EFFECTIVE
PLANNING & CONTROL OF MULTIPLE PROJECTS
A
CASE STUDY OF GR60 - NOKIA STORES CHAIN IN VIETNAM
By
Nguyen Thai
Son
Abstract
The report expresses the key
issues in Effective Planning & Control of Multiple Projects that
known as the popular trends for many projects of those companies who want to
develop marketing strategy in Vietnam.
This study, which refers to the
theories and the standards system, has expressed the concept of Project
Planning and Controlling. The study has briefed the factors that most
effect to multiple projects planning and controlling studied from case study
reports and the key points to control multiple projects effectively from the
design to construction stage. The report has introduced a Planning and
controlling process for the purpose of amendment to the existing Multiple
projects Planning and Controlling in order to obtain a complete process for
better managing multiple projects.
The next part of this report is
the case study on the NOKIA GR60 Project that have been implementing by DHC
contractor in Vietnam in 2011. Through this case study, the findings on the
existing Project Planning and Controlling and the application from the previous
part to this existing Project Planning and Controlling for improvement will be
the foundation for next coming multiple projects. This is also the objective of
this study.
Executive summary
Rationale of research
This research has been conducted to identify multiple project management
strategies.
Objectives of study
To investigate multiple project management in terms of planning,
organizing, communicating and controlling. And propose strategies to manage
multiple projects.
Methodology
The exploratory research method
is used to review the literature and case of GR60 project and applying those theories to the existing
project planning and controlling, in order to amend and improve it.
Findings and conclusion
Project
goals were set very clear to project employees at all levels.
Project scope of work was well defined but not detailed enough, Project manager
used Work Breakdown Structure to develop the level of work as well as work
relationship. Company organization is defined as a matrix organization
structure, so the GR60 project is applied project financing to implement from
beginning to ending. It is very easy to control the financing statement of the
project.
After a
month, Project manager use Object Charts and cost variance to review the schedule,
cost of the projects that finished in a month. Then he created an evaluation to
see if the project schedule is delayed or cost overrun. He also investigated
the problems and proposed solutions to avoid problems that effect on schedule
happen again.
For external
communication, there were many communication problems happened during projects
implementation process such as delay in transfer information, delay in change
order approval, contractor could not work directly with Distributors as well as
store owners. These problems affected too much on projects schedule. Board of
directors and Project manager found some solutions to solve the problem
effectively such as organize meeting more often, issue new communication
procedure to be suitable with the project style.
·
Multiple projects plan must be defined before
starting projects. In terms of scheduling, evaluating, coordinating and
controlling.
·
The multiple projects plan must be developed
with input from people who will be performing the work, and must be
communicated to all participants. The tasks, costs, and schedules of the
multiple projects plan establish the benchmarks and check points that are
necessary for comparing actual accomplishments to planned accomplishment, so
the progress of the multiple projects can be measured, evaluated, and
controlled.
·
Identification of Project Goals which are
specific, measurable and realistic. There must be agreement about Projects
goals. Multiple projects need time frames
for the goals.
·
Identification of suitable organization
structure to apply to multiple projects. Matrix structure and Functional
structure are recommended to control multiple projects
·
Construction companies should select a simple
scheduling technique to plan multiples projects schedule because multiples
projects including many small projects that have limited task and short
interval time.
·
Internal
and external communication procedure also must be considered by construction
companies during multiple project planning process. Clear and well-identified
communication procedure throughout communication channels will contribute a lot
to the successful of multiple projects management.
·
To be effective, construction companies should
develop a multiple projects control system which must be simple to administer
and easily understood by all participants in a project.
·
Line of Balance (L.O.B), a
precursor of the network analysis technique, which relates program to forecast
targets to determine how well a project is processing, is recommended to
maintain control over multiple projects implementation period.
·
Construction companies should
use Objective Chart to review and evaluate work schedule of multiple projects
·
Construction companies also
can use Cost variance to review and evaluate the costs of multiple project