Many construction projects in Vietnam have experiencing
delay which becomes a big problem for each project because of lack of solution.
In the construction stage of any project, anticipating many factors that may cause
delays is one of the important works of the project manager. Therefore, project
managers should give solutions for them before the construction starts. However,
sometimes it is not important for each project because both owners and
consultants do not care about this. That is why many construction projects are
delayed. There are a lot of reasons that
causing delays, including force majeure and human acts. We could not solve
these problems absolutely.
Tran Van Trung made a research, which is
a general view about delay problems in construction projects such as problems
happened during the foundation work, escalation in cost of material, equipment
import management for construction, to find out the reasons and solutions for
each case. The purpose of his report was to find out the main factors causing
delay and affecting other aspects in Thermal Power plants in Vietnam at all
stages of projects. These factors were analyzed in different ways of parties
such as the Laws, Authorities, the Owners, the Contractors, Consultants, and
Sub-contractors. From that, factors which are mainly effective to prevent and
control delays in Thermal Power plants can be seen.
The objectives of his study were
to:
1. identify major delays in
Thermal Power Plants in Vietnam.
2. identify the major cause
(reasons) of delays in Thermal Power Plants in Vietnam.
3. recommend strategies for
improving project delivery based on the finding from the study.
Conclusion
Delay in the construction
industry is a serious problem in general and in all the coal-fired Thermal
Power plant in Vietnam in particular. The project investigated in this study
exhibits a delay like in all power plants in Vietnam. Therefore, the results of
the research provide a framework for project managers who can better understand
the dynamics of project management and taking efforts to reduce incidences of
delay time.
By administering and analyzing
factors affecting the project, this research had identified problems related to
delays during construction phase. From these results, once again, it is noted
that most causes of delay of the project related to Consultant company of owner
who set up F/S and surveyed site conditions before and Fishner Company as A/E
of owner. Furthermore, subcontractor as PM caused delay in the highest impact,
the quality of its equipment was not reliable and the quantity was not
asynchronous in delivery.
In the case of this study, so as
to find out the causes, impacts and solutions when facing delay problems, the
research had analyzed twelve major factors that cause delay in construction
stage. Although these problems may be unprejudiced reasons or subjective
reasons, they were also originated by carelessness in the implementation,
management or supervision. Then, this research had deeply analyzed other
factors that also affect schedule for each case. Therefore, for each delay
case, the overall view and solutions for preventing or reducing delays in
future projects have seen.
In summary, this research
summarized some reasons behind the delays caused to project, and proposed some
recommendations which might enable the main contractor organization to develop
in the competitiveness to achieve one of the major goals in power plants, on
time completion, after that, we can prevent these causes in next projects.
Abstract
In construction
industry, a project is known to be successful when it meets three fundamental
criteria such as finishing on time within the budget, the prescribed quality
requirements such as satisfying customer’s demand and adapt safety in operation
stage. Unfortunately, all of Thermal Power Plants built in Viet Nam had
problems of project management leading to their delay. Investigating these
problems has become project manager’s indispensable demand.
In general, the
problems involved with project delays are solvable. In making effort to solve
these problems, the critical factors influencing negatively on construction
duration need to be discovered. Hence, it is very important to establish a
systematical approach that will be used as a tool for the investigation.
This report will
assess and analyze twelve factors causing the delay problems in Uong Bi Thermal
Power Plant was executed in the North of Viet Nam. The qualitative method
basically is based on the principle of assessing the risk level of factors
impacting negatively on the progress of the project, and it is conducted to
fulfill the objective of the study.
Finally, some
solutions dealing with project delay problems in construction executing stages
are proposed.
1 comment:
If you plan on a long term career as a project manager, then yes, even with your level of experience, I would suggest getting your PMP. You can prepare yourself for the exam in one of the PMP providers likehttp://www.pmstudy.com/. You can do minimal prep-work to get 40 PMI® Contact Hours and apply to PMI for PMP Exam before the class begins.