THE DELAY FACTORS DURING
CONSTRUCTION PHASE OF
A RESIDENTIAL PROJECT IN BINH
DUONG, VIET NAM
CASE STUDY OF AN DIEN
URBANIZED RESIDENTIAL COMMERCIAL ZONE
By
Bui Viet Thi
Abstract
A project is considered to be perfectly
performed when it obtains three basic criteria such as completing on time
within the planned budget, ensures the required quality such as winning the
customer’s demands and meets labor safety requirements successfully in the
performance stage. However, all the residential zones built in Viet Nam
have had problems of project management leading to construction delays. Giving
solutions for these problems has become project manager’s integral
requirements.
Delays in construction projects are able to be solved. In striving
to give solutions for these problems, the significant factors influencing badly
construction duration should soon be found out. Therefore, it is very critical
to form a systematical approach that should be applied as a device for the
investigation.
This report will evaluate and analyze twenty factors
which caused delay matters at Residential Zones and were fulfilled at Ben Cat
District Binh
Duong Province .
The qualitative methods will be used, basically based on the principal of
evaluating the risk level of factors having a negative influence on the
construction schedule of the Residential Zone. It is conducted to realize the
objective of the study.
Finally, some solutions to deal with delay
problems in the construction duration of projects are given in the text.
Executive summary
Rationale of research
This research has been conducted to identify factors causing
delay in construction projects during construction phase.
Objectives of study
To study and analyze delay happening in
residential area An Dien
Commune, Ben Cat District, Binh Duong province. Recommend strategies for
improving project delivery.
Methodology
Case
study approach is considered a major philosophy. In addition, many sources of
data will be collected in this study and project reports, documents from local
authorities and related agencies, construction standards, and exploratory
approach by reviewing available literature to deploy the research of
construction delays at Binh Duong and Viet Nam.
Findings and conclusion
By analyzing factors to
affect delay in the project, this research showed the problems causing delays
in construction stages. This research has identified that delays of the
projects were originated from survey stage till construction one. From these
result, most delays have generated from
the project owner who is responsible for inexcusable and excusable delays with
some compensability and non-compensability.
In this project, the owner committed some
mistakes in blown-off leveling process due to improper planning and slowness
decisions given. Then, the owner lacks of qualification and experiences to
nominate main contractor, suppliers and Tender Prequalification consultants, to
draft Specification resulting in disagreements amongst sub-contractors and fraudulent
tender occurring. Also, to deal with uprising problems related to surrounded
inhabitants and environmental protection, the owner was not activated and
flexible in those eventualities, failed to avoid disputes happening.
In case of the study, the project
has 20 factors causing delays in the construction process of An Dien
Residential Zone. Delay related to accident of labor safety is so serious,
delay related to material delivery is mean effect, and delay related to
break-down of machineries and equipments had smallest impacts to the project.
Suggest
for future research
The research has analyzed the factor of delays,
reason / severity rate and solution for each cause of delay problem in this construction
project. Hence, the similar study can be realized in different type of project
such as: Apartment- zone, Resettlement project, etc… in Viet Nam .