Wednesday, 9 October 2013

Engineering, Procurement and Construction (EPC) Contracts Performance in Oil and Gas Industry

Today, oil and gas companies prefer to sign the EPC contracts than other forms of contracts so that they can avoid and reduce any conflicts in execution of contracts due to interfaces and risks between project companies and contractors and easy to control the projects in every aspects.

EPC contracts are often used in medium and large scale oil and gas projects in Vietnam since 1990s. According to international practices, in case of any disputes or problems happened in the execution of EPC contracts, those problems and disputes shall be referred to clauses of EPC contracts and settled by arbitration in accordance with the signed contractual clauses and conditions. In Vietnam, some projects are usually built to meet the socio-economic issues and often guided by the Government. So it is a bit difference between the Vietnamese and international practice. Hoang Huu Cam made a study which aimed to focus on the following issues with regard to GDC Project’s EPC contract:

1. Delay in commissioning activity.
2. Consequences of the delay.
-    Extension of Time for Completion to EPC Contractor
-    Compensation for EPC Contractor
-    Compensation for Certifying Agent
-    Compensation for BP

General Conclusion

1. The successful factors of the Project
There were two factors resulted in success of the GDC project. The most important factor was tendering process and selecting the right EPC Contractor for the right works. The EPC Contractor, DWE, has much experience in engineering, procurement and construction. Besides, the Sub-contractor, Petrovietnam Engineering & Construction Company (PVECC) is one of the leading contractors in oil and gas industry of Vietnam.

Another factor was that the project management was very good during construction period. The EPC Contractor applied the latest project management knowledge for the project at that time and the Project Company was very satisfactory to this matter. Through this project, with the purpose of “on-job-training” both Subcontractor’s and the Project Company personnel obtained much experience and project management knowledge from EPC Contractor.

2. Adversely Impacted Factors on GDC Project
The first thing PVGC faced with was that it had less authority to control the relationships between the project’s stakeholders as well as responsibilities between them. This happened because a substantial part was mechanism in economic and business activities in Vietnam. Over 20 years of “Doi Moi” process, Vietnam has pursued a Socialist Oriented Market Economy which is a model that has no existence in the world so far. Vietnam has been seeking its own way on the road of development and protection of the country. Hence Vietnam has a lot of things to do in the process of global economy integration. Vietnam also became a member of World Trade Organization in 2006 and it needs time to change its existing legal system and business environment. These changes will create an equal and fair business environment for every enterprise including all businesses in all economic sectors.

Recommendations

Today although EPC Contracts are popularly used for medium and large projects in infrastructure and in oil and gas sector, but the success of applying the form of EPC Contracts are still dependant on both jurisdictions and practices where they are used for. In countries where jurisdictions are very stable and stringent, the application of EPC Contracts is very easier and more advantageous than that in countries where jurisdictions and legal systems are less stable and tight.

Based on the case study and analysis, the following recommendations can be made:

For the project company, PVGC:
- PVGC must have a program summarizing all projects have been done and analyzing adverse factors in order to prevent similar situations occurred in future projects.
- PVGC should make a proposal submitted to PVN and EVN to ask them speed up their gas customers to catch up the construction schedules planned during GDC construction period.
- PVGC should set up a risk management program for each project from the beginning to completion of the project.
- In order to minimizing any loss which may be incurred in the future projects when having a participation of any foreign company as stakeholder, PVGC should have more close relationship with its customers and have some agreement like off-take agreement.

For the EPC Contractor, DWE:

Because the DWE was the foreign EPC Contractor, therefore the EPC Contractor had to scrutinize the local legal system, practices and the economic mechanism in order to evaluate and foresee any situation he may face with in the construction period. The following issues needed to be taken before signing the EPC contract or sometimes are called contract signing checklist.

1. Review your Bid: DWE should review its Bid carefully before starting the signing of EPC contract.
2. Review complete plan: Before signing EPC contract; DWE should review all plans including sub-contractor’s plan, and the plans of other parties involved in the project.
3. Another aspect the EPC Contractor should study laws, regulations and other statutory documents that may affect the EPC Contractor during its execution of EPC Contract.

Abstract

Engineering, Procurement and Construction (EPC) Contract is widely used today in the world in general and in Vietnam in particular. Especially in oil and gas industry EPC contract is getting more and more popular and is often involved in medium and large scale oil & gas projects. According to an EPC Contract a contractor has obligation to hand over a complete facility or complex to a Owner (or client) who needs 'turn a key' to begin operating the facility, therefore EPC Contract is now and then called “turnkey contract. Besides delivering a complete facility or complex, the contractor shall deliver that facility or the complex at a guaranteed price until a guaranteed date and he has to undertake the construction work to satisfy designated specifications, requirements or to the specified level. Any failure of his obligations to comply with any specifications or requirements will often bring the contractor to bear monetary loss and liability.

Vietnam Oil & Gas Group had an early stage to get an application of EPC Contract forms in 1990s when Vietnam had suffered the United States of America’s economic trade embargo against all of its social and economic aspects. All EPC contracts that were used in oil and gas projects in Vietnam at that time always had foreign participations or involvement on those projects and most EPC contractors who undertook the projects were foreigners. After United States of America lifting its economic and trade embargo against Vietnam to date, the use of EPC contracts has been spreading to various industries and sectors, especially for ODA (Official Development Assistance) projects such as infrastructure projects where capital had been funded by foreign countries, regional and international financial institutions. The uses of EPC contracts are very common in energy projects like power generation plants in recent years in Vietnam.

However, there is still debate on the use of EPC contracts in Vietnam, because of Vietnam’s legal system, practices in construction industry and other matters.

This study will only be focusing on the use of one of EPC Contracts in the oil and gas sector in Vietnam – Phu My Gas Distribution Center (hereinafter referred to as GDC) and state the advantages, disadvantages and problems of EPC contracts applicable in oil & gas projects in Vietnam. How to resolve the problems in exercising EPC contracts and measures to be taken to prevent the problems will also be raised in this study.

2 comments:

JCB Services in Pune said...

This is a really good read for me, Must admit that you are one of the best bloggers I ever saw.Thanks for posting this informative article.

Anonymous said...

It is a great sharing...I am very much pleased with the contents you have mentioned. I wanted to thank you for this great article.
Construction, Engineering, Procurement