MANAGEMENT IN HIGH RISK BASEMENT CONSTRUCTION
A
CASE STUDY OF CONSTRUCTION PROJECT
IN
HA NOI CITY, VIETNAM
By
Tran Xuan Canh
Abstract
In civil and industrial
construction, the deep basement construction now contains so many risks and
difficult and complicated works.
To minimize the risks can be
happened during deep basement construction; we should fully and clearly
research the hidden risks for this work as well as give out the suitable
solutions and how to apply those solutions during construction and to reduce
the disadvantages of those risks to the minimum.
A full and exact research on
risks and the method to manage the risks and also the project management during
the deep basement construction is very necessary and urgent.
This project report studied about
project management in high risk basement construction.
Executive summary
Rationale of research 
This research has been conducted to identify risk in basement
construction of high rise building. 
Objectives of study
To study project planning and control to
understand risk in Royal city Project, Hanoi by studying strengths &
weaknesses in planning & control practices.
Propose framework for planning & Control in
basement construction for high rise.
Methodology                                             
The exploratory research method is used to study risk management
in basement construction and the current Vietnam regulations for quality
management in construction projects.
Findings and conclusion
To
obtain the best efficiency for the project and to minimize the possible damages
for the project and the neighboring buildings, we should have a suitable risk
management system (RMS) to implement in the project to ensure that the project
is operated in the best and safest way to gain full targets of the project:
Safety – Quality – Process - Efficiency.
The
deep Basement construction needs to be done by the Professional Contractor with
a full knowledge about the possible risks and there is a methodical and full
control system about this issue.
The
implementation of the risk management system (RMS) also requires Client and
Contractors to accept the necessary costs to maintain and to operate this
system. However, these costs are necessary and proper to ensure the safety for
the project.
Recommendations 
To
achieve the best effect of the risk management in the project, we should take
some steps:
For
Client
·        
Establishing
risk management system (RMS) for projects and ensure the system is properly implemented.
·        
For
collecting data of the contractor, requesting Contractors to submit the risk
management system/policy comply with the requirements, conditions of Client for
the project in the file bid. Client should collect the contractor that has
enough ability to implement the project.
·        
While
checking RMS of client & contractor there is need of third party throughout
implementation to check both.
·        
Need
to have the insurance contracts for the project and related parties with
Insurance Company.
For
Contractor
·        
Establishing
the RMS with the most suitable policies, strategies for the project and to well
comply with the requirements of Client and the legal regulations and the policy
of the company.
·        
There
is a serious combination with Client and related parties throughout the project
implementation to ensure the best maintenance of the risk management for the
project.
·        
Establishing
and using the suitable tools to manage the risk for the project in order to
analyze the reason of the incidents on site and to get the solution to avoid,
minimize the damages the most effectively.
·        
Using
Risk strategies effectively share the risk with third parties as the insurance
company or to require Client to be responsible for some risk of the project.
·        
Giving
out the detail classification for the risks may be occurred for the project,
defining the reason to give out the most suitable solution to avoid or minimize
the influences of the risks.
·        
Establishing
the most suitable and effective Risk Organization Chart for each project and
establishing the most effective plan.
·        
Establish
reward and penalty system to reduce the risk in project.
·        
Having
the most suitable Method Statement for the project to minimize the risks
·        
Developing
the human control with the suitable management measures to ensure that the
staffs are collected and used for the most effectively for the project,
·        
Have
to have the insurance contracts for workers, equipments of Contractor and third
party on site with Insurance Company.
 
2 comments:
thanks for explain the process of risk management system....
Business Analysis Courses
Thank you so much for giving us so much important info at here. Your way to introduce theory is nice. I got good management info. Keep uploading your article at here for the needed people.
http://www.eduberry.com/
Post a Comment