The Ministry of Construction in Vietnam
has issued new codes and standards in order to improve the quality and safety of
the project and address the high requirement and concerns from the clients. However, some high-rise building projects for resettlement are
doubted having quality problems during construction
phase and after putting into operation. These projects might have various
defects but the main factor causing quality problems is quality management
system of the company. 
Mr. Hua Van Hung made a study aimed to:
1. study the Owner’s project quality management practices
from literature view
2.
study the Owner’s project quality management practices in bored piles part of
high rise building project for resettlement of people relocated. 
3.
develop Owner’s project management strategy framework for this part of high
rise building project for resettlement of people relocated
4.
discuss strengths and weaknesses 
5.
propose recommendations
6.
develop a Quality Management System framework. 
Conclusion 
The
Owner’s Quality Management System is responsible in managing the implementation
of the quality management system of the Contractors’ construction works. Aside
from the financial, scheduling planning and all contractual requirements at
optimum cost and time, it is also responsible to oversee that the project meets
the quality requirements. 
In
order to achieve it, the Owner should think the term Quality Management System
(QMS) and refers collectively to the series of inter-related processes intended
to manage the planning, design and construction activities necessary to deliver
projects. The QMS serves as the vehicle to communicate and ensure to understand
the contractual requirements and the process to be followed for successful
project delivery. 
First,
the Owner’s Quality Management System should be established and the top
management has to be committed. The Project Manager shall organize the project
team and ensure that qualified and experienced staff is appointed for each
position with clear responsibilities. 
Secondly,
procurement in construction has been developed for selection of contractors and
suppliers, which are handled under close coordination with project engineer, in
order to produce effective results from the project’s technical and management
stand-point. 
Thirdly,
the project team is responsible for ensuring that the construction project
performed meets the requirements established by the owner and also responsible
for preparing the quality assurance manual together with quality control
standards, and ensuring continuous monitoring and inspection is being performed
by the QA/QC officers to guarantee that the QA/QC standards, procedures and
tests are implemented throughout the project construction.
Lastly,
the Quality Management System should regularly improve and review the
effectiveness of the system. 
In
this project case, a part of bored piles construction of high rise building was
an option, because this structure becomes popular in construction nowadays. The
Quality Management System from the Owner’s project in the construction phase
has been anatomized and pointed some strengths and weaknesses of the existing
system. Moreover, the effort from this existing system has been discussed and
improved project quality via this case study project. In order to reduce some
problems in project’s quality, the Project Management team has made a decision
to strengthen and increase the efficiency of Quality Assurance (QA) and Quality
Control (QC) programs, speed up and increase the efficiency of supervision work
from Consultant, improve health and safety measures and record all
non-conformance products. Due to some impacts and reasons, activities from
improvement are not efficiently enough. As a result, the frequency of problems
in quality is not completely reduced.
The
author proposed some solutions for improving the efficiency of Quality
Management System, and also proposed frameworks to help the Owner in solving
problems and managing the quality project during the construction phase. In conclusion,
this proposed framework, if effectively implemented would generate not only in
this case project but also for the other project for all parties in the
construction industry. 
However,
due to time constraint, this report only discussed the information relating to
the Owner’s quality management system in the construction phase. In addition,
there are remaining of quality management system in design and tendering phase,
two phases are considered an important roles to the project quality.   
Recommendations
·     In order to ensure the efficiency of
the Quality Management System, define clearly the responsibilities and
designate appropriate members of the project team. When the member of the
project team and their sub-consultants are competent and has teamwork, chances of
quality are greatly increased. 
·    Company quality manual would normally
be produced by head office and authorized by the Chief Executive. It should set
out the policy, organization and rules to implement company quality policy 
·    Manufacturers’ and suppliers’
literature and instruction in procurement of construction should be developed
and improved. Specifications often contain the requirement “to be fixed
strictly in accordance with the manufactures’ instruction”. It follows, therefore,
that these instructions become part of the contractual requirements, so when
starting a project make sure that all such manufactures or supplier information
is available on site. 
·     Let the Contractor always understand
that work performance has met in accordance with programs. Plan is a must. 
·    Project Communication on a construction
site must take place at all levels for a variety of reasons. All meetings
involving the Contractor should be accurately informed for future references.
Clear communication information such as requirements, expectations, scope,
cost, schedules and technical data are vital elements in producing quality in
constructed project.
·    One of the very basic requirements of a
quality construction program is that the construction site must be kept clean.
Materials and equipments must be neatly stored for future use. The reason is
very simple. If a person comes to work and the workplace is disorganized, it will
be difficult for him to believe that quality work is really a priority. The
result is that an undesirable attitude would already be established for lack of
quality. Conversely, if the worker arrives at the site that is clean, neat and
orderly, a quality image is set. The worker can perform his tasks without
interference. And lastly, in addition to the site cleanliness, another basic
criterion on any quality construction program would be site safety, and this
safety practices must be followed during construction.   
His
thesis abstract is copied and posted.
Abstract
Construction
activities is an important factor that contribute to gross domestic product
(GDP) in most industrialized and developing countries contributes significantly
to universal economic growth (Walsh and Sawhney, 2002). With growing
commercialization of human activities, construction industry has been a major
commercial activity. Stakes (capital investment) became high as technology
advanced. Huge construction projects have been common. Large roads and rails
system are taken up. Huge urban centers have been sprung up. Increasingly more
and more people are getting engaged in construction and allied industries all
over the world. 
Unlike
the construction sector, it is well-known precept that the manufacturing
industry has notably well-instituted quality systems. This is due to the
differing nature of the two-sectors. Manufacturing calls for repeat process
with products primary put out in large batches. On the other hand, construction
activities is undertaken in the main in single batches or projects (i.e. one
building, one bridge, etc.). Although many of basic processes are repeated from
job to job (e.g. concreting and plastering), the specifics of application are
always changing. However, this is not to say that management systems, which
have worked well in the manufacturing industry, cannot be applied to
construction. Explains the rationale for project performances in construction
phase, and then discusses the proposed solutions on how to get better
performance for any cases especially bored piles part of high rise building project
for resettlement for relocated people. 
Quality is one of the critical
factors in the success of construction projects. Quality of construction, as
well as project success, can be considered as the fulfillment of expectations
of the project participants. The construction sector in Vietnam has been
struggling with quality issues for many years. 
Regarding to the practice process,
this report has also built the quality management system framework to serve as
a management tool for developing next projects. 
 
1 comment:
Super post. I've been thinking about this topic.
Post is very informative and all the points are very easy to understand. ERP software is must needed for our business. Eresource provides process manufacturing solution that covers complete range of services ranging from supply of raw material, production, manufacturing and packing. Process Manufacturing ERP Software helps the Decision makers to manage the business with a click of their mouse's button.
Thanks for sharing such a nice post...
Post a Comment