According
to the Governmental Investment Project Assessment Report for the year 2009 by
Ho Chi Minh City People’s Committee, there are 1,177 projects completed until
end of the year 2009 (which are currently equal to 20% of 5,886 operational
projects in Ho Chi Minh City). However, 65% of the projects were delayed and 20
projects only achieved up to 30% of the target progress. This is due to the
following reasons:
(i)
Weak financial capacity of the project owners.
(ii)
Lack of experienced project managers and project management human resources.
(iii)
Long period for authority submission and lack of transparency of Vietnam law
and regulations.
(iv)
Land clearance and resettlement.
Bui
Quang Huy made a case study which main objective is to investigate the basic
requirements by Vietnam law and regulations, the common practice of housing
development projects in Vietnam complying with Vietnam law and regulations; and
to find out a more efficient process for developing a housing project in
Vietnam.
Conclusions
The
housing development industry has its own characteristics. Every single activity
in the project development process has to comply with local law and
regulations. Hence, the good understanding about local law and regulations is
very useful for developers in their business. The success of the case project
in this study also depends very much on the understanding about local law and
regulations beside the project management knowledge.
The
old practice of housing project development process complying with Vietnam law
and regulation is not efficient, it takes 60 – 78 months to finish the project
from the feasibility study and planning phase to handing over and obtaining the
ownerships for the house buyers. The longer the project development period is,
the more costly the investment in housing projects is. Besides, Vietnam
population and housing demand are developing very fast; the supply could not
satisfy the demand. Hence, the housing price could not be reduced and a major
part of people with low and medium income do not afford to buy houses. It
causes a lot of social issues in Vietnam.
With
the improved housing development process proposed, it takes 45 – 57 months to
finish the project. If we only consider the Project Launching Preparation
phase, the saving is 15 – 21months, it takes 12 -15 months in the improved
process instead of 27 - 36 months of the old process. This is a valuable improvement.
The investment in housing project becomes more efficient when the developers
can recycle their investment faster and cut down financial cost in housing
projects. It helps to increase the supply of housing products and reduce house
price.
Besides
the understanding about Vietnam market, the knowledge from lean production and
last planner theory also offers a basis for evaluating the whole development
process of housing projects and identify waste times in the process. The
project manager/ planner should examine and schedule the project with all
constituent and continuous activities as a whole. By implement that, it will
make the timing of whole project period more efficient, rather than only taking
care of shortening the period of its individual activities. The application of
lean theory is absolutely suitable for the current situation of Vietnam housing
market. It helps to shorten the project development period and make the process
more efficient by ignoring waste time. There are no additional costs to apply
these theories.
Recommendations
In
general, when the understanding about local law and regulations is very
important in housing project development, the developers should continuously
update and study local law and regulations, especially, the new issuances.
A
good relationship with government also helps developers in their submission
works. This relationship could be created by contributing to society and
maintaining the good image in the local market, the developers should properly
deliver what they committed to the government and buyers.
The
developers are recommended to maintain their efforts in evaluating the working
and project development process to find any problems for improvement, not only
waste of time, but also any other wastes such as cost, manpower, etc.
Lastly,
the good schedule should never achieve the good actual result if it is not well
controlled. The control system also needs to be established to monitor the
execution of the project to ensure it is carried out in accordance with the
plan.
ABSTRACT
Vietnam
is a developing country which means that the country need a lot of knowledge
for development, especially in the field of construction project management.
Some
“old men” think that all the construction projects are similar, about the
process, technology and method, especially housing development projects. They
are actually not similar, there are many projects carried out in such a way of
wasting time and cost; and achieving bad quality.
In
this study, a more efficient process for housing development project is
introduced. Hopefully, it could help the project managers / planners schedule
and execute their projects strictly complying with the local law and regulations,
in shorter cycle without any additional costs for advanced technology and
materials.
This
study also affirms that there is always un-efficiency in project development
process of every construction projects. The project managers should always spend
enough efforts to identify wastes and improve them. This is helping the
projects, the company and the country, in a wider angle of view.