For the past decades, construction firms have been facing
problems such as high cost pressure, shortened project time and increasing in
competition. Moreover, the construction industry in many parts of the world
suffers from problems such as workmanship defects, time and cost overrun
(Harrington et al., 2012). In addition, contractors are usually more inclined
toward the profit generation rather than quality improvements, especially if
they have already met the minimum requirements for quality (Low and Teo, 2004).
Clients are
demanding better quality because in many construction projects, clients often
find themselves paying high prices for defective works that do not satisfy
their needs (Low and Sze, 2005). The cost of defect and damage can be minimized
by a proper preventive tool instead of the corrective action. Moreover, Ilozor
et al. (2004) pointed out that some defects caused several other defects and
preventing those defects could eliminate many other defects.
Ms. Kobdao Maneejak made a case study aimed to:
1. Investigate and
classify root cause of defects.
2. Study the behavior
of defects during the architectural stage.
3. Develop
preventive measure tool to minimize defects.
With the complexity of construction methods, high quality of
end product and involvement of many trades, defects are found when moving from
architectural and M/E to end products. In order to minimize defects, site
managers have to understand the behaviors originated defects both activities within
and across the work package. The findings indicated that defects in residential
building construction in Thailand caused from pressure to rush the product to
market.
This chapter summarizes the results in brief of three case
studies. The identified defects from three project case studies were
investigated the root causes and the defect behaviors during architectural
stage to end products in residential building.
Conclusion
Twenty-eight (28) work activities under 7 work groups from
architectural stage to end products were listed to investigate the root cause
of defects. Main root causes of defects were identified by site managers
including project engineers, site engineers and foremen. Four main root causes
of defects are design, workmanship, materials and lack of protection. Once the
root causes of defects were investigated, site managers identified each defect,
its causation and its root cause. All identified defects were registered with
photographs and short noted. For in-depth discoveries, site document were
scrutinized. From data collection, defects were found in all work groups: wall,
floor finishing, wall finishing, ceiling, painting, sanitary and M&E.
Workmanship and lack of protection were found to be two most
critical factors causing defects during architectural stage. Defects which
caused by workmanship were under the following work groups: wall, wall
finishing, floor finishing, ceiling, painting, sanitary and M&E. Defects
were also found during the finishing stage. Floor finishing, wall finishing and
sanitary were the most three common work groups where the defects were
identified by site managers. Moreover, defects originated by materials such as
using wrong equipment/tools or defective materials were found under these work
groups, wall element, ceiling and sanitary wares.
During an investigation, the relationship among defect,
rework and damage were observed. Three types of defects, based on the level of
correction, were derived; corrective defect, rework defect and corrective
defect. Corrective defect needs only a minor correction while rework defect
needs a rework process. The corrective actions of defects are negotiated
between an owner inspector and a contractor to either perform minor correction
or rework. Another type of defect is damage defect. Damage defect is defined as
once a defect occurs and it is either corrected or reworked, it affects the
element which is not related to correction, or rework activities.
After in-depth analysis of defects, corrective defect and
rework defect were commonly found at sites. Majority of corrective defects were
generated from ceiling, painting and M&E work group. Masonry work, wall
tiling, in-wall M&E installation were the critical activities causing rework
defects. Also, M&E installation in ceiling was often found as the rework
defect causation. However, for damage rework, only few items were found during
data collection. From case study, wrong sequencing activity and poor protection
were the main cause of damage rework.
Recommendation
Moreover, it was found that most defects were repetitive.
Their occurring behaviors were quite the same. Activity sequencing was used to
capture and understand defect behaviors. Wall plastering was found to be the
most critical in generating or hiding defects. Strict measures of quality
assurance must be designed and applied in this bottleneck activity including
critical point inspection, agreement on area transfer between trades, and
protection of easily damaged products. Wrong activity sequencing occurs when
many subcontractors from different trades are performing works in sequences.
Without proper crew balance based on synchronized production rate, immediate
succeeding activity will move pass its predecessor causing many subsequent
defects.
Site managers should develop the schedule which concurrently
involves only 2-3 trades at maximum to reduce the number of work package
contractors/subcontractor so that complexity and interdependency can be reduced
and defects can be easily detected. Moreover,
each work package contractor/subcontractor before commencing their work has to
agree that there will be a zero defect and provide protection to their finished
work upon leaving their work areas.
In conclusion, critical quality inspection is the most
essential measure to minimize the occurrence of defects. After the transferring
of structural stage to architectural stage, zoning the work area by using
different shades of color, green, yellow and red, is recommend to minimize the
possible damage defect. Only workers who wear the color-matched armbands are
allowed to the work area. For green zone, all work activities under
architectural stage can be performed and all workers can enter the green zone.
After all works are performed, protection is needed. For yellow zone, only
carpenters and furniture crews can enter the work area, before start working,
both crews have to accept that the work area has zero defects. For red zone,
anyone who needs to enter the work area has to get permission from site
engineers to get into the work area; critical inspection is checked both before
commencing the work and after the completion of the work every single day.
Moreover, both yellow and red zones required all workers taking off their shoes
before entering the work area.
Her thesis abstract is copied below.
Abstract
This
paper identifies and presents findings derived from in-depth investigation of
work behaviors causing defects during architectural and finishing stage of
residential building construction.
High-rise building construction projects were investigated. Data were collected
by structured interviews of on-site managers, direct observations of work
activities, and quality inspection records. Activity sequencing, quality
inspection, and correction of defects were analyzed. When a project team force for progress toward
the finishing stage, defects are commonly found because wrong activity sequencing,
especially when architectural and M/E activities are interfaced. Perceiving
that surface finishing can cover up prior defects, improper quality inspection
on preparatory works occurs mostly in surface finishing activities. The
work sequence and nature of defects are applicable in residential building
construction in Thailand where prefabricated components are not much used,
except exterior facade. The study result can be applied to improve planning and
quality assurance system for defect reduction.
2 comments:
nice article and got to know why the quality of construction materials in bangalore is weaker nowadays
The article reflects the reason and truth of the weakness on constrution materials
Post a Comment