MANAGEMENT OF DIAPHRAGM WALL CONSTRUCTION
AFFECTING
ADJACENT BUILDINGS
A
CASE STUDY OF CONSTRUCTION PROJECT
IN
HO CHI MINH CITY, VIETNAM
By
Huynh
Thanh Quang
Abstract
In Vietnam was, is and will
construct several buildings with basements. The construction of the
basement in the soft ground in urban areas is more difficult and risky. There
have been many successes but also happened to shame. There are many causes affecting
the displacement of the structure and the land around the pit with and without
adjacent works. Due to the urgent problem is mentioned so many studies
summarizing the experience in the design and construction of over. This project report studied about
risk management of basement construction affecting adjacent buildings.
We can
only avoid the risks have clearly defined the cause risks to be proactive
prevention measures in quality control work is to manage every stage of
investment preparation, performance investment and exploitation. To limit risks in this
problem, we must to risk identification and solving methods of risk
in preparing and constructing stage of diaphragm wall and basements. Although
many projects have quality management system, but risk still occurs, and even
causing very severe damages for surrounding building.
Therefore,
risk identification is the problem very important in quality management system
of the project.
Executive
summary
Rationale of research
This research has been conducted to identify risk in construction of Diaphragm
wall.
Objectives of study
To identify the risk factors
involving construction of Diaphragm wall and its effects on surrounding
buildings and to propose recommendations to
reduce its effect on surrounding buildings.
Methodology
The
exploratory research method is used to study Diaphragm wall construction process by
analyzing case of a building construction project Ho Chi Min City Vietnam.
Findings and conclusion
We can only avoid risks when we identified the cause
of risk clearly and made a proactive and preventive measure in project quality
management. So, the cause analysis of incident, technical error should be
considered large study range in the development strategy of science and
technology. Practice shows that many building was caused incidents in execution
process of basement, it create severe impact such as structure damages,
non-uniform settlement, collapse, casualties etc, some of the problems happened
at site are as flows.
·
Damages
to the adjacent buildings due to movement of machines and vibration caused by
execution of diaphragm wall and bored piles, it will bad impact on the adjacent
buildings.
·
Increasingly
local deformation of the diaphragm walls made surrounding soil deformed.
·
Defect
on the diaphragm wall have occurred pierced holes at basement.
We can
see the above reasons are due to less experience of managers. Besides, the
investor and relevant parties does not expected budget for risks. If the
funding to solving of risks have not or not enough, plans for risk management
will be limited and not efficient.
Recommendations |
Limit
and control of incident are a very complicated task; it requires high level
experienced experts and responsibility before the work. Before design and
building construction, the consultant must be to investigate the surrounding
building thorough, to clarify the position, the status of the building,
underground structure, roads, underground pipes, etc, currently in incidence,
and estimated affect about adjacent building due to pumping lower ground water
level and basement excavation. The contractor must be proposed method to
prevent, control, observation and deal with urgent incidents when they happen.
The
risks might cause severe incidents (Defect on diaphragm wall (pierced holes),
deformation of shoring and king-post system, settlement of adjacent building,
displacement of diaphragm wall, etc), there solving problem when it happened is
quick enough and thoroughly. They must have plans to deal with urgent incidents
and to focus on manpower, equipment and finance to solving risks. Besides, when
incident happen they must to displacement and settlement observation for the
building and adjacent building. Moreover, they should be study geologic
conditions inside and outside the building, this problem is also very important
in during process of observing and solving incidents, even solution to move
people exit dangerous area when incidents happen.
1 comment:
Diaphragm walls are commonly used in congested areas for retention systems and permanent foundation walls. They can be installed in close proximity to existing structures with minimal loss of support to existing foundations. In addition, construction dewatering is not required, so there is no associated subsidence.