ANALYSIS OF DEVELOPER’S MISTAKES IN APPRAISAL, APPROVAL AND PERMIT
ISSUANCE OF THE CONSTRUCTION INVESTMENT PROJECT IN HO CHI MINH CITY
By
Nguyen
Thi Thu Nga
Abstract
For construction investment
projects, the investment project time of performance directly affects the
investment efficiency. However, in the recent years, in Vietnam, the management
and the control of “the time of performing construction investment project in
Vietnam” has not been interested in and strictly managed, thus leading to many
projects delayed in a long time, badly affecting the economic development and
social living, especially as for projects using State budgets. Accordingly, the
time of performing the procedures of submitting and approving investment
project documents and asking for the permit of constructing the project is
always troubling the heads of investors and spends so much time. Thus, it seems
challenge for project management consultant, the owner, especially to the
foreign investors!
On PMC aspect, how to ensure
reducing the time for doing project procedures is one of the critical points
that I focus to study. My research is based on surveys about the normal problems
on approvals and permit phase of the construction project. This assessment is
studied together with theory application for the process, procedure of the
construction investing project approval and construction permit, the regulation
compliance in the construction; What to be prepared, done shall be systemized
as a well being prepared for future projects and a contribution to improve
overall the quality of the construction project document through approval and
permit phase.
Executive summary
Rationale of research
This research has been conducted to identify mistakes in
investment project document for approval.
Objectives of study
To
study, and find the appropriate investment project document without errors to
get approval, identify difficulties, mistakes and causes in different stages to
suggest recommendation for getting approval of construction investment project.
Methodology
The exploratory method is used to review the literature and analyze the survey difficulties and mistakes
happened in project approval document.
Findings and conclusion
Through this research, we can identify faults
discovered during the appraising process of
the construction investment project document and document asking for
construction permits
The common mistakes in investment
project document are follows:
·
Procedure
for adjusting the total investment quotation in the designing process
·
The
manner and the form of capital contribution
·
Fees
of evaluating the working drawing design and the cost estimations
·
Procedure
for approving and re-adjusting the project
·
Estimation
about the whole investment quotation
·
Constructive
criteria and norms for the emergency
·
Constructive
criteria and norms for disable people
·
Conformity
of the connection with the technical infrastructure of the area
·
Design
for the basement
·
Concerning
the anti-shaking
· Design
for traffic inside the building
· Concerning the project of total
height > 45m
·
Designing
ventilating height of the rooms
·
Designing
the size of the public community hall
·
Not
conforming to Design /Construction Standards & Construction Rules
·
Demonstrating
wrongly or not clearly the road limits of the lanes adjacent to the site
proposed for construction, leading to a wrong indentation of the project.
·
Lacking or not conforming to detailed planning
legality
·
Lacking
ideas of one or several relevant authorities about the proposed project
·
Lacking land legality
Recommendation
For Project Planning Consultant
·
Paying
more attention for frequent mistakes and often review design before submitting
document for approving.
·
Collecting
and carefully considering all codes and standards usually used in
design/construction activity in order to appropriately applying with each
function of building.
·
Clear
descriptions of using size and sort of functions have been showed on design document
·
Doing well the
survey of the current technical infrastructure before designing the technical
infrastructural system of the project
Project-planning
stage:
·
The
project-planning work is clearly carried out for the whole project in all
stages.
·
Conduct
socio-economic survey in detail, using the survey information from independent
survey sources.
·
Research
and offer all technical arguments to justify the selection of the site of
developing the project.
·
Analyze
and calculate intangible elements affecting the project such as the inflation
element, spiraling price; new guidelines and new policies of the Government
directly affecting the project.
For Owner
·
Together
with consultants well preparing all procedure for
defining deliverable, evaluation, report, assessment. (Quality assurance
system)
·
Choosing
a potential, experienced and prestige design consultancy unit in the designing
work;
·
The
more detailed the economic contract contains, the easier the faults are handled
once faults caused during the stage of making and evaluating the project
appraisal
·
Should
use the model design of several social infrastructure works such as apartment
buildings, schools, head offices of commune-level people's committees and
health clinics to reduce the cost of design consultancy
·
Prepare reality design management program for obtaining target
expected (containing time for review, revising, approval)
·
Verify scope signed in contracts for anticipating gap in the
approving work and asking for permit.
·
Monitor designs and project works to be integrated with operators
closely.
For Government
· Encourage an architectural design
contest for the projects financed by the State budget in addition to compulsory
projects for pre-qualification in order to exclude the less capable units.
Therefore, the design quality will be assured.
· All of detailed plans in the
territory of Ho Chi Minh City completed as soon as possible.
· Build the mechanism of
transparency in the field of investment planning.
· It is to further speed up
administrative reforms, reducing troubles in fields as granting building
licenses and granting investment licenses. .
· The implementation of strict
sanctions against violation of rules