Wednesday, 1 February 2012


OWNER’S PROJECT SCHEDULING STRATEGY
A CASE STUDY OF
SHB - DA NANG F.C SPORTS AND TRAINING COMPLEX CENTER PROJECT 



by



Vuong Hoang Thang




Abstract

A successful construction project is the one that completion within destined time, budget and quality. Project scheduling and project scheduling management are very important parts of any project as they provide the project team, sponsor, and stakeholders a picture of the project’s status at any given time.
The Project schedule is the roadmap for how the project will be executed. A successful construction project is also meaning a successful project scheduling and it is executed in the boundaries schedule's creation.
This report review project scheduling and management theory, time management functions and delay risks address into scheduling management commonly applied in developed countries and developing countries and Vietnam.
The report study the scheduling and management strategy applied in a construction project in Danang city, Vietnam. From the study case, the report identifies and analyzes the practical application of project scheduling management functions and strategy. Then, reviews practices of the project scheduling management and suggest some improvements strategy can be applied

  



Executive summary 

Rationale of research

This research has been conducted to indentify scheduling problems and propose good project scheduling practice and strategy for the owner.

Objectives of study

To identify project delay and risks of project delay in construction stages, and approach to schedule creation to propose owners strategy for project scheduling management.

Methodology

The exploratory research method is used to study delay and understand factors that affect project scheduling management.
By undergoing into project case and practice implementing in scheduling management .
Findings and conclusion
The administration of schedule is the most significant concerns of project management for  project owner, as an investor, mainly concerned about the profitability of investment.
The project scheduling management is resulted from the frame of project management planning and related directly to time aspect in each project.
considering the review of project schedule management, analyzing the practice in Project of SHB-Danang Sports and Trainings Complex Center, 1st phase, a project sponsored by non-state owner resources. The learning from the study is that from the initial stage up to now this project is applied some project management tools and methods to manage cost, time, procurement, etc. And the same to other common projects in Vietnam the scheduling management and time management is always a big challenge to the Owner.
The Owner of project (SHB) wished of completion construction and moving the club into new centres at the end of September 2012 latest. The construction duration is planned maximum of 8,5 months from the earth works till completion the 1st phase. However, the actual performance is slow than schedule and now estimated delay about 5 months hopefully.
The project was traditional design bid and built, each participant team was working well at their responsibility and used computer tools to reduce risk.
But the major problems were in communication and decision making which caused delay and un-professional attitude from owner side.
The team got some unrealistic milestones but overall project management unit from owner side is weak.

Recommendations

To put project schedule on realistic channel owner should focus on following points
·         Set & manage Buffer in the timeframe and activities duration.
·         Reduce dependencies by applying tools and methods such as: WBS, OBS, CPM, LSM, PERT and delay risk management.
·         In the estimation of task / activities, should focus on the Critical path, LOB.
·         Develop communication and report mechanism with some tools such as EV, SV, in order to update and adjust baseline making decision of the Owner.
·         Set penalty/ award provision in the contract both to the contractor and the designer.
·         Put realistic milestones into the contract and general timeframe and bound to all the project's stakeholders (Owner, PMU, PMC, and contractor, and consultants, designer).

No comments: