OWNER’S EPC PROJECT MANAGEMENT IN POWER
PLANT PROJECT A CASE STUDY OF NHON TRACH 2 POWER PLANT PROJECT (750 MW)
By
Nguyen Nhat
Tai
Abstract
In
recent years, construction industry in Vietnam has been developed dramatically,
contributing to national development. Besides civil construction,
infrastructure, residential development, there are a large number of Power
plant projects are and will be implemented in the next 20 years.
Similar
to other types of construction project, power plant project must also deal with
risk of quality, time, cost on construction stage. As a large scale project
with thousands of activities, power plant project requires a very carefully
planning, scheduling and monitoring to avoid these risks.
There
is a fact that in reality, implementation of power projects usually goes behind
the schedule, causing a huge loss to social economy and obstructs the
development of local construction market.
The
purpose of this report, by studying a real case in Nhon Trach 2 Power Plant
Project, is to analyze EPC management strategies in such power plant projects;
from that, to suggest a framework of EPC management strategy for Power Plant
Projects in future.
Executive summary
Rationale of research
This research has been conducted to identify project management
strategies in EPC contract (Power plant projects).
Objectives of study
To study and propose strategies for EPC power plant project in
construction stage for thermal power plant project and develop project
management frame work for owner.
Methodology
The
exploratory research method is used to review the literature and journals and
understanding phases of power plant projects
Findings and conclusion
Demand of
electricity in Vietnam within next 10 years will increase highly, the current
Power Plant Projects in Vietnam are meet problems in terms of schedule, cost,
quality, and those are results of poor project management in Power Plant
Project. The research study summarized and proposed a strategy to manage EPC
Power Plant Project in EPC stage by the following activities:
·
Management
of Engineering;
·
Management
of Procurement;
·
Management
of Construction.
The research
study showed an overview of a thermal power plant project in terms of
characteristics, technology, facilities, contract, process and risks.
Through
collecting related documents as well information from interview from experts as
well as people participated in Nhon Trach 2 Power Plant Project, problems and
risks were anticipated, controlled closely during process of Project.
The
problems and risks in terms of quality, schedule and cost did not occurred
during process of Project through making a copy of Ca Mau 1 and Ca Mau 2
Projects. However, there was a waste of money in construction by making a copy
of Ca Mau 1 and Ca Mau 2 Projects in terms of soil improvement and foundation.
Concurrently, according to guideline of Petro Vietnam about proving internal force
as well as utilizing manpower of subsidiary, therefore, some unqualified and
inexperienced subcontractors were allowed to participate in Project.
·
Optimizing design in Feasibility Study by arranging
layout most properly and selecting the most proper technical solution: this stage is
one of the most important stages, technology and conceptual design were
selected from this stage, then after that, to determine total cost investment
as well as EPC Contract price properly;
·
In bidding stage, review/update latest technical
specifications and put strict requirement for subcontractors into Bidding
document:
because Power Plant Project is a complexity project in terms of civil,
mechanical and electrical. Therefore, subcontractors assigned to conduct
separated packages in scope of EPC package have to have capability as well as
experience about construction in Power Plant Project;
·
In engineering stage, conducting value engineering
in foundation solution: because the price of EPC Contract is lump sum,
therefore, EPC Contractor always wants to conduct engineering according to
their standard designs and procedures. However, implementation of value
engineering not only avoid waste of money but also reduce schedule of
construction;
·
In procurement stage, increasing Owner’s/PMC’s
involvement in controlling QA/QC works of procurement: under EPC
Contract, volume of electrical and mechanical works makes up more than 60%
volume of EPC works, in order to risks in procurement resulting in claim, cost
variation, Owner/PMC should participate in inspection of fabrication and
manufacture of equipments in foreign.
·
In construction stage, coordinating with EPC
Contractor to increase inspection of works conducted by subcontractors and site
preparation : suggest
EPC Contractor to replace unqualified and non-experience subcontractors if
works are delayed and construct temporary drainage system before starting up;
·
In commissioning stage, considering standby
alternatives before commissioning: commissioning is one of the most
important stage of Power Plant Project, if failure, it will result in delay in
completion and handover in order to put into operation.