Completion of construction project within given time, cost, quality and
material specification has become major issues in construction industry. The
typical problem that the construction industry has been always victim of is
project delay and cost overrun dispute (Kaliba et al., 2009). Owner budget, and
schedule constrain, design engineering’s design and preparation of contract
document without deep-rooted understanding of construction method and the
contractors who often builds without appreciation of design principles or
consulting the design engineering are the main reasons that cause disputes
among these different parties that are involved in a construction project
(Bedian, 2004). This dispute is the root cause for the project delay and cost
overrun. In such condition most of the time quality has to be scarified in
order to save time and cost. So to avoid such critical situation there is a
need of key creative ideas that can reduce the project life cycle cost without
lowering quality or function of the product. The creative idea is known as Value
Engineering (Dell’s Isola, 1988). Foo and Chong (2002) have given some
beneficial structure on the application of VE. This concept has been
implemented successfully in various developed countries across the globe and it
has been successfully proven that construction industry can be benefited by the
application of the VE concept.
From preliminary
investigation, it was found that Nepalese building construction industry is
also suffering from the problems mentioned above. In most cases, local
contractors have not been able to deliver projects on time and sometimes not up
to the required quality standard (Bhattarai, 1996). They still follow the old
construction technology and methods.
The problems that Nepalese construction industries are facing from the
past many years are as follows:
(i) Delay in project, revise and cost overrun
due to lack of supervision and coordination.
(ii) Outdated
standard and poor technology method used for preparing and conducting all job
in site.
(iii) Lack of developing and maintaining construction
schedules and incomplete drawings and terms and condition.
(iv) Lack of funding directly affecting in productivity and
quality of work.
(v) Lack of effective communication which causes conflicts.
(vi) Lack of expertise which leads to dissatisfied customers
and a negative reputation of the industry.
(vii) Unsatisfied customers due to poor quality service and
delay in work
Therefore it is important to search for VE applications in Nepalese
construction industry.
Ms. Shreena Malla made as case study to understand the concept of
Value engineering that is required throughout the construction process. The
major objectives of her study were to:
- develop a
Value Engineering application methodology in building construction
projects by using 6 value job plans.
- identify
the cost overrun itemsin building constructions projects and apply the VE methodology
to reduce the cost of the project.
- propose recommendation and suggestion.
Conclusion
Nepal is a developing country, where construction industry
is just booming. Even though construction is booming, people involved in this
industry are still following the traditional construction technology. People
are still unaware of the high and advance technologies that have been already
adopted by other developing countries. The typical problems that Nepalese
construction industry has been facing for years are project delay and cost
overrun. Lack of key creative ideas, out-dated standards and poor construction
technology, communication gap among project team members are the major
drawbacks that cause project delay and cost overrun. So the main objective of
this research was to apply value engineering in Nepalese construction industry
in order to omit those weaknesses.
Value engineering is a methodology that helps to reduce
project cost by generating value alternatives. So here in this research also
value engineering methodology was applied in both cases throughout the
research. First the VE methodology (6 job plans) developed in chapter 3 was
verified from the professionals which was the first objective of this study
then each step that this method consists was applied in detail. Before applying
those steps the cost overrun items were identified with the help of
professionals. Value engineering 6 job plans was then applied on those items in
order to test the VE application, which was second and the core objective of
this study. After purposing VE, it was found that the project cost was reduced
by 7% and 14% in case 1 and 2 respectively.
1. The key
findings of the research
In Nepalese construction industry, it was found that people
always try to find the low price materials without considering the quality in order
to save the project cost. Sometimes they even adopt poor construction
technology to complete the projects within given time frame. But they don't
think about the future consequences that might cause bigger problems than they
have expected. As a result they always have to suffer from reworks leading the
project towards delay, which is the main cause of cost overrun. Due to delay
and cost overrun, clients are found disappointed with contractors. So, this
research was done to omit these typical problems seen in Nepalese construction
industry.
After the detailed
research, it is found that value engineering is quite beneficial for a
developing country like Nepal where people are suffering from project delay and
cost overrun due to lack of key ideas and poor construction methods. This
method proved that it has a high potential for bringing a new change in
Nepalese construction industry as it will help them to identify the problem
areas and also provide ideas to solve them. This new method will help Nepalese
contractors to bring quality in work and also to enhance their credibility. It
will not only enhance the contractor's credibility but will also enhance the
relationship between owners and contractors.
Other key findings observed during the research were as
follows:
(i) Lack of Incentive clause in contract document.
(ii) Lack of VE re-proposal clause in contract document.
(iii) Project delivery system is usually based on unit
price, where all scope of works and items are already fixed by clients.
(iv) Designers are not ready to change the design or
materials once contract is awarded.
(v) Not applicable for Government project since the overhead
cost is fixed.
(vi) More appropriate for relation based contract.
(i) Research was done on construction
phase projects.
(ii) Only contractors were
involved.
(iii) Research was done on BOQ
items only.
(iv) Only building construction
projects were considered for this research.
A. Recommendation as per the Research
(i) Incentive clause for VE
re-proposal should be included in contract document.
(ii) Commitment from top
management level
(iii) Highly experiences people
to form a VE tem
(iv)Sufficient time to apply VE (
depending upon project size)
(v) Open communication among
client, consultant and contractor
(vi) Complete design should be
provided to the contractors to avoid reworks, wastage of materials, labor
overhead cost and schedule overrun.
B. Recommendation for further Studies
(i) Conduction study from design
phase to construction phase.
(ii) Only construction companies
shouldn't be focused for the research.
(iii) Incorporate all the parties
involved in the project (Contractor, Owner, an Designer).
(iv) Conducting qualitative study
(v) This study can be further
extended to all type of construction projects such as road, bridge etc.
Her thesis abstract is copied below.
Abstract
Construction industry is considered as economic activities
that play essential role in accomplishing socio economic goals of any country.
But the construction industry of Nepal has shown a continuous decline since
last few years. The industry has become noticeably wasteful, unproductive,
ineffective, and adversarial. The typical problems that this industry has been
facing for years are poor performance, project delay and cost overrun. Lack of
key creative ideas, out-dated standards and poor construction technology,
communication gap among project team members are the major drawbacks that leads
the project towards delay and cost overrun. To overcome such critical problems,
value engineering has been introduced as a tool for cost reduction within
construction industry in a developing country like Nepal. It is a proven method
that has been already applied in various developed and developing countries.
This is a technique that not only reduces project cost but also enhances the
quality of the project. So this dissertation presents the essential fundamental
of Value Engineering and its different phases that have been applied in
projects to reduce the cost without compromising quality. This research
discusses about building construction projects in which construction materials
of the project are changed according to Value engineering methodology. The
alternatives of those materials are chosen such that the cost is reduced
without affecting the value of the project. Since the main objective of this
research is to investigate the opportunity of VE application in the
construction industry of Nepal, the VE methodology (6 Job Plans), after being
verified from seven experts was applied for collecting data from Nepal. During
the data collection process, cost overrun items are identified through face to
face interview and then VE methodology is applied on these items. Then detail
analysis of both chases has been done to investigate the opportunity of value
engineering application in construction phase.
After detail analysis, it was found that this concept is
very much new in Nepal but quite beneficial for the people involved in this
industry. This investigation finding reflects that this concept has high potential to reduce the
project cost, but in order to apply this method commitment from top management
level is required first and then highly experienced people to form a VE team.
Keywords: Value
Engineering, Cost reduction, Nepalese construction industry, BOQ, VE Job plans,
Value alternative.
4 comments:
VALUE ENGINEERING IN CONSTRUCTION
Agencies are encouraged to apply VE techniques to all projects including bus maintenance and storage facilities whose construction costs are estimated to exceed $2 million. The objective of VE is to satisfy the required functions of the project at the lowest initial total cost and cost over the lifeof the project When to Perform Value…
to get more - https://myengineerings.com/value-engineering-in-construction/
Consult with a couple of companies and ask the questions you would like answered, so you'll make an informed decision concerning which company to rent .
concrete contractors syracuse ny
Value Analysis and Engineering - Examples by L.D. Miles - Part 1
Construction industry is considered as economic activities that play essential role in accomplishing socio economic goals of any country. But the construction industry of Nepal has shown a continuous decline since last few years. The industry has become noticeably wasteful, unproductive, ineffective, and adversarial. The typical problems that this industry has been facing for years are poor performance, project delay and cost overrun. Lack of key creative ideas, out-dated standards and poor construction technology, communication gap among project team members are the major drawbacks that leads the project towards delay and cost overrun. To overcome such critical problems, value engineering has been introduced as a tool for cost reduction within construction industry in a developing country like Nepal. It is a proven method that has been already applied in various developed and developing countries. This is a technique that not only reduces project cost but also enhances the quality of the project. So this dissertation presents the essential fundamental of Value Engineering and its different phases that have been applied in projects to reduce the cost without compromising quality. This research discusses about building construction projects in which construction materials of the project are changed according to Value engineering methodology. The alternatives of those materials are chosen such that the cost is reduced without affecting the value of the project. Since the main objective of this research is to investigate the opportunity of VE application in the construction industry of Nepal, the VE methodology (6 Job Plans), after being verified from seven experts was applied for collecting data from Nepal. During the data collection process, cost overrun items are identified through face to face interview and then VE methodology is applied on these items. Then detail analysis of both chases has been done to investigate the opportunity of value engineering application in construction phase.
Project Centers in India
IEEE projects for cse
Deep Learning Projects for Final Year
Post a Comment