PROJECT
DELAYS IN CONSTRUCTION TAXIWAY S1
IN
NOI BAI INTERNATIONAL AIRPORT
By
Nguyen Xuan Thang
Abstract
Construction
mismanagement results in multiple problems that can cascade throughout the work
force chain, affecting the schedule and leading to damages to multiple parties.
Although the problem may start with a single subcontractor, it can result in
all contractors feeling some impact to their work.
The actual
delays causation occur in all kind of activities, but mostly in technical and
management mistakes. The most important part comes from information,
documentation and staff management. The impact from details engineering and
purchasing materials are mainly related from the mismanagement of this process.
The
construction schedule updating and forecasting can handle the uncertainty
associated with quantifying activity delays and their impacts. The conditions
in the schedule, that they are able to react and take the appropriate
corrective measures to avoid and minimize delays.
The
construction firms and the contractors need to feel in the same rhythm of their
project. Especially in large and sophisticate project, our desire to complete
the works on time and within budget is hard to fulfill. We can only achieve
this goal if we have the experience, competence staff and numerous resources,
strong financial aspects, and most of all we use it reasonable.
Executive summary
Rationale of research
This research has been conducted to identify the causes of delay
in airport construction projects.
Objectives of study
To identify factors involved in delay in construction of airport
projects completed and which are under construction and to develop a frame work
for remaining or under construction projects of airports.
Methodology
The exploratory research method is used for literature review,
to study and analyze project management of taxiway S1 in Noi
Bai international airport in terms of strengths & weakness and to propose
recommendations.
Findings and conclusion
The problem
of delay time in the project construction of aviation infrastructure in Viet Nam is a serious problem. The results of this
study provide a framework for project management can better understand the
dynamics of project management and implementation of efforts to reduce incidences
of delay time.
It was found
that there are some important factors affecting the project time in
implementing to build aviation infrastructure project. Completion time of any
project is effected by the factors: Namely policy, budget, human source and materials.
Recommendations
In order to consider improving schedule of transport
construction project, five
policies having the most potential were evaluated. The result showed that delay
can be reduced by carrying out several important policies during the construction
phase including:
·
Design
accuracy
·
Budget
·
Bidding document
·
Fluctuation and scarcity of material
·
Quality contractor (design, construction,
consultant).
For future
research:
·
Expand the model boundary assumptions to
include other project stage, may comprise of design stage, bidder stage and
deeper involvement of other parties.
·
Incorporate of deeper related with governmental
institutions such as policies of government and inconsistencies in laws and
aviation authority regulations.
·
Base on
measurement, we can find out the good way to manage and finish the project on
time, avoid the mistakes that it is occurring in the construction of transport
infrastructure in Viet Nam.