Even though a large portion of a construction project is
usually performed by subcontractors, the issues concerning about the
subcontracting practice are rarely acceptable (acknowledged) and the ways to
improve subcontracting practice are seldom debated.
Project delays are due to many
reasons such as poor communication, lack of resources and other factors. Most
of vast projects usually have problem with time and cost control. Vu Van Ngu made a case study which
main objective was to find out “How main contractors manage
subcontractors including procurement, cost, quality, scheduling and safety
aspects?”
Conclusion
In this case, it was found out that there are many factors that
influence subcontractor management such as tender preparation, subcontractor
selection, and contract with subcontractor, and subcontractor scheduling
management etc. In this case, the most important factor is tender document
preparation. The tender document was prepared but it was insufficient and
unclear because of poor design and inexperienced person was assigned to prepare
tender document. Due to these reasons, the subcontractor evaluation and subcontractor
selection were influenced and consequence of further sequences occurred.
The main contractor and subcontractor have responsibility in
management of project scheduling, project quality, project cost, and project
safety. However, the role of subcontractor is most important. If the selected subcontractor
have past experience for the project, have good management system, have enough
capability to carry out the project such as equipment, tools, labor, they can complete
the project by themselves. The main contractor only supports the subcontractor;
it can’t replace management of subcontractor. The main contractor subcontract
because of its not capable to carry out the project, or it is not specialized
in the subcontracted field.
Recommendation
Based on the problems, it can be said that the management of
subcontracting firm almost depended on the Main contractor organization such us
their capabilities, their experience, their management system. If their people
don’t have experience and capability, these problems normally happened:
1. They can’t properly prepare the
tender document which leads to difficulty in subcontractor evaluation.
2. They can’t select the right
subcontractor especially that some people base their decision on their and not base
on the actual requirement written in the tender documents and biding submitted
by the bidder. The subcontractor selection actually is a sensitive issue.
3. They can’t prepare sufficient
contract in which all risks have been considered, possible events mentioned
together with solving solution.
4. They can’t manage the
subcontractor’s schedule because they don’t know how to control their schedule.
5. They can’t monitor and
control the quality of the project because they don’t know exactly the quality
requirements applied for the project.
6. They can’t control the cost
and safety.
In tender
document for tender:
1. The tender document is very
important for bidders in preparation of document for submission. The main
contractor should assign competent person to carry out this works and all
tender documents should be reviewed carefully before issuance. If Main
contractor do not have people who have enough experience, the main contractor
should hire expert from outside.
2. When preparing the scope of
work, main contractor have to check and totally understand all contents of the detailed
design, any missing content or unclear content/ differences should be
explained, added in tender document or request subcontractor to check and
propose their solution/ methodology in submitted documents as option.
3. Evaluation form is very important
for evaluation. It should be reviewed carefully by well-experienced people. It
should indicate key factors based on which we can evaluate exactly in order to
choose the right subcontractor.
4. In order to use for further
reference, those document should be stored in systematic manner.
In
subcontractor selection
1. Members of evaluation team
should be carefully selected. They have to read and understand configuration of
project and all its requirements. He/ she should know what major factors
influence to project, what are minor factors which can be discussed, clarified,
adjusted in negotiation step.
2. In addition, members of the evaluation
team have to understand the requirements in the legal documents such as law,
decree…
3. Members of the evaluation
team should have negotiation skill, should be flexible, shouldn’t be rigid
during negotiation, should know how to ask subcontractor to understand
capabilities and past experience of subcontractor which we intend to select.
4. Members of the evaluation
team should have equitable behavior.
In
Subcontractor contract
1. During
negotiation, all responsibilities of each party should be detailed and clear.
2. The scope of work should be
cleared; any ambiguous issues shall be raised and discussed until both parties
understand the same meaning.
3. Payment term, milestone
should be defined in details; any documents which are necessary for payment
should be specified.
4. Main contractor,
subcontractor should predict situations for impact cost, impact schedule and
set out feasible rules for implementation.
5. Main contractor should assign
a person to manage the contract ensuring that it is controlled according to
commitment between parties.
In subcontractor
scheduling management
1. The
main contractor should assign personnel to control project schedule (Project
schedule controller), update and report to project manager every week or when
necessary. Base on report of inspector, project schedule controller should calculate
achieved schedule and comparison with targeted schedule. The calculation result
will serve as evidence for giving necessary solution.
2. The inspector of main
contractor should go to the site regularly to inspect and record the exact
quantity done by subcontractor.
3. The main contractor should carefully
review the schedule of subcontractor, make sure it is feasible and includes any
possible risks.
4. A solution to settle delaying
schedule of subcontractor should be given in the contract. The main contractor
can take over subcontractor’s responsibility to recover project schedule when
the subcontractor is not able to catch schedule.
In subcontractor quality
management
1. The
main contractor shall assign experience inspectors to control quality of
project.
2. The design document provided
by client should be detailed, sufficient, indicated the criteria, and the standard
applied. The design document of subcontractor should be reviewed and approved
by main contractor when necessary.
3. Main contractor should check
and approve construction procedures, especially inspection and test plan (ITP ) content in the procedures.
4. Main contractor should
require subcontractor set up quality team and control quality by themselves.
In
subcontractor cost management
1. The
payment should be based on completed quantity; this quantity should be strictly
controlled.
2. Any impact cost should be
checked, approved, and controlled strictly.
In
subcontractor safety management
1. The
safety should be emphasized at the start of the project and maintain through
the project.
2. The safety should be reminded
regularly.
3. The risk assessment is always
useful.
4. The permit to work should be
applied for hazardous work.
Abstract
Because of the increased project
complexity and the highly competitive nature of the construction industry, a
construction project often is executed by several subcontractors. Hence,
effectively managing the numerous subcontractors involved in a construction
project becomes a crucial challenge for the general contractor in ensuring
timely project completion with acceptable quality.
Managing subcontractors does not
simply involve asking them to allocate resources (labor, material, and
machinery/equipment) into the jobsite whenever an activity is scheduled, and
then pushing them to speed up the work without a clear consciousness of
schedule risk. Factors (or uncertainties) such as weather, labor, site
conditions, material delivery, and equipment breakdown can influence the time
performance of subcontractors, affecting total project duration.
But almost General Contractor is
leak of management sub-contractor and it caused many difficulties and conflicts
during performance, management of projects.
The most difficulty of sub-contractor
management is deviation scope of work between sub-contractors, controlling
schedule and interfacing between subcontractors.
In managing project subcontractors,
a general contractor must determine the items of work to be subcontracted,
select subcontractors, set subcontract agreements, and control the
subcontractors during construction.
1 comment:
It is really what I wanted to see hope in future you will continue for sharing such a excellent post.
Assignment Help Tutors
Post a Comment