Design consultant or designer plays an important
role in project quality. Currently in Viet Nam, there are
many requirements for design quality. However, investors (public or private
sector) have not really focused on the management of the project design, and
the role of consultant/engineer in the design process has not been properly concerned.
This affects the quality of work negatively. In order to create a good
construction work, quality should be paid attention to all stages, especially
in the first design stage. A detailed and perfect design will help to minimize
defects or failures in construction, thus save costs and expenses. During
construction period, such minor defects or failures may cause personal injuries
or work delays, leading to indirect costs of insurance, inspection or
regulation. In summary, the success or failure of a project is greatly affected
by the decisions during design and planning stage.
Design quality must refer to health and safety factor in the project. A lot of decisions made in planning and design process related to safety during construction, and such careless design can make it dangerous or difficult to carry on construction works. On the other hand, good plans may considerably reduce the possibility of accidents. Hence, design consultant bears the responsibility to the owner and the society for design quality, material specifications and functional performance in their design. Mr. Doan Ngoc Hoai Vinh made a case study which major objective was to study the Quality Management in Design Process, and in order to achieve this objective, three sub-objectives were needed to accomplish such as: (i) study the existing practices of design process and management in Phuoc Binh Apartment project; (ii) analyze the effectiveness of design process and management; and (iii) provide framework for design process.
Conclusion
Design process quality management is very important to make high-performance of design and construction services. However, there are a few design companies which apply quality management for the design process in Vietnam and there are many causes related to this problem.
Abstract
v Sometimes we lose the next project for a client, even when we have done
a great job on the previous one.
Design quality must refer to health and safety factor in the project. A lot of decisions made in planning and design process related to safety during construction, and such careless design can make it dangerous or difficult to carry on construction works. On the other hand, good plans may considerably reduce the possibility of accidents. Hence, design consultant bears the responsibility to the owner and the society for design quality, material specifications and functional performance in their design. Mr. Doan Ngoc Hoai Vinh made a case study which major objective was to study the Quality Management in Design Process, and in order to achieve this objective, three sub-objectives were needed to accomplish such as: (i) study the existing practices of design process and management in Phuoc Binh Apartment project; (ii) analyze the effectiveness of design process and management; and (iii) provide framework for design process.
Conclusion
Design process quality management is very important to make high-performance of design and construction services. However, there are a few design companies which apply quality management for the design process in Vietnam and there are many causes related to this problem.
1. They do
not have design quality awareness.
2. They work
by experience and habits
3. They
have limited capacity.
During a period
of construction boom when people has just known benefit, profit without regard the
quality of building. On the other hand, recently, the quality issues are always
considered a top priority by investors when they want to evaluate and select
the design consultants and construction contractors. Below are the conclusions
drawn from the three sub-objectives.
1. Existing
practices of design process
Quality management in the design process
that starts before a project even begins and touches all aspect of our
business/internal processes. Design process include: design planning, structure
and responsibility, design integration, conceptual design, preliminary design, detail
design, value engineering, design review, design verification and validation, design
change control, bidding and negotiation, construction, and feedback data. The main benefit of this management is
reduced risk, better client satisfaction, advancements in knowledge and ways of
doing things, better-educated staff, and better projects in technical and design
sense. Disadvantages are small. This study gives a standardization of the
design process to encourage/remind designer to practice and also encourage the
senior staff to continue to advise the younger staff.
2. Effectiveness of design process and
management
This study provides an overview of quality management and the analysis
of specific existing design process quality management. Most of
the requirements of quality management have been covered and presented in the
existing system. However, the quality problems occur in most of design process that
caused main risk to owner such as schedule delay, extra cost, abortive works and generating V.O.
In order
to apply quality management in design process of project effectively, design
consultants need to define the factors that affect to the quality of the design
process and set quality as requirements to performance. And QM also depends on
the characteristics of different projects to build feedback and develop appropriately.
For example, requirements of apartment project are different from hotel
project. Additionally, design consultants need to pay attention to quality
perception. So, it is necessary to implement the internal quality audit and
provide training at different position. It helps to consolidate quality
perception in design team effectively.
Through above assessment and
analysis, the study established a framework of design process, where entire
project teams include: client, architects and consultants meet early to
establish the vision, goals, objectives, criteria, and process for successful
project.
Recommendation
- The ‘traditional’ outcome often dissatisfied clients, project budget and
schedule overruns, and completed projects that were not actually achieving the
results that the client had originally intended. There ‘had to be a better way’
as we embraced the new technology era. The firm began to record the processes
and tools, using information management systems to formalize tools, processes and
began a new model of working in a highly interactive and collaborative manner
with our clients.
- The firm developed a clear strategic vision and a strong organization
with embracing of quality improvement. The firm based on its direction should
align the design processes together through proper communication, sustainable
development and empowering the human resources of organization and concentrate
on creating nurturing corporate culture.
- Focus on quality people is that the firm do not hire when need help;
hire when find the very best people. The firm conducting interviews all year round
and when find a top quality person and hire him or her; adjust workload of staff
and not adjust staff to workload. The firm provides excellent working
conditions and environment, the latest computer equipment and software, flexible
work schedules, excellent benefits, fair pay.
His thesis abstract is copied and pasted below.
Abstract
- We probably do a lot more rework than we need to, but we do not know
because we do not measure it.
- Our designers never know when to stop designing, and it impacts on the
time to complete the project.
- Scope omission is a constant problem, and it is hard to get increasing
fees for it.
- We are expected to manage the project team, but our people are not very
good at keeping the project team on schedule.
These, and a lot of other situations that frustrate principals, are in fact
quality
problems in disguise.
The
research aims to study project quality management and improvement. The scope of
study was limited in design firm in Viet Nam . Cross literature was
reviewed and real case analysis was implemented in order to find out the
factors influencing on the quality issue and focus on the framework of quality
management in design process.
Recently, quality management has
been applied widely in construction projects. As we all know that it is
developed to manage the performance of design and construction activity. In Vietnam
nowadays, people pay more attention to the quality in building projects as well
as to meet client’s requirements as much as possible. Therefore, the objective
of quality management is not only to enhance the quality of construction
projects but also to raise the effect and productivity during construction
period. All of this aims to satisfy client’s needs, as a result.
The overall objective of
the research is to provide owner, project manager, designer, contractor with
information and practice knowledge which
could support them to handle the tasks and solve the problems more effectively
with their limited resources. All of this, as a result, will help to achieve
better quality outcomes.