's important to recollect , though, that within the business of power tools, you usually get what you buy .
contractors Mobile AL

prafton finance said...

Great !! I am glad to read this article. Thanks for taking time to tell us more about Heavy euipment leasing !

prafton finance said...

Great blog on this topic, It has a lot of information about HEAVY EQUIPMENT LEASING but if you want more details so please visit my blog-HEAVY EQUIPMENT LEASING

TC Consultancy said...

TC Consultancy providing Best Service in Construction Management Solutions in UAE & Saudi arabia. for more information you can contact our website +971 6 557 3924
Construction Management Solutions

MindCypress said...

The need for a qualified Project Management Professional is at the rise, turning it into one of the most desired professions. Take the plunge towards industry standards, it’s not going to be easy but MindCypress is here for help.

Proall Refurbish said...
This comment has been removed by the author.
ProAll Equipment Refurbishing said...

An effective blog that carries all information regarding heavy equipment.Your blog entries are seriously interesting.
heavy equipment repair services

prafton finance said...

Thanks for sharing such an amazing and informative blogs.This is very helpful for me.More about details:
Equipment Repair Loan

tigerkingkhan0786 said...

We provide road construction & earth moving equipments in India. Active Hire is an excellent option. Contact us today at renthire.in

Visit here:- hire earth moving equipment India

Renta machinery said...

construction machinery rental in pakistan at best Prices.every Project can not be completed with out the heavy machinery so i think renting is a betterb option then buying

Dayim Equipment Rental said...

Nice blog. Dayim equipment rental Company offers specialized and modern forklifts for rental services. We have a wide scope of electrical and mechanical equipment to meet our customer's requirement. Visit here - Forklift Rental

EZ Equipment Rental said...

Hi there, just wanted to tell you, I enjoyed this article. It was helpful. Keep on posting!

bsnssexpert said...

Small Construction Equipment, Construction Machinery On Rent India

Renthire.in offers small construction equipment and machinery products of excellent quality and very competitive rent prices. For all your equipment needs call us: +91-7033591595.

Visit here:- construction machinery on rent India

Universal Machines said...

Get a highly durable and power saving chicken cutting machine from the leading chicken cutting machine manufacturers in Coimbatore.

Armstrong said...

Nice content
Automated Guided Vehicle systems
Automatic Guided Vehicle systems
Automated Guided Vehicle
Warehouse Management System
Industrial Automation Companies in Pune
Stretch Wrapping Machine
Industrial Racking

Lucifer Smith said...

used excavator supplier

Jia Xin said...

Thank You Very Much For Great Post At Sparkling, we're Heavy Machine Moving Companies with decades of experience, and we serve as Heavy Machine Moving to a variety of industries Heavy Machine Moving offer trusted end-to-end moving services with reliable in-house tools and expertise you can trust.

Renta machinery said...

where can I buy construction machine in pakistan at best cost.I am a little lost on it.

crisantoandrada said...

Thank you so much for this article really this post is helpful, it has a lot of information about Protective Equipment.I have gained knowledge from this article. keep sharing

Mazing.store said...

Thanks for sharing this useful information. User can buy industrial equipment online from anywhere

Durobyte Inc. said...

Thank you for sharing this wonderful Blog. It's a really helpful and Informational blog. Keep sharing technical & informational content. We are also from the same domain. We offer an Automated Quality Inspection System in Canada.

Hutto Pest said...


Really i like the way of your blog post content, it's a good information..

pest control services in pflugerville
pflugerville pest control company

Oliver John said...

Hello, this is an excellent piece of information; I appreciate it. I hope you will continue to publish posts of this nature.Lawson is America's largest moving company. They provide such a diverse range of machinery moving services

FOSHAN SKR TECHNOLOGY CO.,LTD. said...

hi sir / mam
chack types of machine in china 2021 at skrmachinery.com
about more product ckick on link mention blow:-
Granules machine
Vacuum forming machine
Plastic machinery
Extrusion machine

SKR_MSMS said...

wonderful machinery details, want to know about machine monitoring solutions, contact Automated AI based Predictive Maintenance Solutions

Site supplies midland said...

When carrying out construction, it becomes necessary to carry out a large number of physically difficult ones. Unfinished concrete is not aesthetically pleasing and attracts dust very well. To. Repair or construction of any premises is associated with the formation of dust and debris. Concrete builders and craftsmen are probably aware of the complexities associated with. After the concrete is poured, it may be necessary to drill holes and grooves in the concrete. The concrete vibrator is used to eliminate air bubbles and voids.

Dunvei Construction Consultants said...

Thanks for sharing your thoughts!

construction consultancies

Praveen chandra said...

Thank you

nice content and very usesful keep posting
Top Construction Equipment Rental Company
Construction Equipment Rental Company

Ganesh said...

Nice blog....Centering Material Manufacturers in Chennai
Scaffolding Material Manufacturers in Chennai
Sheet Cutting Service in Chennai

Emkay Engineering said...




Emkay Engineering is a leading of Cosmetic Machinery Manufacturer in India. These products are used in cosmetic processing. These products are collectively used as boilers, compressors, packaging machines, furnaces etc. These machines consume voltage starting from 220 V AC. These are automatic working machines which are made up of stainless steel and are made-up with another rust resistant coating. The capacity of the machines depends upon the work they are specifically designed to perform. We provide this Two Roll Mill Machine, Triple Roll Mill Machine in different technical specifications as per the exact need of our clients.

EZ Equipment Rental said...

Thank you for sharing your valuable tips! This is very helpful and informative! I’m looking forward to seeing more updates from you.

Sarwar said...

thanks for the information of heavy equipment maintenance management.

Find out our services at Construction equipment rental business

merit2005 said...

ENGINEERING PARTS FOR CONSTRUCTION MINING OILFIELD
Non OEM engineering parts for construction-mining-oilfield hydraulic hammer rock breakers of Epiroc, Rammer, Furukawa, DNB, Atlas Copco, MTB, Krupp, Sandvik, MSB, Allied, Kent, Montabert, Daemo, Bretec, Steck, Hanwoo, Chicago Pneumatic, Kwanglim, Tramac, Fine, Vega, Komatsu, Soosan, Topa, Toku, DandA, etc.
HYDRAULIC HAMMERS
Rock Breaker Hydraulic Hammer
Email: meritautomotive@gmail.com

Dennishahn said...

Thank you for sharing informative blog. Keep sharing this kind of blog
miller welding machine
airman generator
airman compressor
airman air compressor

ackerleyacton8 said...

Awesome article, it was exceptionally helpful! I simply began in this and I'm becoming more acquainted with it better! Cheers, keep doing awesome!
construction equipment appraisal

Certification course said...

If you want to know what is prince2 certification? you can visit PRINCE2 CERTIFICATION

EZ EQUIPMENT RENTAL said...

Thanks a lot for sharing this informative blog with us. If you are searching for construction equipment rental in Dallas Tx, you are in the perfect place. EZ Equipment Rental is well-known provider of all kinds of heavy equipment on rent. We provide it at very lowest price.

Khopart said...

Supplier of heavy equipment parts since 1968 KHO Parts is a family owned business specializing in Caterpillar parts. Located in Roelofarendsveen the Netherlands KHO Parts has become in the mid-2000’s one of the leading part dealers in west Africa. Equipped with European hospitality, a streamlined business process, and exceptional customer service, KHO Parts has grown tremendously over the years and continues to improve and expand.

Heavy Equipment Parts

Heavy Equipment Machinery said...

Hello, author! This blog was really enjoyable. Also I am very impressed with your post because this post is very beneficial for me and provide a new knowledge to me. We also the leading firm in Texas for buying and selling heavy equipment. TO learn more, visit our site.

Cindy Shelton said...

We, at DG web design Dubai Agency in UAE, simplify this web development process by focusing on every challenge and solution related to website designing .

Heavy Construction Equipment said...

This blog serves as a valuable resource for Thai highway contractors and stakeholders in the infrastructure sector. Addressing the common problems associated with heavy equipment management and proposing effective solutions, contributes to the overall efficiency and success of highway projects in Thailand. Implementing the recommended practices outlined in this article can help improve project timelines, reduce costs, and enhance the quality and sustainability of the country's highway infrastructure. Thanks for posting.

Cássio Cunha Lima said...

Another fantastic blog post! I always look forward to reading your articles. Thanks for sharing your expertise with us.

ellisonwilliams said...

I appreciate you giving your insightful advice. This is incredibly instructive and useful! More updates from you are something I'm looking forward to.

Cássio Cunha Lima said...

This blog stands as a valuable asset for Thai highway contractors and stakeholders within the infrastructure industry. By tackling typical issues related to heavy equipment management and presenting viable solutions, it plays a pivotal role in enhancing the overall efficiency and triumph of highway projects in Thailand. Embracing the suggested practices detailed in this article has the potential to boost project timelines, trim expenses, and elevate the caliber and sustainability of the nation's highway infrastructure. Much appreciated for sharing this insightful content.




Daniel Dantas said...

Thank you for this insightful and informative blog post, it really helped me understand the topic better. Keep up the great work!

Pedro Cunha Lima said...
This comment has been removed by the author.
Pedro Cunha Lima said...

Your insightful and informative blog post was greatly appreciated. It has significantly enhanced my understanding of the topic. Keep up the excellent work!

Beatriz Barata said...

Thank you for shedding light on the critical topic of 'Heavy Equipment Management Practices and Problems in Thai Highway Contractors.' Your insightful blog post not only highlights the challenges faced by these contractors but also offers valuable insights into potential solutions

Cássio Cunha Lima Odebrecht said...

Looking forward to your future articles. Your expertise in this field is invaluable. Regards Cássio Cunha Lima Odebrecht

smithwaugh@Dayinaustralia said...

Nyc article! The challenges mentioned, such as maintenance issues and downtime, are universal concerns in the construction industry. Implementing effective management practices can definitely improve efficiency and overall project outcomes.Thanks!





Australiacite said...

Wonderful article! It's truly a game-changer in today's competitive business world. This kind of training not only equips you with valuable skills but also boosts your confidence in handling complex projects. Thanks for highlighting its significance! To know more click here

smithwaugh said...

Thanks for sharing this post on heavy equipment management practices and problems in Thai highway contractors.Proper equipment management can lead to cost savings and better project outcomes. I'm interested in learning more about the specific challenges faced in Thailand and how contractors are working to overcome them. Great topic! To know more click here

José Felipe Duarte Ferreira said...

Your blog is an invaluable source of information. We appreciate you taking the time to write such insightful and thoroughly researched blogs. I eagerly await your updates every time!

João Carlos Duarte Ferreira said...

Your blog is a knowledge gold mine. We appreciate you taking the time to write postings that are so thorough and educational. Your updates always excite me!

Beatriz Barata said...

I appreciate the insightful blog post on "Heavy Equipment Management Practices and Problems in Thai Highway Contractors." This topic is of great significance, especially in the construction and infrastructure development industry. The article provides valuable insights into the challenges faced by highway contractors in Thailand when it comes to managing heavy equipment, which is crucial for project efficiency and safety.

Cássio Cunha Lima Odebrecht said...

Your blog contains a wealth of information. We are grateful that you have dedicated your time to writing such comprehensive and instructive blogs. I am constantly excited by your updates!

Beatriz Barata said...

Thank you for this insightful and comprehensive exploration of heavy equipment management in Thai highway contractors. Your blog brilliantly navigates through the intricacies of the industry, shedding light on both the commendable practices and the challenges faced by professionals in the field. The meticulous analysis of management strategies provides valuable insights, making it an invaluable resource for anyone involved in or intrigued by the construction sector. Your dedication to addressing the specific context of Thai highway contractors adds a layer of nuance that is often overlooked. Kudos on delivering such a well-researched and thought-provoking piece that undoubtedly contributes to a deeper understanding of the dynamics at play in heavy equipment management. Looking forward to more illuminating content from your expertise!

João Carlos Duarte Ferreira said...

Article about New York City! The difficulties described, including as maintenance issues and downtime, are widespread in the construction business. Implementing excellent management methods can significantly increase project efficiency and outcomes.Thanks!

Beatriz Barata said...

I wanted to express my sincere appreciation for the insightful and well-researched blog post on 'Heavy Equipment Management Practices and Problems in Thai Highway Contractors.' The depth of analysis and the clarity with which you presented the challenges faced by the industry in Thailand is truly commendable.Beatriz Barata

Luiz Antonio Duarte Ferreira Filho said...

Your blog is a treasure trove of knowledge. Thanks for taking the time to create such well-researched and informative posts. I always look forward to your updates!

Sidney De Queiroz Pedrosa said...

Looking forward to your future Posts. Your expertise in this field is invaluable.

Carzilla Auto Services said...

Thank you very much for this discussion. I read all the comments and really appreciate you all.

Aston Martin Transmission Repair in Dubai

Ricardo Oliveira said...

Your blog is an invaluable source of information. We appreciate you taking the time to write such insightful and thoroughly researched blogs. I eagerly await your updates every time!

Ricardo Oliveira said...

Thank you for bringing light on the vital issue of 'Heavy Equipment Management Practices and Problems in Thai Highway Contractors.' Your excellent blog post not only emphasizes the issues encountered by these contractors, but also gives great insights into possible solutions.

Ryan Cicchelli said...

Thank you for sharing this post about heavy machinery management procedures and issues with Thai highway contractors.Proper equipment management can result in cost savings and improved project outcomes. I'd like to understand more about the unique obstacles that contractors encounter in Thailand and how they're overcoming them. Fantastic topic! Visit here

Fast Marine Boats said...

Highway construction is a sector heavily reliant on machinery utilization to improve contractor capabilities and project efficiency. boats for sale abu dhabi

The Rental Boat said...

The strategic utilization of heavy machinery and equipment is vital in the mining sector to increase production rates, reduce costs, and enhance overall operational efficiency. boat rental abu dhabi

Digital Tech said...

By implementing a robust methodology for machinery management, contractors can optimize resources and reduce project timelines significantly. Cisco distributors in dubai

Beatriz Barata said...

Thanks for sharing! It’s impressive to see the depth of analysis on the current practices and challenges. The insights on optimizing equipment use and addressing maintenance issues are particularly valuable. Beatriz Barata

EZ Equipment Rental said...

Hello, the whole thing is going perfectly here, that’s truly good, keep up writing.

THEJEMBE said...

This article provides valuable insights. The challenges discussed are thought-provoking, highlighting key areas where improvements are needed. The professional project management perspective is especially useful for those looking to optimize equipment usage and efficiency. Great read! THEJEMBE

Luiz Gustavo Mori said...

Thank you for sharing such a detailed and insightful post on heavy equipment management practices. I truly appreciate the practical approach you’ve taken in breaking down the key aspects like preventive maintenance, equipment tracking, and lifecycle costing. This kind of content is incredibly valuable for project managers and construction professionals alike. Looking forward to reading more of your work! Luiz Gustavo Mori

Martha Stewart said...

Great read! Really appreciate the insights shared here. If anyone is also interested in quality living room furniture, I found a helpful guide: https://billsmattressandfurniture.com/how-to-choose-the-best-living-room-furniture-set/