The insurance premium payment is a major cost of project. If insurance is used, the premium must be paid in advance. If any losses happen in project, the project can get indemnification. However, the using of insurance can get loss of premiums. Therefore, the contract manager and risk manager need to consider about insurable risks. All kinds of insurable risks are not insured. Bunni (2003) mentioned that classification of risks on the basic insurability is shown in figure below.

There are many risks in the construction project. Each project activity may be its own risks such as occurrence of physical damages, accidents, materials delivery delays, unforeseeable problems, unforeseeable site conditions, natural hazards, political affects, etc. These risks will affect to the client, contractor, design professional, employees, third party and public. For instance, the contractor cannot be able to finish the project with contract price because of the economic situation and changes, the site condition changes, the difficulties of resources and others. Therefore, contractor’s default is one of the most important risks in construction projects (Arditi et al. 2000 cited in Al-Sobiei et al. 2005).
Contractor’s risks cannot be eliminated by the client, but it can be partly or totally transferred to the bonds (Al-Sobiei et al. 2005). When the project meets the unforeseeable contractor’s failure, it is very difficult to finish on time because the projects may have financial difficulties, delays and others. However, the surety bonds can provide to the client as a guarantee to complete the project and defaulting financial payment from the contractor (Russell, 1990; Mills, 2001).
Ms. Kyawt Phyu Phyu made a case study which objectives were to : (1) study insurable risks which can be managed using insurance and surety bonds; (2) study the insurance and surety bonds in oil & gas and petrochemical projects; and (3) develop a framework on risk and insurance
Conclusions
Objective 1
It was found out that there are many kinds of risks in oil and gas and petrochemical projects. Their risk management (risk transfer) approaches are the insurance, surety bonds and other approaches. However, most of the appropriate risk transfer approaches are the insurance and surety bonds and the detailed conclusion for objective-2 are described in table below.

Objective 2
it was found out that most of the projects don’t have the same insurances and surety bonds because of their project nature, project types, different project parties, different risks management system. The insurance premiums are also different relating with risks, project types, company background and others. If the risks are high, insurance premiums are also high. There are eleven (11) kinds of insurance and four (4) kinds of bonds on petrochemical and oil & gas project in this research according to case study.
(i) Recommendation Insurances for offshore pipeline project
The recommendation insurances for offshore oil and gas projects according to case study are:
1. Construction All Risk Insurance
2. General Third Party Liability Insurance
3. Marine Hull and Machinery Insurance
4. Protection and Indemnity Insurance
5. Worker’s Compensation Insurance
6. Transportation Insurance
(ii) Recommendations Insurances for Transportation and Installation Offshore
Facilities Projects
The recommendation insurances for transportation and installation offshore facilities projects according to case study are:
1. Construction All Risk Insurance/ Erection All Risk Insurance
2. General Third Party Liability Insurance3. Worker’s Compensation Insurance
4. Marine Hull and Machinery Insurance
5. Protection and Indemnity Insurance
6. Transportation (Marine Cargo) Insurance
7. Builder All Risk Insurance
(iii) Recommendation Insurances for Urea Fertilizer Factory Projects
The recommendation insurances for Urea Fertilizer Projects according to case study are:
1. Construction All Risk Insurance/ Erection All Risk Insurance
2. Transportation Insurance
3. Fire and Exploration Insurance
4. Worker’s Compensation Insurance
5. General Third Party Liability Insurance
(iv) Recommendation Insurances for Refinery Projects
The recommendation insurances for refinery projects according to case study are:
1. Construction All Risk Insurance/ Erection All Risk Insurance
2. General Third Party Liability Insurance
3. Worker’s Compensation Insurance
4. Construction Plant and Equipment Insurances
5. Business Interruption Insurance
(v) Recommendation Surety Bonds for Petrochemical and Oil and Gas Projects
In petrochemical and oil and gas projects, bid bond is needed in the bidding stage. In the construction and operation phases, performance bond (bank guarantee) and advance payment bond are important according to case study.
Objective 3
Main types of insurable risks in petrochemical and oil and gas projects are loss of life and personnel injury, material damage, material in transit and contractor’s risks. The insurable risks for oil and gas projects are collusion, oil pollution related with marine property. The researcher shows the detailed level of respective insurable risks in below figure. The project’s participants transfer these kinds of insurable risks to insurance and surety bonds, and the detailed descriptions are mentioned in figure below.

Her thesis abstract is copied and posted.
Abstract
There are many uncertainties, risks and probability and possibility of loss of chance in every firm, business, projects and human beings. The oil and gas project and petrochemical projects have many uncertainties and risks because these projects are related with geological risks, probability of existing oil, oceanography, and others. Insurance and surety bond are very important in projects because they can protect the risks, contractor’s default, and the project can get the financial and performance security. This study is emphasizing on insurable risks with appropriate types insurance and surety bonds.
This study emphasizes on the case study approach on petrochemical and oil and gas projects. The study was conducted to two oil and gas projects from Myanmar, two urea fertilizer projects from Myanmar and two refinery projects from Thailand to study types of insurable risks, insurance and surety bonds.
 
10 comments:
These kind of post are always inspiring and I prefer to read quality content so I happy to find many good point here in the post. Buy car insurance online
Those who are still far from your site they are missing the more brilliant stuff of the blogs.
Caia
In the projects like petrochemical it is extremely important to have insurance or surety bonds that can avoid risks that may be arise due to uncertainties.
Georgia dealership bond
The complete blogs are really inconceivable and definitely everyone will share this information.
cheapest life insurance rates
Fascinating information I haven’t been experienced such information in quite a long time.Continued
Thanks you have provided the nice blogs for us, I am glad about you.
bubblegum casting
Thanks you have provided the nice blogs for us, I am glad about you.
bubblegum casting
These are truly amongst the wonderful informative blogs.ppi reclaim
Great post! This case study is very informative. There are law that requires contractors to carry surety bonds and this protects not only your business but also your employees. Of course a Workers' compensation insurance is required if your business has employees. There are a lot business out there who provide life insurance for their employees in case something happens.
With the progress in civilization, the people of United States started to move inland into the continent. Gradually, they started to unveil natural resources from the vast stretch of land.
see more details : excavation massachusetts
Post a Comment