Japanese
contractors have been setting up their companies in Vietnam since 1990 and
operating successfully with many buildings finished on schedule with good
performances. Although Japanese contractors have created a good reputation with
Japanese standard quality and on time delivery, there have been some problems
remained in their system that the report was analyze in terms of Procurement
Management, Organizational Structure, Sub-contractors Management, Customer
Management, and Safety Control. Mr. Le Hoang Nguyen focused
on the following problems:
3. The owner – the main contractor – subcontractors – suppliers can form a supply chain.
4. The most important thing, how to control safety matters following the safety plan in the actual Vietnamese conditions with local subcontractors.
3. Sub-contractors Management.
4. Customers Management.
5. Safety Control.
1. Procurement
or project delivery type of the Japanese contractors is Design & Build.
2. The
organization structure of the Japanese contractors is usually too simple to meet
all the requirements such as safety and QA/QC properly. 3. The owner – the main contractor – subcontractors – suppliers can form a supply chain.
4. The most important thing, how to control safety matters following the safety plan in the actual Vietnamese conditions with local subcontractors.
In
conclusion, by analyzing the current project management approaches in Japanese construction
companies in terms of procurement management, organization management, sub-contractors
management, customer management and safety control, the report will find out
strengths & weaknesses of the existing system and recommend for
improvements.
The objectives of this case study were to : (i) study the current practices in Japanese contractors in Vietnam in term
of Procurement Management, Organizational Structure Management, Sub-contractors
Management, Customer Management, and Safety Control; (ii) investigate for an efficiency
of organization set up; (iii) find out strength and weakness of the current
system; and (iv) recommend approaches for improvements.
Conclusion
Basically,
through the analysis of the current project management approaches the strengths
and weaknesses of the current system were found at some points. Although the
report shows the efficiency of the existing organization and the management
system, in conclusion, the mentioned above project managements was reviewed and
some approaches are recommended for improvements.
1. Procurement Management and organizational
structure
Design
& Build with lump sum contract and fast-track management is still the strong
point of this type of procurement. This is based on the relationship and trust.
Though, the high cost and risk are the remained issues need to be improved to increase
the contractor’s competitiveness. There are some proposed approaches such as
breaking down the scopes of work into smaller scopes with specialty suppliers,
direct purchasing for main materials, equipments and machines. As a result, the
direct cost could be reduced considerably.
As the
demands of the procurement system, the organizational structure has some related
issues. The organization is too simple to cover all the required works in terms
of technical issues, construction works, QA/QC, safety matters and purchasing
orders. In the proposal, the organizational structure should include necessary
departments: Technical Department included QA/QC and Safety departments,
Construction Department, Commercial Department with Procurement Department,
Administration Department and Accounting Department etc.
The
concerned issue is that how to localize the management in the Japanese construction
companies in Vietnam. The return of the localization the management could be
the cost reduction, better communication, management and/ or coordination between
local staffs & different departments and local suppliers, subcontractors,
consultants. This is essential to form a supply chain network.
2. Sub-contractors management and customer
management
As a
matter of fact, in a general view, subcontractors – main contractor – customers
form a supply chain network through project by project. So, the importance of
relationships, between the client and the contractor, the contractor and the
subcontractors should be understood properly. Moreover, the relationship should
be focused on improving performance and adding value to the process.
In order
to achieve the above targets, the following approaches could be applied.
First,
at least three companies of each supplier, subcontractor and consultant should
be considered, evaluated and then maintained for every project to have the best
competitive price and performance delivery. Second, co-operations with supplier,
subcontractor and consultant should be in more than one project in order to
incorporate the knowledge into the new project and achieve continual improvement.
Third, long-term relationship with the subcontractors should be considered and
maintained in the concept of supply chain network by keeping payments on
schedule and variations approval and any necessary supports at the right time
of need. In other word, the Japanese contractor has to play the main role as
the chairman in every meeting and co-ordinations in terms of time, cost,
quality, and safety control in all the phases of the project.
Customers
are almost the Japanese companies, the unique specific characteristic in Japanese
contractor. Because of the increasing critical competition, the demand is that
how to get jobs from non-Japanese customers. Achieved this target, the Japanese
contractors not only could increase their competitiveness with local contractors
but also expand the supply chain network.
3. Safety control
Finally
and the most importance is safety first, the much different thing compared with
local contractors. Safety control at jobsite is follow the company safety policy,
safety targets and safety plan with specific measures and safety construction
cycle in daily, weekly and monthly. However, the following recommendations
should be considered.
First,
the safety policy should include all of business activities, and the organization
should be set up to make sure the safety plan is implemented seriously sufficiently
and efficiently.
Second,
planning and implementing safety targets should get agreements with managers
and supervisors to make sure the targets are achievable. In addition, purchasing
and supply policy should be taken into account too.
Finally,
for continual improvement, not only safety construction cycle is implemented
regularly but also PDCA (Plan-Do-Check-Action) circle should be applied
continuously. Moreover, health and environment matters should be taken care of
and applied at jobsite for a better working and living environment.
His thesis abstract
is copied and pasted below.
Abstract
Vietnam construction industry has been
developing significantly since 1990 with more and more high-rise buildings and factories
built in Ho Chi Minh City, Hanoi, Da Nang, Can Tho and other cities due to continuously
increasing demands in economical, cultural and social aspects. Foreign contractors found
this big chance and set up their company in Vietnam at the right time. Among them are
Japanese contractors such as Kazima Corporation, Shimizu Corporation,
Obayashi Corporation, Fujita Corporation, and Taisei Corporation, which have been operating
over fifteen years in mainly the industrial buildings section. As the result, the
competition between the contractors, local and foreign companies, has been increasing dramatically.
So the most challenge for the Japanese
contractors in Vietnam is how to increase
efficiency, competitiveness and sustainable development.
For these purposes, this report will
analyze the current project management approaches in Japanese contractors in Vietnam in terms
of:
1. Procurement Management.
2. Organizational structure.3. Sub-contractors Management.
4. Customers Management.
5. Safety Control.
Finally, in comparison with the theory
and practices, the report will point out the strengths and weaknesses of the existing management
system in comparison with the local companies, then recommend for improvement
approaches that could be applied in Vietnam.
3 comments:
Really nice information to go through this...please share more detail of this...
Such Wonderful information. It can really grasp helpful and informative insights to everyone. Thank you
Nice blog!
Construction Companies
Post a Comment