In
Vietnam the construction industry especially residential and complex building
is now suffering many problems from design to operation. Some normal problems
are:
1. Coordinate between Architect
and Structural have many difference because they maybe are another country but
the project to be built at other country.
2. Difference communication from
Architect and structure by the owner, maybe the condition of contract to be
limited.
3. In during construction have
many problems from project as lack permit of government of other board.
4. The method of construction
from contractor is uncorrected with local building therefore accident will be
happen. Example: When the designer provide method for excavation work but they
study little big about geology, the result happen underground water to damage
the diaphragm wall so the neighbor house to be subsidence.
5. The project be delay which
reason the owner return payment to contractor is not on time following contract
condition.
6. Disputation between project
construction management group with main contractor or main-contractor with
sub-contractor about claim, variation order, quality, delay of schedule, and
coordinate with other contractor.
7. Taking over have a lot of
difficult from contractor to project management group because the standard not
clear or unable enter general standard.
8. When PCMG hand over the
project to client but client have difficult about finance, on the other hand
the client does not receive because some reason from the owner as service
following the contract.
9. Problems during operation as
warranty manager. Example when the owner pay all the claim but it included
percent of warranty and then the project have problem they request contractor
to come rework but contractor do not want to come in order to rework.
10. Resolve complain from client
about service quality, the method manage project.
It
is very important to understand the normal problems and to find the ways to
solve all of them in order to be able to develop an effective planning management
process, and also to take experience manager in project construction
management.
Nguyen
Hung Cuong made a case study aimed to:
1. study delay in planning, design, construction.
2. find out to solve at prevent problems in each
stage.
3. propose project life cycle strategy in how to
develop residential complex.
Conclusions
The
project life cycle will be successful in each phase if the project management
must have a clear plan and resolve the problems earlier during construction
phase in coordination with all the contractors. The project will be completed
on time and it satisfies quality, safety and more pleasing to clients.
In
order to solve the problems, proposed solutions based on theoretical and
recommended practices including guidance from the PMI’s PMBOK guide, one of the
world’s most prestigious guides to the project management, were presented.
Besides, some useful tools were considered and suggested to use as the aids for
the project managers to improve control management in the project.
However,
this case has limited information, due to some companies’ confidentiality.
Thus, the data gathered were from their staff, from the internet and during the
actual construction.
The
project delay usually involves the contractor, the owner, and the client. So,
the PCMG have to resolve the cause of delay and control the taking over process
to accomplish the project on time which brings profit to company.
Recommendations
In
order to avoid project delay problems from concept design to project operation,
The Manor phase II project made the following recommendations:
1. PCMG
have to prepare permission together with concept design before constructing the
project, and control the plan in such a good way. The plan monitoring is very important
for project management. In this project case, the owner committed a mistake when
they started the project without Government permission yet resulting to 1.5
years delay. The reason why the reason why the contractor and client lost a lot
of profit.
2. With
regard to the Owner, to estimate the project expenditure, the owner should have
board that will double check it phase by phase. In this case, the owner did not
estimate the cost of project.
3. The
Project Construction Management Group should organize training in order for
them to know how to use the process to accomplish project and contract
condition.
4. Document
controls for project is very important, all the site instruction should make
the process for resolved and return it to contractor soon, with the process
that all the scope of work will be completed on time.
5. In
case of ISO certified company, Project Manager should give feedback to the
company’s Quality Manager to add in personality test forms together with Job Application
Assessment Procedures forms. That will save Project Manager’s time whenever
there is new job applicant coming to job site for interviewing.
6. With
contractors, PCMG have to request them to submit the schedule of delivery
material to PCMG in order to double check it. Also schedule of project, PCMG
can check and give the site instruction to contractor if they detect problems.
7. The
contractors always make report of human resource to PCMG in order to inform
that the manpower is enough for scope of work. They make sure that with this
manpower project can be completed on time.
8. Relation
division always have the plan to solve problems with the method soon to
contractors, also project will be base on the site condition to work in order
to complete the project on time.
9. The
weekly meeting is very important for PCMG and also to the contractor. All
problems have to be resolved in that meeting, and relation division have
limited time to return the request for information to contractors.
10. Some
reasons relating to project delay and about safety work on site, all contractor
must provide policy of safety to PCMG, the safety policy monitoring everyday will
reduce accidents. The project having zero accident mean safety policy is
successful.
11. Finally,
the taking over and claim of payment during construction are bigger problem
between contractors and the Owner. Some project delays are sometimes due to
this reason.
Abstract
The
planning process in project life cycle is one case study in the Project
Management Institute’s A guide to the Project Management Body of Knowledge. In
the case study of Project management is established planning process in project
lifecycle is very importance therefore this is really a tough challenge and
time-consuming task to any project manager.
The
drawing up the plan from concept design to operation project that it suggested
management must have large line of vision also experience .The planning process
will be evaluated clear that must link everything from the owner, design,
contractor. This final project report focuses on construction project as
lifecycle project needs who’s have responsibility to design planning process to
be clear within knowledge. Though a case study of residential and complex
project in Ho Chi Minh City, many problems that we can saw which cause project
interruption will be investigate and analyzed. A lot of solutions be proposed
which base on the knowledge will be discussed to help project management in
order to improve skill in the project.
3 comments:
I Agree with u.Your blog is creating
with company's brand and related to the powerful marketing.
Residential Project For Buy
Planning, Design and Construction really Important in timely. I’m glad to have learned there is such a thing. thanks for Explaining Delay planning, designing and construction in his article.
Reserve Specialist
You have put something nice information about Delay in Planning, Design and Construction. today be need more careful Thanks For sharing here.
Condominium Association Engineering
Post a Comment